TO: PTS CONTRACTORS, INC. CHANGE ORDER#1 (FINAL)
4075 EATON ROAD DATE: JANUARY 16, 2019
GREEN BAY, WI 54311
Your present contract with the City of Oshkosh, Contract No. 17-22, awarded June 27, 2017, is hereby
amended and changed as follows:
NET INCREASE TO SECTION: $533,837.38
NET DECREASE TO SECTION: ($411,782.92)
NET INCREASE TO CONTRACT $122,054.46
BID TOTAL $3,974,211.60 $3,974,211.60
CO#1 $122,054.46 $122,054.46
CONTRACT TOTAL $4,096,266.06 $4,096,266.06
CITY OF OSHKOSH
BY: I
, r1-U^z
City Mana
City Clerk
Approved and a cepted:
Contractor
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin,
under the within Change Order.
`4
hoihvC1 I R, Dr►(\
Comptroller
Approved alto form:
City Att y
CONTRACT 17-22 CHANGE ORDER#1
17-22
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE/N
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Clearing; complete as
1010 specified Stations 1.30 1.38 0.08 $3,500.00 $280.00
Clearing; complete as Inch
1011 specified Diameter 18.00 16.00 -2.00 $75.00 ($150.00)
Grubbing; complete as
1020 specified Stations 1.30 1.38 0.08 $3,500.00 $280.00
Grubbing; complete as Inch
1021 specified Diameter 18.00 52.00 34.00 $75.00 $2,550.00
Removing pavement; Square
1100 complete as specified Yards 2,420.00 2,640.50 220.50 $10.00 $2,205.00
Removing concrete and
asphalt sidewalk and
driveway;complete as Square
1120 specified Feet 12,405.00 12,769.60 364.60 $4.50 $1,640.70
Unclassified excavation; Cubic
1200 complete as specified Yards 5,010.00 3,544.68 -1,465.32 $16.50 ($24,177.78)
Excavation special(paving);
1220 complete as specified Tons 7,162.00 1,063.22 -6,098.78 $15.10 ($92,091.58)
7"concrete pavement;with
5"CABC and grading; Square
1301 complete as specified Yards 2,760.00 2,701.60 -58.40 $61.50 ($3,591.60)
8"concrete pavement;with
6"CABC and grading; Square
1311 complete as specified Yards 1,850.00 1,957.60 107.60 $63.50 $6,832.60
Crushed aggregate base
course; complete as
1340 specified Tons 230.00 0.00 -230.00 $16.50 ($3,795.00)
Pavement ties; complete as
1350 specified Each 400.00 294.00 -106.00 $9.00 ($954.00)
Drilled dowel bars; 1";
1352 complete as specified Each 16.00 34.00 18.00 $12.00 $216.00
Drilled dowel bars; 1 1/4";
1354 complete as specified Each 34.00 0.00 -34.00 $14.00 ($476.00)
Adjust manholes and inlets;
1360 complete as specified Each 61.00 58.00 -3.00 $475.00 ($1,425.00)
Turf restoration on East 11th
Avenue; complete as Square
1370A specified Yards 1,277.00 1,475.70 198.70 $15.00 $2,980.50
Turf restoration on East 14th
Avenue; complete as Square
1370B specified Yards 776.00 1,320.20 544.20 $15.00 $8,163.00
Turf restoration on South
Main Street; complete as Square
1370C specified Yards 1,380.00 1,430.20 50.20 $15.00 $753.00
Turf restoration on East
South Park Avenue; Square
1370D complete as specified Yards 704.00 548.00 -156.00 $15.00 ($2,340.00)
Restore gravel driveway/ Square
1372 apron; complete as specified Yards 600.00 640.70 40.70 $7.50 $305.25
12"radius curb with 6"CABC
and grading; complete as Linear
1410 specified Feet 500.00 483.90 -16.10 $15.00 ($241.50)
30"curb and gutter;8";with
6"CABC and grading; Linear
1442 complete as specified Feet 605.00 674.20 69.20 $18.00 $1,245.60
30"curb and gutter; plain; 8";
with 6"CABC and grading; Linear
1443 complete as specified Feet 865.00 745.30 -119.70 $26.00 ($3,112.20)
Page 1 of 13
' CONTRACT 17-22 CHANGE ORDER#1
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Sidewalk curb; complete as Linear
1460 specified Feet 58.00 26.70 -31.30 $42.00 ($1,314.60)
4"concrete sidewalk with 3"
CABC and grading; complete Square
1500 as specified Feet 12,850.00 11,958.90 -891.10 $6.50 ($5,792.15)
6"concrete sidewalk/
driveway/ramp with 3"CABC
and grading;complete as Square
1510 specified Feet 5,080.00 5,385.90 305.90 $6.50 $1,988.35
