13961 1-j
TO: VINTON CONSTRUCTION COMPANY CHANGE ORDER#2 (REVISED)
P.O. BOX 1987 DATE: MAY 2,2019
MANITOWOC,WI 54221-1987
Your present contract with the City of Oshkosh, Contract No. 17-19,awarded July 25,2017, is hereby amended
and changed as follows:
NET INCREASE: $17,108.85
NET DECREASE: $0.00
NET INCREASE TO CONTRACT $17,108.85
TOTALS
BID TOTAL $1,598,113.98 $1,598,113.98
CO#1 $137,990.00 $137,990.00
PREVIOUS BID TOTAL $1,736,103.98 $1,736,103.98
CO#2 $17,108.85 $17,108.85
CONTRACT TOTAL $1,753,212.83 $1,753,212.83
CITY OF OSHKOSH
City Manager
City Clerk
Approve and accepted:
ontractor
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh,Wisconsin,
under the within Change Order.
. flrc tt'
Co ptroller
Approved 1sto form:
City A r
•
CONTRACT 17-19 CHANGE ORDER#2 FINAL(REVISED)
17-19
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
Clearing;complete as
1010 specified Stations 3.80 4.50 0.70 $986.00 $690.20
Grubbing; complete as
1020 specified Stations 3.80 4.50 0.70 $986.00 $690.20
Removing pavement; Square
1100 complete as specified Yards 790.00 667.70 -122.30 $2.50 ($305.75)
Removing concrete and
asphalt sidewalk and
driveway;complete as Square
1120 specified Feet 240.00 156.60 -83.40 $0.80 ($66.72)
Unclassified excavation; Cubic
1200 complete as specified Yards 219.00 149.90 -69.10 $16.50 ($1,140.15)
Restore gravel driveway/ Square
1372 apron;complete as specified Yards 150.00 516.00 366.00 $4.00 $1,464.00
Sawing existing pavement; Linear
1700 complete as specified Feet 905.00 700.20 -204.80 $3.00 ($614.40)
Tack coat;complete as
1900 specified Gallons 56.00 0.00 -56.00 $5.05 ($282.80)
5"asphaltic pavement with
10"CABC and grading; Square
1905 complete as specified Yards 790.00 667.70 -122.30 $44.65 ($5,460.70)
4"asphaltic surface with 6"
CABC and grading; complete Square
1916 as specified Yards 240.00 156.20 -83.80 $48.14 ($4,034.12)
Furnish and install 10"storm Linear
2002 sewer; complete as specified Feet 25.00 20.00 -5.00 $44.50 ($222.50)
Furnish and install 12"storm Linear
2003 sewer; complete as specified Feet 85.00 69.50 -15.50 $46.50 ($720.75)
Furnish and install 15"storm Linear
2006 sewer; complete as specified Feet 35.00 34.00 -1.00 $48.50 ($48.50)
Furnish; install; maintain; and
remove Type D modified inlet
protection; complete as
2508 specified Each 2.00 2.00 $150.00
Sediment removal-Type D
modified inlet protection;
2510 complete as specified Each 2.00 0.00 -2.00 $100.00 ($200.00)
Furnish; install;maintain; and
remove stone tracking pad;
2512 complete as specified Each 2.00 0.00 -2.00 $1,500.00 ($3,000.00)
Furnish;install; maintain;and
remove stone bag; complete
2516 as specified Each 10.00 0.00 -10.00 $150.00 ($1,500.00)
Furnish; install; maintain;and
remove 12"diameter
sediment logs;complete as Linear
2518 specified Feet 40.00 10.00 -30.00 $10.00 ($300.00)
Furnish; install; maintain; and
remove ditch check;
2522 complete as specified Each 77.00 66.00 -11.00 $250.00 ($2,750.00)
Install salvaged topsoil 6" Square
2602 depth;complete as specified Yards 9,184.00 8,851.50 -332.50 $4.00 ($1,330.00)
Furnish and install native
seeding;complete as Square
