HomeMy WebLinkAboutAl Dix Concrete Change Order 3 PW 17-06 TO: AL DIX CONCRETE, INC. CHANGE ORDER#3(FINAL)
401 GERTRUDE STREET DATE: March 28,2019
KAUKAUNA,WI 54130
Your present contract with the City of Oshkosh,Contract No. 17-06,awarded March 28, 2017, is hereby
amended and changed as follows:
NET INCREASE TO: SECTION I $22,719.83
SECTION I TOTALS
BID TOTAL $1,041,710.90 $1,041,710.90
CO#1 (N EAGLE ST) $82,939.65 $82,939.65
CO#2 $231,840.58 $231,840.58
PREVIOUS CONTRACT TOTAL $1,356,491.13 $1,356,491.13
CO#3 $22,719.83 $22,719.83
CONTRACT TOTAL $1,379,210.96 $1,379,210.96
CITY OF OSHKOSH
BY:
..4--)E-:(7-4C-it.
City Manager ‘
111)1171n‘
(-- i Al lit-Sda e)
City Clerk
4 prove nd accepted:
ontractor
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh,Wisconsin,
under the within Change Order.
�� �1i ,r
Comptroller
Approved as iilorm:
ev,
City Att
•
CONTRACT 17-06 CHANGE ORDER#3(FINAL)
SECTION I:
Work Unit A
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Removing curb and gutter, Linear
A-1110 complete as specified Feet 750.00 1,532.70 782.70 $5.00 $3,913.50
Removing concrete and
asphalt sidewalk and
driveway,complete as Square
A-1120 specified Feet 119,616.28 128,327.00 8,710.72 $1.10 $9,581.79
7"concrete pavement
removal and replacement,
including sawing,pavement
ties,integral curb and fine
grading,turf restoration,and
traffic control,complete as Square
A-1308 specified Yards 1,000.00 153.08 -846.92 $63.00 ($53,355.96)
8"concrete pavement
removal and replacement,
including sawing,pavement
ties, integral curb and fine
grading,turf restoration,and
traffic control,complete as Square
A-1318 specified Yards 1,200.00 1,968.95 768.95 $68.00 $52,288.60
8"concrete pavement HES
removal and replacement,
including sawing,pavement
ties, integral curb and fine
grading,turf restoration,and
traffic control,complete as Square
A-1319 specified Yards 500.00 315.77 -184.23 $71.00 ($13,080.33)
Adjust manholes and inlets,
A-1360 complete as specified Each 19.00 0.00 -19.00 $300.00 ($5,700.00)
Turf restoration,complete as Square
A-1370 specified Yards 1,078.00 324.83 -753.17 $8.00 ($6,025.36)
12"radius curb with 6"CABC
and grading,complete as Linear
A-1410 specified Feet 250.00 0.00 -250.00 $8.00 ($2,000.00)
18"curb and gutter,7"with 5"
CABC and grading,complete Linear
A-1420 as specified Feet 250.00 352.00 102.00 $25.00 $2,550.00
30"curb and gutter,7"with 5"
CABC and grading,complete Linear
A-1440 as specified Feet 500.00 1,078.70 578.70 $27.00 $15,624.90
Sidewalk curb,complete as Linear
A-1460 specified Feet 445.00 190.00 -255.00 $25.00 ($6,375.00)
4"concrete sidewalk with 3"
CABC and grading,complete Square
A-1500 as specified Feet 73,160.35 80,164.87 7,004.52 $3.70 $25,916.72
4"concrete sidewalk with 3"
CABC and grading,in
existing subdivisions, Square
A-1500A complete as specified Feet 18,000.00 18,175.20 175.20 $4.50 $788.40
4"concrete sidewalk with 3"
CABC and grading,water
department locations, Square
A-1502 complete as specified Feet 2,000.00 2,236.30 236.30 $7.00 $1,654.10
6"concrete sidewalk/