8"concrete sidewalk/
driveway/ramp with 3"CABC
and grading;complete as Square
1520 specified Feet 3,705.00 3,327.60 -377.40 $7.40 ($2,792.76)
Curb ramp detectable
warning field(natural/non-
painted); complete as Square
1540 specified Feet 160.00 176.00 16.00 $38.00 $608.00
No.4 reinforcing rods-
deformed; epoxy-coated; Linear
1550 complete as specified Feet 690.00 330.00 -360.00 $2.00 ($720.00)
Drilled No.4 sidewalk tie bars
-deformed;epoxy-coated;
1560 complete as specified Each 60.00 63.00 3.00 $8.00 $24.00
Locate existing property
monuments; complete as
1650 specified Each 18.00 15.00 -3.00 $750.00 ($2,250.00)
Replace existing property
monuments; complete as
1652 specified Each 13.00 5.00 -8.00 $750.00 ($6,000.00)
Sawing existing pavement; Linear
1700 complete as specified Feet 230.00 249.90 19.90 $5.00 $99.50
Sawing concrete pavement
full depth; complete as Linear
1710 specified Feet 2,230.00 1,908.10 -321.90 $4.00 ($1,287.60)
Base aggregate dense: 3/4";
1800 complete as specified Tons 35.00 35.00 $26.00
Base aggregate dense; 1-
1801 1/4"; complete as specified Tons 1,650.00 1,648.60 -1.40 $14.60 ($20.44)
Breaker run; complete as
1810 specified Tons 3,050.00 1.576.80 -1,473.20 $14.60 ($21,508.72)
Tack coat; complete as
1900 specified Gallons 320.00 139.40 -180.60 $6.00 ($1,083.60)
HMA Pavement MT:
1902 complete as specified Tons 1,370.00 1,454.60 84.60 $84.00 $7,106.40
5"asphaltic surface MT with
6"CABC and grading; Square
1915 complete as specified Yards 305.00 260.30 -44.70 $45.00 ($2,011.50)
Prepare foundation for
asphaltic paving; complete as Lump
1960 specified Sum 2.00 2.00 $21,525.00
Furnish and install 10"storm Linear
2002 sewer; complete as specified Feet 95.00 48.50 -46.50 $102.00 ($4,743.00)
Furnish and install 12"storm Linear
2003 sewer; complete as specified Feet 610.00 619.10 9.10 $107.00 $973.70
Furnish and install 12"RCP
Class Ill storm sewer; Linear
2004 complete as specified Feet 245.00 238.10 -6.90 $94.00 ($648.60)
Furnish and install 15"storm Linear
2006 sewer;complete as specified Feet 180.00 175.10 -4.90 $98.00 ($480.20)
Page 2 of 13
CONTRACT 17-22 CHANGE ORDER#1
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Furnish and install 15"RCP
Class Ill storm sewer; Linear
2007 complete as specified Feet 290.00 287.80 -2.20 $88.00 ($193.60)
Furnish and install 18"storm Linear
2009 sewer; complete as specified Feet 65.00 57.50 -7.50 $137.00 ($1,027.50)
Furnish and install 24"storm Linear
2015 sewer; complete as specified Feet 100.00 87.70 -12.30 $142.00 ($1,746.60)
Furnish and install 24"RCP
Class Ill storm sewer; Linear
2016 complete as specified Feet 35.00 36.00 1.00 $134.00 $134.00
Furnish and install 30"RCP
Class III storm sewer; Linear
2022 complete as specified Feet 35.00 27.00 -8.00 $140.00 ($1,120.00)
Furnish and install 29"x 45"
HERCP Class Ill storm Linear
2051 sewer; complete as specified Feet 385.00 378.30 -6.70 $135.00 ($904.50)
Furnish and install 38"x 60"
HERCP Class Ill storm Linear
2055 sewer; complete as specified Feet 15.00 15.00 $507.00
Furnish and install 4'x 6'box
culvert storm sewer; Linear
2072 complete as specified Feet 355.00 354.70 -0.30 $640.00 ($192.00)
Furnish and install 5'x 8'box
culvert storm sewer; Linear
2079 complete as specified Feet 430.00 427.00 -3.00 $750.00 ($2,250.00)
Furnish and install 4'x 6'box
culvert storm sewer with
manhole or inlet riser; Linear
2096 complete as specified Feet 16.00 16.00 $800.00
Furnish and install 5'x 8'box
culvert storm sewer with
manhole or inlet riser; Linear
2103 complete as specified Feet 24.00 22.50 -1.50 $853.00 ($1,279.50)
Furnish and install 84"
HOBAS storm sewer; Linear
2113 complete as specified Feet 150.00 0.00 -150.00 $890.00 ($133,500.00)
Furnish and install standard
