ADA Transition Plan

Transition Plan for Public Buildings and Facilities

ADA Transition Plan Progress Tracking 1st Quarter, 2026

Updated 1/13/2026

There are a total of 377 projects identified in the ADA Transition Plan.

Tracking Status Code: Completed; In-Progress (anticipate completion in 3-6 months) or Planned in Future Funding Projects (e.g. CIP projects).

City-Wide metrics #3 Accessibility

This metric reflects the completed, in-progress or future funding counts for all projects in the ADA Transition Plan divided into the total (377).

  • Completed: 197 (52%)
  • In-Progress: 6 (2%)
  • Planned in Future Funding Projects: 174 (46%)

Departmental metrics #3 Accessibility for Administrative Departments

This metric is the total of all completed, in-progress or future funding counts for OCC, CH, OSC, Osh-Buy, and GOH divided into their total (89).

  • Completed: 42 (47%)
  • In-Progress: 0 (0%)
  • Planned in Future Funding Projects: 47 (53%)

Departmental metrics #3 Accessibility for Cultural and Recreation Departments

This metric is the total of all completed, in-progress or future funding counts for Parks, OPM and OPL divided into their total (239).

  • Completed: 127 (53%)
  • In-Progress: 6 (3%)
  • Planned in Future Funding Projects: 106 (44%)

Departmental metrics #3 Accessibility for the Fire Department

This metric is the total of all completed, in-progress or future funding counts for OFD divided into their total (17).

  • Completed: 12 (71%)
  • In-Progress: 0 (0%)
  • Planned in Future Funding Projects: 5 (29%)

Departmental metrics #3 Accessibility for the Police Department

This metric would be the total of all completed, in-progress or future funding counts for the Safety Building divided into their total (21).

  • Completed: 8 (38%)
  • In-Progress: 0 (0%)
  • Planned in Future Funding Projects: 13 (62%)

Departmental metrics #3 Accessibility for the Transportation Department

This metric is the total of all completed, in-progress or future funding counts for Transit divided into their total (11).

  • Completed: 8 (73%)
  • In-Progress: 0 (0%)
  • Planned in Future Funding Projects: 3 (27%)