driveway/ramp with 3"CABC
and grading,complete as Square
A-1510 specified Feet 55,914.49 58,976.69 3,062.20 $4.00 $12,248.80
Page 1 of 6
CONTRACT 17-06 CHANGE ORDER#3(FINAL)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
6"concrete sidewalk/
driveway/ramp with 3"CABC
and grading,water
department locations, Square
A-1512 complete as specified Feet 1,000.00 1,312.50 312.50 $8.00 $2,500.00
8"concrete sidewalk/
driveway/ramp,with 3"CABC
and grading,complete as Square
A-1520 specified Feet 500.00 2,870.60 2,370.60 $8.00 $18,964.80
Curb ramp detectable
warning field(natural/non-
painted),complete as Square
A-1540 specified Feet 668.00 480.00 -188.00 $30.00 ($5,640.00)
No.4 reinforcing rods-
deformed,epoxy-coated, Linear
A-1550 complete as specified Feet 1,000.00 3,820.00 2,820.00 $1.10 $3,102.00
Drilled No.4 sidewalk tie bars
-deformed,epoxy-coated,
A-1560 complete as specified Each 10,240.00 7,621.00 -2,619.00 $4.00 ($10,476.00)
Cold weather covering
(sidewalk)-single visquine, Square
A-1580 complete as specified Feet 1,000.00 89.89 -910.11 $0.05 ($45.51)
Cold weather covering
(sidewalk)-double visquine, Square
A-1582 complete as specified Feet 1,000.00 84.66 -915.34 $0.05 ($45.77)
Cold weather covering
(sidewalk)-double visquine
with 6"hay,complete as Square
A-1584 specified Feet 500.00 0.00 -500.00 $0.05 ($25.00)
Up-charge for late season
concrete sidewalk,driveway,
or ramps,complete as Square
A-1590 specified Feet 500.00 1,662.81 1,162.81 $1.00 $1,162.81
Up-charge for late season
concrete pavement,complete Square
A-1591 as specified Yards 500.00 659.65 159.65 $5.00 $798.25
Sawing existing pavement, Linear
A-1700 complete as specified Feet 3,000.00 4,459.10 1,459.10 $3.50 $5,106.85
Profile saw cut concrete curb, Linear
A-1720 complete as specified Feet 150.00 4.00 -146.00 $40.00 ($5,840.00)
Re-grade existing gravel
driveways,complete as
A-1820 specified Tons 75.00 0.00 -75.00 $20.00 ($1,500.00)
4"asphaltic pavement with
10"CABC and grading, Square
A-1906 complete as specified Yards 1,155.00 904.43 -250.57 $45.00 ($11,275.65)
5"asphaltic surface with 6"
CABC and grading,complete Square
A-1915 as specified Yards 500.00 0.00 -500.00 $55.00 ($27,500.00)
2"asphaltic surface with 6"
CABC and grading,complete Square
A-1917 as specified Yards 100.00 13.20 -86.80 $45.00 ($3,906.00)
Page 2 of 6
CONTRACT 17-06 CHANGE ORDER#3(FINAL)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Remove and replace fence,
A-1999 complete as specified Each 2.00 0.00 -2.00 $300.00 ($600.00)
SECTION I-WORK UNIT A(BID ITEMS A-1110-A-1999)-SUBTOTAL: $156,201.52 ($153,390.58)
NET INCREASE TO A: $2,810.94
Work Unit B
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Removing curb and gutter; Linear
B-1110 complete as specified Feet 45.00 46.00 1.00 $5.00 $5.00
Removing concrete and
asphalt sidewalk and
driveway;complete as Square
B-1120 specified Feet 5,000.00 3,328.40 -1,671.60 $1.10 ($1,838.76)
Unclassified excavation
(sidewalk);complete as Cubic
B-1205 specified Yards 50.00 525.00 475.00 $20.00 $9,500.00
Adjust manholes and inlets;