storm sewer manhole(4'
diameter); complete as Vertical
2201 specified Feet 14.50 14.27 -0.23 $380.00 ($87.40)
Furnish and install standard
storm sewer manhole(6'
diameter);complete as Vertical
2203 specified Feet 7.40 7.38 -0.02 $620.00 ($12.40)
Furnish and install standard
storm sewer manhole(8'
diameter); complete as Vertical
2205 specified Feet 11.35 13.62 2.27 $1,120.00 $2,542.40
Furnish and install standard
storm sewer inlet manhole(4'
diameter); complete as Vertical
2213 specified Feet 7.60 9.46 1.86 $480.00 $892.80
Furnish and install Storm
Sewer Junction Chamber 14-
2225A 5; complete as specified Each 1.00 1.00 $80,250.00
Furnish and install Storm
Sewer Junction Chamber 14-
2225E 6; complete as specified Each 1.00 1.00 $65,465.00
Page 3 of 13
CONTRACT 17-22 CHANGE ORDER#1
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Furnish and install Storm
Sewer Junction Chamber 14-
2225C 10; complete as specified Each 1.00 1.00 $62,460.00
Furnish and install Storm
Sewer Junction Chamber 14-
2225D 11;complete as specified Each 1.00 1.00 $61,750.00
Furnish and install Storm
Sewer Junction Chamber S-
2225E 5; complete as specified Each 1.00 1.00 $46,785.00
Furnish and install standard
storm sewer manhole riser(4'
diameter);complete as Vertical
2227 specified Feet 13.25 15.13 1.88 $365.00 $686.20
Furnish and install Type 1
2236 inlet;complete as specified Each 3.00 3.00 $2,155.00
Furnish and install Type 3
inlet(with 18"sump);
2237 complete as specified Each 19.00 19.00 $2,356.00
Furnish and install 96"storm
sewer casing pipe by
trenchless methods; Linear
2370 complete as specified Feet 80.00 80.00 $5,230.00,
Furnish and install 6"storm
sewer lateral; complete as Linear
2400 specified Feet 175.00 119.00 -56.00 $85.00 ($4,760.00)
Furnish and install 8"storm
sewer lateral; complete as Linear
2402 specified Feet 50.00 51.00 1.00 $95.00 $95.00
Furnish and install storm
sewer marker balls; complete
2404 as specified Each 11.00 11.00 $58.00
Furnish and install storm
sewer clay dams; complete
2406 as specified Each 6.00 5.00 -1.00 $145.00 ($145.00)
Furnish; install; maintain; and
remove Type D modified inlet
protection; complete as
2508 specified Each 68.00 59.00 -9.00 $148.00 ($1,332.00)
Sediment removal-Type D
modified inlet protection;
2510 complete as specified Each 68.00 1.00 -67.00 $41.00 ($2,747.00)
Furnish; install; maintain; and
remove stone tracking pad;
2512 complete as specified Each 1.00 0.00 -1.00 $2,546.00 ($2,546.00)
Furnish; install; maintain; and
remove stone bag; complete
2516 as specified Each 25.00 18.00 -7.00 $25.00 ($175.00)
Furnish; install; maintain; and
remove 12"diameter
sediment logs; complete as Linear
2518 specified Feet 380.00 240.00 -140.00 $6.60 ($924.00)
Furnish; install; maintain; and
remove turbidity barrier;
2526 complete as specified Each 1.00 1.00 $1,981.00
Furnish and install topsoil 6" Square
2600 depth; complete as specified Yards 14.00 14.00 $25.00
Furnish and install turf grass; Square
2620 complete as specified Yards 14.00 14.00 $15.00
Page 4 of 13
' CONTRACT 17-22 CHANGE ORDER#1
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE/N
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Furnish and install Class I;
Urban;Type A erosion
control mat; complete as Square
2632 specified Yards 14.00 14.00 $10.00
Furnish and install heavy rip-
rap with filter fabric; complete Square
2650 as specified Yards 90.00 90.00 $65.00
Rock excavation; complete Cubic
2750 as specified Yards 25.00 0.00 -25.00 $0.01 ($0.25)
Abandon 8"-12"storm Linear
2800 sewer; complete as specified Feet 455.00 452.00 -3.00 $21.00 ($63.00)
Abandon 15"and larger
storm sewer; complete as Linear
2802 specified Feet 1,020.00 1,294.00 274.00 $35.00 $9,590.00
Remove 30"and smaller
