HomeMy WebLinkAboutAl Dix Change Order No 1 18-06 TO: AL DIX CONCRETE, INC. CHANGE ORDER#1
401 GERTRUDE STREET DATE: MARCH 1, 2019
KAUKAUNA, WI 54130
Your present contract with the City of Oshkosh, Contract No. 18-06, awarded March 27, 2018, is hereby amended
and changed as follows:
NET INCREASE TO UNIT A: $328,464.53
NET DECREASE TO UNIT B: ($1,540.00)
NET DECREASE TO UNIT C: ($33,545.40)
NET INCREASE DUE TO ADDITIONAL WORK REQUIRED: $7,312.51
NET INCREASE TO CONTRACT $300,691.64
SECTION I TOTALS
BID TOTAL $1,279,130.00 $1,279,130.00
CO#1 $300,691.64 $300,691.64
CONTRACT TOTAL $1,579,821.64 $1,579,821.64
CITY OF OSHKOSH
BY:
City an•g,
' !1.
City Clerk
r and accepted:
Contractor
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin,
under the within Change Order.
Comptroller
Approved o form:
City Atto y
CONTRACT 18-06 CHANGE ORDER#1
18-06
WORK UNIT A
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
Removing concrete and
asphalt sidewalk and
driveway; complete as Square
A-1120 specified Feet 90,000.00 133,796.74 43796.74 $1.50 $65,695.11
7"concrete pavement
removal and replacement;
including sawing; pavement
ties;dowel bars; bond
breaker; integral curb and
fine grading;turf restoration;
and traffic control;complete Square
A-1308 as specified Yards 1,000.00 91.27 -908.73 $68.00 ($61,793.64)
8"concrete pavement
removal and replacement;
including sawing; pavement
ties;dowel bars; bond
breaker; integral curb and
fine grading;turf restoration;
and traffic control; complete Square
A-1318 as specified Yards 1,500.00 1,740.77 240.77 $75.00 $18,057.75
8"concrete pavement HES
removal and replacement;
including sawing; pavement
ties;dowel bars; bond
breaker; integral curb and
fine grading;turf restoration;
and traffic control;complete Square
A-1319 as specified Yards 500.00 181.17 -318.83 $83.00 ($26,462.89)
Adjust manholes and inlets;
A-1360 complete as specified Each 10.00 6.00 -4.00 $400.00 ($1,600.00)
Turf restoration;complete as Square
A-1370 specified Yards 400.00 94.97 -305.03 $12.00 ($3,660.36)
Up-charge for late season
cold weather concrete
pavement;complete as Cubic
A-1390 specified Yards 500.00 171.32 -328.68 $9.00 ($2,958.12)
12'radious curb with 6"
CABC and grading; complete Linear
A-1410 as specified Feet 250.00 0.00 -250.00 $12.00 ($3,000.00)
18"concrete curb and gutter
removal and replacement;
including sawing; pavement
ties;dowel bars;bond
breaker; integral curb and
fine grading;turf restoration;
and traffic control;complete Linear
A-1428 as specified Feet 750.00 304.30 -445.70 $65.00 ($28,970.50)
30"concrete curb and gutter
removal and replacement;
including sawing; pavement
ties;dowel bars; bond
breaker; integral curb and
fine grading;turf restoration;
and traffic control; complete Linear
A-1448 as specified Feet 750.00 2,985.60 2235.60 $68.00 $152,020.80
Page 1 of 5
CONTRACT 18-06 CHANGE ORDER#1
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
Sidewalk curb; complete as Linear
A-1460 specified Feet 100.00 538.70 438.70 $50.00 $21,935.00
4"concrete sidewalk with 3"
CABC and grading; complete Square
A-1500 a specified Feet 65,000.00 90,513.67 25513.67 $4.50 $114,811.52
4"concrete sidewalk with 3"
CABC and grading; in
existing subdivisions; Square
A-1500A complete a specified Feet 1,500.00 8,910.30 7410.30 $5.25 $38,904.08
4"concrete sidewalk with 3"