B-1360 complete as specified Each 1.00 3.00 2.00 $300.00 $600.00
Turf restoration;complete as Square
B-1370 specified Yards 460.00 473.34 13.34 $8.00 $106.72
30"curb and gutter;7";with
5"CABC and grading; Linear
B-1440 complete as specified Feet 45.00 46.00 1.00 $27.00 $27.00
Sidewalk curb;complete as Linear
B-1460 specified Feet 25.00 39.00 14.00 $25.00 $350.00
4"concrete sidewalk with 3"
CABC and grading;complete Square
B-1500 as specified Feet 9,475.00 10,014.70 539.70 $4.50 $2,428.65
6"concrete sidewalk/
driveway/ramp with 3"CABC
and grading;complete as Square
B-1510 specified Feet 1,435.00 2,289.90 854.90 $5.00 $4,274.50
8"concrete sidewalk/
driveway/ramp(HES)with 3"
CABC and grading;complete Square
B-1524 as specified Feet 1,020.00 947.50 -72.50 $5.50 ($398.75)
Curb ramp detectable
warning field(natural/non-
painted);complete as Square
B-1540 specified Feet 16.00 24.00 8.00 $30.00 $240.00
Drilled No.4 sidewalk tie bars
-deformed;epoxy-coated;
B-1560 complete as specified Each 40.00 20.00 -20.00 $4.00 ($80.00)
Sawing existing pavement; Linear
B-1700 complete as specified Feet 750.00 917.50 167.50 $3.50 $586.25
4"asphaltic pavement LT
with 10"CABC and grading; Square
B-1906 complete as specified Yards 100.00 157.67 57.67 $45.00 $2,595.15
5"asphaltic surface MT with
6"CABC and grading; Square
B-1915 complete as specified Yards 508.00 492.78 -15.22 $55.00 ($837.10)
Page 3 of 6
CONTRACT 17-06 CHANGE ORDER#3(FINAL)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Furnish and install standard
storm sewer inlet manhole(4'
diameter);complete as Vertical
B-2213 specified Feet 3.50 3.50 $575.00
SECTION I-WORK UNIT B(BID ITEMS B-1110-B-2213)-SUBTOTAL: $20,713.27 ($3,154.61)
NET INCREASE TO B: $17,558.66
Work Unit C
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Removing concrete and
asphalt sidewalk and
driveway;complete as Square
C-1120 specified Feet 300.00 490.12 190.12 $1.10 $209.13
Unclassified excavation
(sidewalk);complete as Cubic
C-1205 specified Yards 100.00 0.00 -100.00 $20.00 ($2,000.00)
Crushed aggregate base
course;complete as
C-1340 specified Tons 200.00 0.00 -200.00 $15.00 ($3,000.00)
30"curb and gutter;7";with
5"CABC and grading; Linear
C-1440 complete as specified Feet 30.00 0.00 -30.00 $32.00 ($960.00)
4"concrete sidewalk with 3"
CABC and grading;complete Square
C-1500 as specified Feet 4,700.00 2,764.80 -1,935.20 $4.50 ($8,708.40)
6"concrete sidewalk/
driveway/ramp with 3"CABC
and grading;complete as Square
C-1510 specified Feet 200.00 3,090.00 2,890.00 $5.00 $14,450.00
Curb ramp detectable
warning field(natural/
non-painted);complete as Square
C-1540 specified Feet 24.00 16.00 -8.00 $30.00 ($240.00)
Sawing existing pavement; Linear
C-1700 complete as specified Feet 75.00 0.00 -75.00 $3.50 ($262.50)
4"asphaltic transition LT with
10"CABC and grading; Square
C-1911 complete as specified Yards 30.00 0.00 -30.00 $45.00 ($1,350.00)
SECTION I-WORK UNIT C(BID ITEMS C-1120-C-1911)-SUBTOTAL: $14,659.13 ($16,520.90)
NET DECREASE TO C: ($1,861.77)