storm sewer; complete as Linear
2804 specified Feet 245.00 204.00 -41.00 $85.00 ($3,485.00)
Remove 33"-60"storm Linear
2806 sewer; complete as specified Feet 25.00 45.00 20.00 $97.00 $1,940.00
Abandon storm sewer
manholes and inlets;
2810 complete as specified Each 11.00 10.00 -1.00 $425.00 ($425.00)
Remove storm sewer
manholes and inlets;
2812 complete as specified Each 11.00 12.00 1.00 $465.00 $465.00
Connect to existing storm
sewer main; complete as
2850 specified Each 4.00 5.00 1.00 $890.00 $890.00
Connect to existing storm
sewer lateral; complete as
2852 specified Each 1.00 4.00 3.00 $405.00 $1,215.00
Connect to existing storm
sewer manhole;complete as
2856 specified Each 13.00 13.00 $650.00
Connect to existing storm
sewer inlet;complete as
2858 specified Each 1.00 1.00 $745.00
Storm sewer utility line
opening (ULO); complete as
2914 specified Each 5.00 6.00 1.00 $660.00 $660.00
Excavation special(storm);
2950 complete as specified Tons 1,280.00 3,525.88 2,245.88 $16.00 $35,934.08
Bentonite slurry dam (storm);
2952 complete as specified Each 6.00 2.00 -4.00 $333.00 ($1,332.00)
Additional cost for using
Nitrile gaskets on box culvert;
2990 complete as specified Each 16.00 0.00 -16.00 $468.00 ($7,488.00)
Additional cost for using Mac
Wrap CR on box culvert;
2991 complete as specified Each 16.00 9.00 -7.00 $350.00 ($2,450.00)
Furnish and install absorbent Lump
2992 boom; complete as specified Sum 1.00 1.00 $2,021.00
Furnish and install 8"sanitary
sewer(relay); complete as Linear
3000 specified Feet 110.00 184.30 74.30 $185.00 $13,745.50
Furnish and install standard
sanitary sewer manhole(4'
diameter); complete as Vertical
3100 specified Feet 4.80 4.80 $485.00
Page 5 of 13
• CONTRACT 17-22 CHANGE ORDER#1
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Furnish and install external
sanitary sewer manhole
chimney seal; complete as
3114 specified Each 1.00 5.00 4.00 $458.00 $1,832.00
Furnish and install external
sanitary sewer manhole
chimney seal extension;
3116 complete as specified Each 1.00 0.00 -1.00 $407.00 ($407.00)
Furnish and install internal
sanitary sewer manhole
chimney seal;complete as
3118 specified Each 1.00 1.00 $356.00
Furnish and install internal
sanitary sewer manhole
chimney seal extension;
3120 complete as specified Each 1.00 0.00 -1.00 $305.00 ($305.00)
Furnish and install 8"x 6"
sanitary sewer factory wyes
or tees; complete as
3210 specified Each 3.00 3.00 $104.00
Furnish and install 6"sanitary
sewer laterals(new); Linear
3232 complete as specified Feet 25.00 2.00 -23.00 $165.00 ($3,795.00)
Furnish and install 4"/6"
sanitary sewer lateral(relay); Linear
3234 complete as specified Feet 95.00 137.00 42.00 $165.00 $6,930.00
Furnish and install sanitary
sewer lateral marker balls;
3236 complete as specified Each 6.00 6.00 $58.00
Furnish and install clay
3238 dams; complete as specified Each 3.00 2.00 -1.00 $350.00 ($350.00)
Furnish and install
connection to existing 8"
3300 mains; complete as specified Each 1.00 3.00 2.00 $3,250.00 $6,500.00
Closed circuit televising; Linear
3700 complete as specified Feet 110.00 184.00 74.00 $5.00 $370.00
Abandon sanitary sewer
manholes;complete as
3800 specified Each 1.00 1.00 $475.00
Abandon 8"sanitary sewer; Linear
3802 complete as specified Feet 220.00 220.00 $20.00
Furnish and install 4"ductile
iron water main(relay)with
polywrap; complete as Linear
4000 specified Feet 25.00 17.00 -8.00 $525.00 ($4,200.00)
Furnish and install 6"ductile
iron water main (relay)with
polywrap; complete as Linear
4002 specified Feet 186.00 200.70 14.70 $275.00 $4,042.50
Furnish and install 8"ductile
iron water main(relay)with
polywrap; complete as Linear
4004 specified Feet 15.00 9.30 -5.70 $265.00 ($1,510.50)
Furnish and install 10"ductile
iron water main(relay)with
