HomeMy WebLinkAboutVinton Change Order No. 1 PW 18-11 TO: VINTON CONSTRUCTION CO CHANGE ORDER#1 REVISED FINAL P.O. BOX 137 (WITH BOWEN STREET ADDITIONAL WORK) TWO RIVERS,WI 54241 DATE: MAY 2,2019 Your present contract with the City of Oshkosh,Contract No. 18-11, awarded July 10,2018, is hereby amended and changed as follows: NET INCREASE TO SECTION I: $14,961.40 NET DECREASE TO SECTION I: ($70,698.30) NET DECREASE TO CONTRACT ($55,736.90) TOTALS BID TOTAL $177,072.50 $177,072.50 CO#1 ($55,736.90) ($55,736.90) CONTRACT TOTAL $121,335.60 $121,335.60 CITY OF OSHKOSH BY: City Mana er o City Clerk Approved and accepted: ator I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh,Wisconsin, under the within Change Order. Comp roller Approved a to form: 1pvir.). City f • ' CONTRACT 18-11 CHANGE ORDER#1 REVISED FINAL(BOWEN ST EXTRA WORK) 18-11 SANITARY MANHOLE/REHABILITATION ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE Replace sanitary manhole casting(CITY to furnish casting); complete as 100 specified Each 60.00 56.00 -4.00 $300.00 ($1,200.00) External manhole chimney seal(9"); complete as 102 specified Each 45.00 51.00 6.00 $695.00 $4,170.00 External manhole chimney seal(Infrashield);complete 103 as specified Each 15.00 3.00 -12.00 $585.00 ($7,020.00) 8"external manhole chimney seal extension; complete as 104 specified Each 22.00 17.00 -5.00 $260.00 ($1,300.00) Internal manhole chimney seal(10"); complete as 106 specified Each 5.00 3.00 -2.00 $675.00 ($1,350.00) 10"internal manhole chimney seal extension; complete as 108 specified Each 5.00 3.00 -2.00 $1.00 ($2.00) 7"internal manhole chimney seal extension; complete as 110 specified Each 5.00 2.00 -3.00 $1.00 ($3.00) Re-form/re-shape manhole 111 bench; complete as specified Each 2.00 0.00 -2.00 $500.00 ($1,000.00) Concrete adjusting rings; Vertical 112 complete as specified Feet 29.00 28.55 -0.45 $200.00 ($90.00) Rubber adjusting rings; Vertical 114 complete as specified Feet 2.00 0.64 -1.36 $750.00 ($1,020.00) Reconstruct sanitary sewer manhole(slurry); complete as Vertical 116 specified Feet 10.00 0.00 -10.00 $650.00 ($6,500.00) Furnish and install standard sanitary manhole(4' diameter)(slurry); complete Vertical 118 as specified Feet 20.00 0.00 -20.00 $945.00 ($18,900.00) Saw cut concrete pavement; Linear 122 complete as specified Feet 480.00 484.60 4.60 $4.00 $18.40 Remove concrete pavement; Square 124 complete as specified Yards 300.00 142.40 -157.60 $1.00 ($157.60) Pavement ties;complete as 126 specified Each 75.00 156.00 81.00 $7.00 $567.00 Drilled dowel bars;complete 128 as specified Each 160.00 73.00 -87.00 $10.00 ($870.00) 7"concrete pavement; Square 130 complete as specified Yards 200.00 46.40 -153.60 $65.00 ($9,984.00) 7"concrete pavement(HES); Square 132 complete as specified Yards 50.00 0.00 -50.00 $68.00 ($3,400.00) 8"concrete pavement; Square 134 complete as specified Yards 50.00 0.00 -50.00 $69.00 ($3,450.00) 8"concrete pavement(HES); Square 136 complete as specified Yards 50.00 100.00 50.00 $72.00 $3,600.00 Partial depth joints; complete Linear 138 as specified Feet 25.00 0.00 -25.00 $5.00 ($125.00) Page 1 of 3 ' CONTRACT 18-11 CHANGE ORDER#1 REVISED FINAL(BOWEN ST EXTRA WORK) ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE 12"radius curb with 6"CABC and grading; complete as Linear 140 specified Feet 25.00 0.00 -25.00 $10.00 ($250.00) 30"curb and gutter; 7";with 5"CABC and grading; Linear 142 complete as specified Feet 25.00 0.00 -25.00 $30.00 ($750.00) 4"concrete sidewalk; Square 144 complete as specified Yards 100.00 0.00 -100.00 $7.00 ($700.00) 6"concrete sidewalk; driveway;and ramp; Square 146 complete as specified Feet 100.00 0.00 -100.00 $8.00 ($800.00) Drilled No.4 sidewalk tie 148 bars; complete as specified Each 8.00 0.00 -8.00 $6.00 ($48.00) Curb ramps detectable warning field;complete as Square 150 specified Feet 16.00 0.00 -16.00 $30.00 ($480.00) Saw cut asphalt pavement; Linear 152 complete as specified Feet 260.00 128.60 -131.40 $3.00 ($394.20) Remove and replace HMA pavement;complete as Square 154 specified Yards 200.00 29.00 -171.00 $30.00 ($5,130.00) Turf restoration; complete as Square 156 specified Yards 500.00 540.60 40.60 $10.00 $406.00 Manhole lid plug; complete 158 as specified Each 10.00 0.00 -10.00 $20.00 ($200.00) Tuck point manhole; 160 complete as specified Each 15.00 13.00 -2.00 $200.00 ($400.00) Sanitary manhole grouting 162 setup; complete as specified Each 8.00 5.00 -3.00 $725.00 ($2,175.00), Sanitary manhole grout; 164 complete as specified Gallons 475.00 56.00 -419.00 $2.50 ($1,047.50) Sanitary MH cementitious liner setup; complete as 166 specified Each 1.00 0.00 -1.00 $1,850.00 ($1,850.00) Structural cementitious liner; Vertical 168 complete as specified Feet 10.00 0.00 -10.00 $10.00 ($100.00) Cold mix patch;complete as Square 170 specified Yards 200.00 0.00 -200.00 $0.01 ($2.00) Traffic control; complete as Lump 172 specified Sum 1.00 1.00 $21,350.00 (BID ITEMS 100-172)-SUBTOTAL $8,761.40 ($70,698.30) NET DECREASE TO SECTION I: ($61,936.90) ADDITIONAL WORK REQUIRED:CO#1 BOWEN ST EXTRA WORK ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE Additional Traffic Control on Bowen Street; complete as Lump 10000 specified Sum 0.00 1.00 1.00 $1,000.00 $1,000.00 Additional flagging on Bowen Street 10/29 and 10/30; 10002 complete as specified Hours 0.00 37.00 37.00 $100.00 $3,700.00 Page 2 of 3 CONTRACT 18-11 CHANGE ORDER#1 REVISED FINAL(BOWEN ST EXTRA WORK) ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE Additional mobilization for Bowen Street;complete as Lump 10003 'specified Sum 0.00 1 1.00 1.00 $1,500.00 $1,500.00 ADDITIONAL WORK REQUIRED:CO#1 BOWEN ST EXTRA WORK- SUBTOTAL: $6,200.00 $0.00 NET INCREASE: $6,200.00 NET INCREASE TO SECTION I: $14,961.40 NET DECREASE TO SECTION I: ($70,698.30) NET DECREASE TO CONTRACT: ($55,736.90) Page 3 of 3