SECTION I-ADDITIONAL WORK REQUIRED: CO#1 (WORK UNIT D-N EAGLE ST)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Removing curb and gutter; Linear
1-D-1110 complete as specified Feet 18.60 18.60 $5.00
Removing concrete and
asphalt sidewalk and
driveway;complete as Square
1-D-1120 specified Feet 225.00 225.00 $1.10
Page 4 of 6
CONTRACT 17-06 CHANGE ORDER#3(FINAL)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
8"concrete pavement
removal and replacement;
including sawing;pavement
ties;integral curb and fine
grading;turf restoration;and
traffic control;complete as Square
1-D-1318 specified Yards 1,064.10 1,064.10 $66.00
8"concrete pavement HES
removal and replacement;
including sawing;pavement
ties; integral curb and fine
grading;turf restoration;and
traffic control;complete as Square
1-D-1319 specified Yards 140.70 140.70 $69.00
Pavement ties;complete as
1-D-1350 specified Each 8.00 8.00 $7.00
30"curb and gutter,7";with
5"CABC and grading; Linear
1-D-1440 complete as specified Feet 18.60 18.60 $27.00
6"concrete sidewalk/
driveway/ramp with 3"CABC
and grading;complete as Square
1-D-1510 specified Feet 225.00 225.00 $4.00
Curb ramp detectable
warning field(natural/non-
painted);complete as Square
1-D-1540 specified Feet 8.00 8.00 $30.00
Drilled No.4 sidewalk tie bars
-deformed;epoxy-coated;
1-D-1560 complete as specified Each 4.00 4.00 $4.00
Sawing existing pavement full Linear
1-D-1710 depth;complete as specified Feet 21.10 21.10 $3.50
Base aggregate dense;3/4";
1-D-1800 complete as specified Tons 62.30 62.30 $14.00
SECTION I-(ADDITIONAL WORK REQUIRED: CO#1 ITEMS 1-D-1110-1-D-1800)-SUBTOTAL $0.00 $0.00
NET INCREASE TO D: $0.00
SECTION I-ADDITIONAL WORK REQUIRED: CO#2
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
8"concrete sidewalk/
driveway/ramp(HES)with 3"
CABC and grading;complete Square
2-A-1524 as specified Yards 557.50 557.50 $5.50
8"concrete pavement
removal and replacement;
including sawing;pavement
ties; integral curb and fine
grading;turf restoration;and
traffic control;complete as Linear
2-B-1318 specified Feet 16.67 16.67 $68.00
No.4 reinforcing rods-
deformed,epoxy-coated, Linear
2-C-1550 complete as specified Feet 1,000.00 1,000.00 $1.10
Page 5 of 6
CONTRACT 17-06 CHANGE ORDER#3(FINAL)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Drilled No.4 sidewalk tie bars
-deformed,epoxy-coated,
2-C-1560 complete as specified Each 4.00 4.00 $4.00
SECTION I-(ADDITIONAL WORK REQUIRED:CO#2 ITEMS 2-A-1524-2-C-1550)-SUBTOTAL $0.00 $0.00
NET INCREASE TO:CO#2 $0.00
SECTION I-ADDITIONAL WORK REQUIRED:CO#3
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE/N DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Pavement ties;complete as
3-A-1350 specified Each 0.00 468.00 468.00 $9.00 $4,212.00
SECTION I-(ADDITIONAL WORK REQUIRED: CO#3 ITEMS 3-A-1350-3-A-1524)-SUBTOTAL $4,212.00 $0.00
NET INCREASE TO:CO#3 $4,212.00
NET INCREASE TO A $2,810.94
NET INCREASE TO B $17,558.66
NET DECREASE TO C ($1,861.77)
NET INCREASE TO D $0.00
NET INCREASE TO ADDITIONAL WORK REQUIRED: $4,212.00
NET INCREASE TO CONTRACT: $22,719.83
Page 6 of 6