polywrap; complete as Linear
4006 specified Feet 665.00 651.40 -13.60 $158.00 ($2,148.80)
Page 6 of 13
CONTRACT 17-22 CHANGE ORDER#1
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Furnish and install new 12"
ductile iron water main with
polywrap;complete as Linear
4026 specified Feet 400.00 394.00 -6.00 $147.00 ($882.00)
Furnish and install 1"water
service(relay); complete as Linear
4036 specified Feet 20.00 26.00 6.00 S145.00 S870.00
Furnish and install 1"
corporation and stop box;
4048 complete as specified Each 1.00 1.00 S465.00
Furnish and install water
service clay dams; complete
4055 as specified Each 1.00 2.00 1.00 $350.00 $350.00
Furnish and install
connections to existing 6"
water main; complete as
4058 specified Each 5.00 8.00 3.00 $1,506.00 $4,518.00
Furnish and install
connections to existing 12"
water main; complete as
4064 specified Each 2.00 3.00 1.00 $2,080.00 $2,080.00
Furnish and install 6"x 6"
water main tee; complete as
4101 specified Each 1.00 0.00 -1.00 $465.00 ($465.00)
Furnish and install 8"x 8"
water main tee; complete as
4111 specified Each 1.00 1.00 $850.00
Furnish and install 10"x 6"
water main tee;complete as
4119 specified Each 3.00 3.00 $1,250.00
Furnish and install 12"x 6"
water main tee; complete as
4128 specified Each 2.00 2.00 $1,450.00
Furnish and install 10" 11-1/4
degree water main bend;
4220 complete as specified Each 2.00 0.00 -2.00 $1,452.00 ($2,904.00)
Furnish and install 4"45
degree water main bend;
4235 complete as specified Each 2.00 0.00 -2.00 $1,197.00 ($2,394.00)
Furnish and install 6"45
degree water main bend;
4236 complete as specified Each 24.00 20.00 -4.00 $1,246.00 ($4,984.00)
Furnish and install 10"45
degree water main bend;
4238 complete as specified Each 7.00 6.00 -1.00 $1,450.00 ($1,450.00)
Furnish and install 8"x 6"
water main reducer;complete
4264 as specified Each 2.00 2.00 $1,292.00
Furnish and install 10"x 6"
water main reducer; complete
4266 as specified Each 1.00 1.00 $1,338.00
Furnish and install 10"x 8"
water main reducer;complete
4267 as specified Each 1.00 1.00 $1,365.00
Furnish and install 12"x 6"
water main reducer;complete
4269 as specified Each 1.00 1.00 $1,472.00
Furnish and install 10"water
main plug; complete as
4310 specified Each 1.00 1.00 $1,215.00
Page 7 of 13
CONTRACT 17-22 CHANGE ORDER#1
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Furnish and install 12"water
main plug;complete as
4311 specified Each 1.00 1.00 $1,250.00
Furnish and install 4"water
main gate valve; complete as
4400 specified Each 1.00 0.00 -1.00 $1.918.00 ($1,918.00)
Furnish and install 6"water
main gate valve; complete as
4401 specified Each 7.00 5.00 -2.00 $2,060.00 ($4,120.00)
Furnish and install 8"water
main gate valve; complete as
4402 specified Each 1.00 1.00, $2,430.00
Furnish and install 10"water
main gate valve; complete as
4403 specified Each 5.00 4.00 -1.00 $3,028.00 ($3,028.00)
Furnish and install 12"water
main gate valve; complete as
4404 specified Each 2.00 2.00 $3,508.00
Furnish and install 6"x 6"
tapping valve and sleeve;
4419 complete as specified Each 1.00 1.00 $2,504.00
Furnish and install 12"x 6"
tapping valve and sleeve;
4446 complete as specified Each 1.00 1.00 $2,675.00
Furnish and install 12"x 10"
tapping valve and sleeve;
4448 complete as specified Each 1.00 1.00 $4,078.00
Furnish and install hydrant;
4500 complete as specified Each 5.00 5.00 $4,508.00
Relocate existing hydrant;
4501 complete as specified Each 2.00 2.00 $924.00
Jack and bore 24"steel water
main casing pipe; complete Linear
4702 as specified Feet 110.00 110.00 $1,650.00
Remove water main; Linear
4920 complete as specified Feet 75.00 75.00 $194.00
Excavation special(water);
4990 complete as specified Tons 192.50 671.40 478.90 $16.00 $7,662.40