2610 specified Yards _ 9,184.00 13,250.05 4066.05 $1.01 $4,106.71
Page 1 of 3
•
CONTRACT 17-19 CHANGE ORDER#2 FINAL(REVISED)
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
Furnish and install Class I;
Type A erosion control mat; Square
2630 complete as specified Yards 9,184.00 13,250.05 4066.05 $1.85 $7,522.19
Furnish and install 8"sanitary
sewer(new); complete as Linear
3030 specified Feet 300.00 298.00 -2.00 $28.20 ($56.40)
Furnish and install standard
sanitary sewer manhole(4'
diameter);complete as Vertical
3100 specified Feet 14.76 14.00 -0.76 $179.00 ($136.04)
Furnish and install internal
sanitary sewer manhole
chimney seal; complete as
3118 specified Each 1.00 1.00 $382.00
Furnish and install internal
sanitary sewer manhole
chimney seal extension;
3120 complete as specified Each 1.00 0.00 -1.00 $186.00 ($186.00)
Core into existing manhole;
3332 complete as specified Each 1.00 1.00 $990.00
Trenchless 18"sanitary
sewer casing pipe;complete Linear
3500 as specified Feet 240.00 240.00 $370.00
Closed circuit televising; Linear
3700 complete as specified Feet 300.00 298.00 -2.00 - $3.00 ($6.00)
Furnish and install new 6"
ductile iron water main with
polywrap;complete as Linear
4020 specified Feet 132.00 163.60 31.60 $45.70 $1,444.12
Furnish and install new 16"
ductile iron water main with
polywrap; complete as Linear
4028 specified Feet 10,990.00 10,993.00 3.00 $83.42 $250.26
Furnish and install new 16"
ductile iron water main with
polywrap and TR Flex
restrained joints;complete as Linear
4029 specified Feet 380.00 380.00 $78.80
Furnish and install
connections to existing 16"
water main;complete as
4066 specified Each 2.00 2.00 $1,679.00
Furnish and install 16"x 6"
water main tee;complete as
4137 specified Each 14.00 16.00 2.00 $1,481.00 $2,962.00
Furnish and install 6"45
degree water main bend;
4236 complete as specified Each 28.00 20.00 -8.00 $321.00 ($2,568.00)
Furnish and install 16"45
degree water main bend;
4240 complete as specified Each 14.00 14.00 $1,371.00
Furnish and install 6"water
main gate valve;complete as
4401 specified Each 14.00 16.00 2.00 $1,086.00 $2,172.00
Furnish and install 16"water
main gate valve; complete as
4405 specified Each 14.00 16.00 2.00 $7,006.00 $14,012.00
Page 2 of 3
•
CONTRACT 17-19 CHANGE ORDER#2 FINAL(REVISED)
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
Furnish and install 16"x 16"
tapping valve and sleeve;
4459 complete as specified Each 1.00 1.00 $13,788.00
Furnish and install hydrant;
4500 complete as specified Each 14.00 16.00 2.00 $3,362.00 $6,724.00
Jack and bore 30"steel water
main casing pipe; complete Linear
4704 as specified Feet 380.00 380.00 $417.00
SECTION (BID ITEMS 1010-4704)-SUBTOTAL: $42,037.68 ($24,928.83)
NET INCREASE TO SECTION: $17,108.85
ADDITIONAL WORK REQUIRED: CO#1
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRIC:F PRIC:F
Install the Ripple Avenue
Pressure Regulating Valve
(PRV)Station; complete as
FO1 specified Stations 1.00 1.00 $137,990.00
ADDITIONAL WORK: CO#1 (BID ITEM FO1)-SUBTOTAL: $0.00 $0.00
NET DECREASE TO SECTION: $0.00
NET INCREASE TO SECTION $17,108.85
NET DECREASE TO SECTION $0.00
NET INCREASE TO CONTRACT: $17,108.85
Page 3 of 3