CABC and grading;water
dept. locations;complete a Square
A-1502 specified Feet 1,500.00 1,832.69 332.69 $8.00 $2,661.52
6"concrete
sidewalk/driveway /ramp with
3"CABC and grading; Square
A-1510 complete as specified Feet 25,000.00 40,156.33 15156.33 $5.25 $79,570.73
6"concrete
sidewalk/driveway /ramp with
3"CABC and grading;water
dept. locations; complete as Square
A-1512 specified Feet 1,000.00 976.78 -23.22 $8.75 ($203.18)
8"concrete
sidewalk/driveway /ramp with
3"CABC and grading; Square
A-1520 complete as specified Feet 500.00 3,709.85 3209.85 $8.25 $26,481.26
6"concrete sidewalk with 3"
CABC and grading; London
Paver Pattern;complete as Square
A-1526 specified Feet 300.00 62.80 -237.20 $65.00 ($15,418.00)
Curb ramp detectable
warning field(natural/non-
painted); complete as Square
A-1540 specified Feet 500.00 560.00 60.00 $35.00 $2,100.00
No.4 reinforcing rods-
deformed; epoxy-coated; Linear
A-1550 complete as specified Feet 1,000.00 544.00 -456.00 $2.50 ($1,140.00)
Drilled No.4 sidewalk tie bars
-deformed;epoxy-coated;
A-1560 complete as specified Each 10,000.00 9,298.00 -702.00 $6.50 ($4,563.00)
Cold weather covering
(sidewalk)-single visquine; Square
A-1580 complete as specified Feet 1,000.00 0.00 -1,000.00 $1.00 ($1,000.00)
Cold weather covering
(sidewalk)-double visquine; Square
A-1582 complete as specified Feet 1,000.00 0.00 -1,000.00 $1.00 ($1,000.00)
(sidewalk)-double visquine
with 6"hay;complete as Square
A-1584 specified Feet 500.00 0.00 -500.00 $1.00 ($500.00)
Up-charge for late season
cold weather concrete
sidewalk; complete as Cubic
A-1590 specified Yards 500.00 0.00 -500.00 $9.00 ($4,500.00)
Sawing existing pavement; Linear
A-1700 complete as specified Feet 3,000.00 2,046.40 -953.60 $5.00 ($4,768.00)
Profile saw cut concrete curb; Linear
A-1720 complete as specified Feet 150.00 39.00 -111.00 $50.00 ($5,550.00)
Page 2 of 5
CONTRACT 18-06 CHANGE ORDER#1
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
Re-grade existing gravel
driveways; complete as Square
A-1820 specified Feet 75.00 0.00 -75.00 $20.00 ($1,500.00)
5"asphaltic surface MT with
6"CABC and grading; Square
A-1915 complete as specified Yards 500.00 0.00 -500.00 $65.00 ($32,500.00)
4"asphaltic surface LT with
6"CABC and grading; Square
A-1916 complete as specified Yards 500.00 494.13 -5.87 $65.00 ($381.55)
2"asphaltic surface LT with
6"CABC and grading; Square
A-1917 complete as specified Yards 100.00 218.401 118.40 $65.00 $7,696.00
WORK UNIT A (BID ITEMS A-1120-A-1917)-SUBTOTAL: $529,933.77 ($201,469.24)
NET INCREASE TO WORK UNIT A: $328,464.53
WORK UNIT B
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICF PRICF
7"concrete pavement
removal and replacement;
including sawing; pavement
ties;dowel bars; bond
breaker; integral curb and
fine grading;turf restoration;
and traffic control;complete Square
B-1308 as specified Yards 830.00 818.30 818.30 -11.70 $68.00 ($795.60)
Crushed aggregate base
course;complete as
B-1340 specified Tons 130.00 112.78 112.78 -17.22 $20.00 ($344.40)
Adjust manholes and inlets;
B-1360 complete as specified Each 1.00 0.00 0.00 -1.00 $400.00 ($400.00)
WORK UNIT B(BID ITEMS B-1308 -B-1360)-SUBTOTAL: $0.00 ($1,540.00)
NET DECREASE TO WORK UNIT B: ($1,540.00)
WORK UNIT C
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE-
Removing concrete and
asphalt sidewalk and