Furnish and install pull box
(steel); 24"x 36";complete
5016 as specified Each 44.00 41.00 -3.00 $763.00 ($2,289.00)
Adjust pull box; complete as
5025 specified Each 44.00 0.00 -44.00 $152.00 ($6,688.00)
Remove pull box; complete
5026 as specified Each 9.00 9.00 $102.00
Remove existing concrete
5027 base; complete as specified Each 15.00 15.00 $254.00
Furnish and install control
cabinet; complete as
5050 specified Each 3.00 3.00 $1,018.00
Furnish and install 2"
Schedule 40 PVC;complete Linear
5120 as specified Feet 1,020.00 1,020.00 $6.10
Furnish and install 2"
Schedule 80 PVC; complete Linear
5122 as specified Feet 250.00 250.00 $6.60
Furnish and install 3"
Schedule 40 PVC; complete Linear
5130 as specified Feet 2,370.00 2,370.00 $7.10
Page 8 of 13
CONTRACT 17-22 CHANGE ORDER#1
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE/N
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Furnish and install 3"
Schedule 80 PVC;complete Linear
5132 as specified Feet 1,545.00 1.545.00 $7.60
Connect to existing conduit;
5184 complete as specified Each 1.00 1.00 $183.00
Furnish and install 4 gauge
red-coated wire; complete as Linear
5230 specified Feet 3,300.00 3,000.00 -300.00 $2.10 ($630.00)
Furnish and install 4 gauge
blue-coated wire; complete Linear
5237 as specified Feet 3,300.00 3,000.00 -300.00 $2.10 ($630.00)
Furnish and install 6 gauge
green-coated wire;complete Linear
5242 as specified Feet 3,300.00 3,000.00 -300.00 $2.10 ($630.00)
Furnish and install 12 gauge
red-coated wire;complete as Linear
5270 specified Feet 426.00 426.00 $1.20
Furnish and install 12 gauge
green-coated wire; complete Linear
5272 as specified Feet 426.00 426.00 $1.20
Furnish and install 12 gauge
blue-coated wire; complete Linear
5277 as specified Feet 426.00 426.00 $1.20
Furnish and install 14 gauge
green-coated wire; complete Linear
5282 as specified Feet 1,265.00 1,415.00 150.00 $1.20 $180.00
Install controller and cabinet;
"CITY supplied";complete as
5320 specified Each 3.00 3.00 $2,070.00
Install control cabinet service;
"CITY supplied"; complete as
5325 specified Each 3.00 0.00 -3.00 $3.250.00 ($9,750.00)
Furnish and install 14 gauge
stranded single pair twisted
with shield; complete as Linear
5356 specified Feet 1,880.00 1,300.00 -580.00 $1.20 ($696.00)
Furnish and install 14-21
solid IMSA 19-1 Cable; Linear
5370 complete as specified Feet 1,800.00 2,200.00 400.00 $2.60 $1,040.00
Furnish and install 14-7 solid
IMSA 19-1 Cable; complete Linear
5378 as specified Feet 488.00 488.00 $1.80
Furnish and install 14-5 solid
IMSA 19-1 Cable; complete Linear
5380 as specified Feet 248.00 148.00 -100.00 $1.60 ($160.00)
Furnish and install 14-3 solid
IMSA 19-1 Cable; complete Linear
5382 as specified Feet 186.00 186.00 $1.60
Install single head fixture,
"City Supplied,"complete as
5400 specified Each 7.00 7.00 $78.00
Install pole and pole top light;
"CITY supplied"; complete as
5410 specified Each 12.00 12.00 $860.00
Install 10'traffic signal pole
with pedestal base; "CITY
supplied"; complete as
5420 specified Each 1.00 1.00 $404.00
Install 15'traffic signal pole
with pedestal base; "CITY
supplied"; complete as
5422 specified Each 4.00 4.00 $505.00
Page 9 of 13
CONTRACT 17-22 CHANGE ORDER#1
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Install 20'traffic signal pole
with transformer base; "CITY
supplied"; complete as
5424 specified Each 6.00 6.00 $986.00
Install 30'traffic signal pole
with transformer base;"CITY
supplied"; complete as
5426 specified Each 2.00 2.00 $986.00
Install 20'trombone arm;
"CITY supplied";complete as
5428 specified Each 3.00, 3.00 $306.00
Install 25'trombone arm;
"CITY supplied";complete as
5430 specified Each 5.00 5.00 $306.00
Install traffic control camera;
"CITY supplied"; complete as
5432 specified Each 2.00 0.00 -2.00 $404.00 ($808.00)
Install 5-section traffic signal
head; "CITY supplied";
5434 complete as specified Each 8.00 8.00 $164.00
Install 3-section traffic signal
head;"CITY supplied";
5436 complete as specified Each 16.00 16.00 $144.00
Install pedestrian signal head
with countdown timer; "CITY
supplied"; complete as
5438 specified Each 14.00 14.00 $144.00
Install pedestrian push
button; "CITY supplied";
5440 complete as specified Each 14.00 14.00 $208.00
Furnish and install Type 1
5500 Base;complete as specified Each 1.00 1.00 $1,245.00
Furnish and install Type 2
5502 Base;complete as specified Each 24.00 24.00 $1,245.00
Furnish and install Type 9
5506 Base; complete as specified Each 3.00 3.00 $2,485.00
Furnish and install Type 2
Modified Base; complete as
5508 specified Each 7.00 7.00 $2,485.00
Furnish and install GLR fuse
5600 holder; complete as specified Each 38.00 30.00 -8.00 $116.00 ($928.00)
Furnish and install 5A fuse;
5612 complete as specified Each 38.00 30.00 -8.00 $24.00 ($192.00)
SUBTOTAL-(BID ITEMS 1010-5612) $143,416.48 ($411,455.88)
NET DECREASE TO SECTION I: ($268,039.40)
ALTERNATE:
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Reinforcing 7"concrete
pavement on East 11th
Avenue; complete as Square
1301-A specified Yards 2,760.00 2,701.60 -58.40 $5.60 ($327.04)
ALTERNATE: SUBTOTAL $0.00 ($327.04)
Page 10 of 13
CONTRACT 17-22 CHANGE ORDER#1
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
NET DECREASE TO ALTERNATE: ($327.04)
ADDITIONAL WORK REQUIRED: CO#1
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Extra cost to provide 8"HES
concete pavement;complete Square
1-10000 as specified Yards 0.00 153.90 153.90 $3.00 $461.70
Extra cost to provide heated
concrete for sidewalk and
driveways; complete as Cubic
1-10001 specified Yards 0.00 298.50 298.50 $8.95 $2,671.58
Extra cost to provide single
layer poly for concrete
sidewalk; complete as Square
1-10002 specified Yards 0.00 9,368.20 9,368.20 $0.55 $5,152.51
Extra cost to provide single
layer poly for concrete
roadway and curb and gutter;
complete as specified Square
1-10003 Yards 0.00 1,051.10 1,051.10 $1.75 $1,839.43
Extra cost for cold weather
asphalt operatons; complete
1-10004 as specified Tons 0.00 261.92 261.92 $8.00 $2,095.36
Extra cost for 8"HES
concrete curb and gutter on
South Main Street; complete Square
1-10005 as specified Yards 0.00 215.50 215.50 $1.10 $237.05
Extra cost to take down and
re-install traffic control for
East 14th Avenue; complete Lump
1-10006 as specified Sum 0.00 1.00 1.00 $4,641.92 $4,641.92
Extra cost to remove and
replace damaged pavement
at South Park and Main Lump
1-10007 Street; complete as specified Sum 0.00 1.00 1.00 _ $500.00 $500.00
T&M#2 time and material
storm sewer undercut; Cubic
1-20000 complete as specified Yards 0.00 62.51 62.51 $29.40 $1,837.79
T&M#4 time and material
added steel plates; complete Lump
1-20001 as specified Sum 0.00 1.00 1.00 $3,850.00 $3,850.00
T&M#9 time and material
for fixing the blowout of the
existing storm sewer; Lump
1-20002 complete as specified Sum 0.00 1.00 1.00 $2,577.36 $2,577.36
T&M#10 time and materials
for adding structural angle
iron to the steel plates for
manholes under asphalt
pavements; complete as Lump
1-20003 specified Sum 0.00 1.00 1.00 $2,990.05 $2,990.05
T&M#16 time and materials
for fixing a deteriorated storm
manhole at 12th Avenue and
South Main Street; complete Lump
1-20004 as specified Sum 0.00 1.00 1.00 $1,117.85 $1,117.85
Page 11 of 13
•
CONTRACT 17-22 CHANGE ORDER#1
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
T&M#17 time and materials
for breaking apart existing
junction chambers which
were pulled out of the ground;
complete as specified Lump
1-20005 Sum 0.00 1.00 1.00 $845.52 $845.52