driveway; complete as Square
C-1120 specified Feet 500.00 784.00 284.00 $1.50 $426.00
8"concrete pavement
removal and replacement;
including sawing; pavement
ties;dowel bars; bond
breaker; integral curb and
fine grading;turf restoration;
and traffic control; complete Square
C-1318 as specified Yards 200.00 407.90 207.90 $75.00 $15,592.50
Page 3 of 5
CONTRACT 18-06 CHANGE ORDER#1
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE!N DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
8"concrete pavement HES
removal and replacement;
including sawing;pavement
ties;dowel bars; bond
breaker; integral curb and
fine grading;turf restoration;
and traffic control; complete Square
C-1319 as specified Yards 300.00 0.00 -300.00 $80.00 ($24,000.00)
Crushed aggregate base
course;complete as
C-1340 specified Tons 200.00 46.70 -153.30 $25.00 ($3,832.50)
Adjust manholes and inlets;
C-1360 complete as specified Each 3.00 0.00 -3.00 $400.00 ($1,200.00)
18"concrete curb and gutter
removal and replacement;
including sawing; pavement
ties; dowel bars; bond
breaker; integral curb and
fine grading;turf restoration;
and traffic control; complete Linear
C-1428 as specified Feet 200.00 0.00 -200.00 $65.00 ($13,000.00)
30"concrete curb and gutter
removal and replacement;
including sawing; pavement
ties;dowel bars;bond
breaker; integral curb and
fine grading;turf restoration;
and traffic control; complete Linear
C-1448 as specified Feet 200.00 100.00 -100.00 $68.00 ($6,800.00)
4"concrete sidewalk with 3"
CABC and grading; complete Square
C-1500 a specified Feet 500.00 457.20 -42.80 $4.50 ($192.60)
6"concrete sidewalk/
driveway/ramp with 3"CABC
and grading; complete as Square
C-1510 specified Feet 500.00 326.80 -173.20 $5.25 ($909.30)
Curb ramp detectable
warning field(natural/non-
painted); complete as Square
C-1540 specified Feet 6.00 24.00 18.00 $35.00 $630.00
Drilled No.4 sidewalk tie bars
-deformed;epoxy-coated;
C-1560 complete as specified Each 20.00 32.00 12.00 $6.50 $78.00
Sawing existing pavement; Linear
C-1700 complete as specified Feet 75.00 7.50 -67.50 $5.00 ($337.50)
WORK UNIT C(BID ITEMS C-1120-C-1700) -SUBTOTAL: $16,726.50 ($50,271.90)
NET DECREASE TO WORK UNIT C: ($33,545.40)
ADDITIONAL WORK REQUIRED:
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE 1N
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
Cold Weather Covering
(concrete pavement)-Single Square
1-1380 Visquine Yards 0.00 617.86 617.86 $3.50 $2,162.51
Page 4 of 5
CONTRACT 18-06 CHANGE ORDER#1
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
Extra time and materials to
remove and fill the vaults
within the righ-of-way on
Brown Street and High Lump
1-10000 Avenue Sum 0.00 1.00 1.00 $2,000.00 $2,000.00
Extra time and materials to
pour light bases within Lump
1-10001 sidewalk rehab areas Sum 0.00 1.00 1.00 $2,900.00 $2,900.00
Extra work for using a power
buggy to transport concrete Lump
1-10002 through side yards Sum 0.00 1.00 1.00 $250.00 $250.00
ADDITIONAL WORK REQUIRED:CO#1 (BID ITEMS 1-1380-1-10002)-SUBTOTAL: $7,312.51 $0.00
NET INCREASE DUE TO ADDITIONAL WORK REQUIRED : $7,312.51
NET INCREASE TO WORK UNIT A $328,464.53
NET DECREASE TO WORK UNIT B ($1,540.00)
NET DECREASE TO WORK UNIT C ($33,545.40)
NET INCREASE DUE TO ADDITIONAL WORK REQUIRED: $7,312.51
NET INCREASE TO CONTRACT: $300,691.64
Page 5 of 5