T&M#18 time and materials
for installing a temporary
connection from the new box
culvert to the existing storm
sewer on the west side of the Lump
1-20006 tracks; complete as specified Sum 0.00 1.00 1.00 $4,006.16 $4,006.16
T&M#19 time and materials
for installing a temporary
connection from the new box
culvert to the existing storm
sewer on the east side of the Lump
1-20007 tracks; complete as specified Sum 0.00 1.00 1.00 $8,755.42 $8,755.42
T&M#25A cost to
demobilize to the site(PTS); Lump
1-20008 complete as specified Sum 0.00 1.00 1.00 $5,295.00 $5,295.00
T&M#25B cost to set up
and remove pumps for the
system dewatering; complete Lump
1-20009 as specified Sum 0.00 1.00 1.00 $1,500.00 $1,500.00
T&M#25C cost to set up
and remove pumps and
generator for the ground
dewatering; complete as Lump
1-20010 specified Sum 0.00 1.00 1.00 $900.00 $900.00
T&M#25D cost to pick up
and return the steel plate for
the end of the box culvert; Lump
1-20011 complete as specified Sum 0.00 1.00 1.00 $336.00 $336.00
T&M#25E cost to remove
frost from both sides of the
railroad tracks: complete as Lump
1-20012 specified Sum 0.00 1.00 1.00 $3,058.80 $3,058.80
T&M#25F cost to deliver
84"pipe from Fernau Yard to
the site:complete as Lump
1-20013 specified Sum 0.00 1.00 1.00 $2,506.00 $2,506.00
T&M#25G cost to
demobilize and re-mobilize to
the site(Boremaster); Lump
1-20014 complete as specified Sum 0.00 1.00 1.00 $6,300.00 $6,300.00
T&M#25H cost for extra 84"
steel pipe: complete as Linear
1-20015 specified Feet 0.00 70.00 70.00 $829.50 $58,065.00
T&M#251 cost for welding
the 84"steel pipe;complete
1-20016 as specified Each 0.00 9.00 9.00 $3,780.00 $34,020.00
T&M#25J cost for installing
the rails for the 84"steel Lump
1-20017 pipe;complete as specified Sum 0.00 1.00 1.00 $14,175.00 $14,175.00
T&M#25K cost for installing
the 84"steel pipe;complete Linear
1-20018 as specified Feet 0.00 155.00 155.00 $552.00 $85,560.00
Page 12 of 13
• CONTRACT 17-22 CHANGE ORDER#1
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
T&M#25L cost for cutting
the front steel sheeting for
the installation of the 84"
steel pipe; complete as
1-20019 specified Each 0.00 1.00 1.00 $4,250.00 $4,250.00
T&M#21 cost for downtime
for AT&T conflict for 84"
storm sewer bore; complete Lump
1-20020 as specified Sum 0.00 1.00 1.00 $72,219.60 $72,219.60
T&M#11 cost for structural
engineering and extra
structural work at the railroad; Lump
1-20021 complete as specified Sum 0.00 1.00 1.00 $13,687.12 $13,687.12
Cost for excess Mac Wrap
joints wraps delivered to the
1-20022 City; complete as specified Each 0.00 7.00 7.00 $270.42 $1.892.94
T&M#1 time and materials
to lower 12"water main at the
interesection of 11th Avenue
and South Main Street
because of storm sewer
conflicts; complete as Lump
1-40001 specified Sum 0.00 1.00 1.00 $15,583.14 $15,583.14
T&M#3 time and materials
to cut out the existing hydrant
tee on East 11th Avenue; Lump
1-40002 complete as specified Sum 0.00 1.00 1.00 $2,341.02 $2,341.02
T&M#8 time and materials
to install temporary water for
Oshkosh Area School District
Maintenance Building; Lump
1-40003 complete as specified Sum 0.00 1.00 1.00 $1,686.97 $1,686.97
T&M#13 time and materials
to lower the water main at
14th and Main Street
Intersection;complete as Lump
1-40004 specified Sum 0.00 1.00 1.00 $6,492.93 $6,492.93
T&M#24 time and materials
to add extra boring of South
Main Sreet to the contract; Lump
1-50001 complete as specified Sum 0.00 1.00 1.00 $16,971.68 S16,971.68
ADDITIONAL WORK REQUIRED: CO#1 (ITEMS 1-10000-1-40003)-SUBTOTAL $390,420.90 $0.00
NET INCREASE TO CO#1: $390,420.90
NET INCREASE TO SECTION I: $533,837.38
NET DECREASE TO SECTION I: ($411,782.92)
NET INCREASE TO CONTRACT: $122,054.46
Page 13 of 13