Proposal for Replacement of Piezometer Monitoring Well PZ-10 at Timmerman Landfill
Dear Mr. Rabe,
AECOM Technical Services, Inc. (AECOM) has prepared this proposal for replacing piezometer monitoring well PZ-10
at the former Timmerman Landfill. This proposal provides a summary of the proposed scope of services and
estimated costs for replacing the well.
Background
AECOM has been assisting the City of Oshkosh(City)with environmental services related to the former Timmerman
Landfill since 1978. These services have included groundwater and methane monitoring, landfill cap thickness
verification, laboratory testing, data review, and closure planning. In response to the Wisconsin Department of Natural
Resources(WDNR)Notice of Violation dated August 2, 2006,AECOM completed a Site Assessment Report(SAR) in
compliance with Wisconsin Administrative Code Section NR 700 and subsequently installed three additional
groundwater monitoring wells. In 2008 and early 2009,AECOM completed the closure of the site under the WDNR
Remediation and Redevelopment(RR)program and the site was transferred to the WDNR Solid Waste Program. In
2010,AECOM recommended the abandonment of six monitoring wells. The WDNR subsequently requested
additional investigation regarding the presence of a passive methane collection trench, which AECOM completed
using test pits. Based on the results of the test pit investigation and AECOM's recommendation in 2010, the WDNR
approved the abandonment of the six wells and required the installation of two gas probes(in addition to the four
already installed at the site)for additional methane monitoring in a letter dated February 2013.
In the summer of 2017, a WDNR Solid Waste Engineer inspected the site. AECOM and City staff completed the site
inspection with the WDNR representative. All items that were identified during this inspection were corrected by
AECOM or City staff, and AECOM prepared a letter detailing the corrective actions and submitted it to the WDNR.
Piezometer Abandonment and Replacement
During an October 2018 monitoring event, piezometer PZ-10 was discovered to be damaged beyond repair. It
appeared the well and associated protector pipe had been hit by large equipment. AECOM notified the City that the
well had been compromised. Subsequently the well was abandoned and the WDNR was notified on October 26,
2018. The WDNR responded on October 29, 2018 with the following two options:
• Reinstall the well exactly how it was previously constructed, or
• Submit a plan modification to the department evaluating the abandonment of the well and any other changes
that may be requested to the current monitoring program.
AECOM reviewed the groundwater and methane sampling results and discussed the following options: reducing
monitoring, abandoning PZ-10, and/or reinstalling PZ-10. Because Vinyl Chloride was detected in the groundwater in
PZ-10 during the last sampling event,AECOM recommended reinstalling PZ-10. The WDNR concurred with this
recommendation on November 11, 2018. In addition, after a review of the recent monitoring program results for
groundwater and landfill gases, it is AECOM's recommendation not to pursue a Plan Modification request at this time.
In our opinion there is a very low potential that approval of a reduction in sampling will be granted by the WDNR.
AECOM will continue to review the data and pursue a plan modification when a higher degree of success is identified.
K:\PROPOSAL\City of Oshkosh\OPP-899022_Timmerman Well Replacement\OPP-899022_Timmerman
Well Replacment Proposal docx 1/4
AECOM
On November 16, 2018, James Rabe, City of Oshkosh notified the landowner, SMET Construction Services
Corporation, of the damaged well and the replacement plan.
Scope of Services
This proposal includes Project Management/WDNR communication, well abandonment of PZ-10, solicitation and
retention of a drilling subcontractor to install replacement well PZ-10R to a depth of 38 feet, assistance with and
subcontracting costs for disposal of well installation excess impacted soil, observation/documentation services during
well replacement, and well development.
Assumptions
This proposal and scope of work has been prepared on the following assumptions:
• WDNR reporting will be limited to submitting an Abandonment Form (Form 3300-005), Soil Boring Log (Form
4400-122)and Well and Development Installation (Form 4400-113A). No documentation report will be required.
• Site access will be granted.
• The City will directly pay for any review or submittal fees.
• The subcontract soil disposal budget is based on disposing of up to two(2)drums of impacted soil.
• The sampling costs associated with the new well (PZ-10R), including the field effort and subcontract laboratory
costs will be compensated under the 2018 Knapp Street Quarries and Timmerman Landfill Operations and
Maintenance Support agreement.
Schedule
The following is an estimated schedule for completing the scope of work outlined above:
Project Management/WDNR Communication—October through December, 2018
Well Abandonment—October 2018
Well Replacement—November 27-28, 2018
Well Development—December 3-5, 2018
Information Submittal to WDNR—December 13-14, 2018.
Estimated Fees
The following summarizes the proposed tasks and estimated fees:
Fee
Project Management/WDNR Communication $2,500
Senior Environmental Hydrogeologist 13 hours
Well Abandonment $500
Senior Environmental Technician 4 hours(including equipment and bentonite hole plug)
Subcontract Drilling Services
Cascade Drilling Technical Services $6,500
Subcontract Soil Disposal
Covanta/Waste Management $3,000
Drilling Observation/Documentation and Well Development $2,500
Senior Environmental Technician 25 hours(including supplies and equipment)
Total Estimated Project Fees $15,000
K.\PROPOSAL\City of Oshkosh\OPP-899022_Timmerman Well Replacement\OPP-899022_Timmerman
Well Replacment Proposal docx 2/4
AECOM
Terms and Conditions
If services to be provided under this proposal require the agents, employees, or contractors of AECOM to enter onto
the Project site, Client shall provide right-of-access to the site to AECOM, its employees, agents, and contractors, to
conduct the planned field observations or services. The services described in this proposal will be provided on a time-
and-material basis. AECOM will not exceed the above estimate without your authorization and approval. The
services provided will be performed in accordance with the approved Fee schedule and with the conditions of the
2009 City of Oshkosh Negotiated General Conditions of Service, which are expressly incorporated into, and are an
integral part of, our contract for professional services.
To initiate this work, please sign and return the attached Authorization to the AECOM Oshkosh, Wisconsin office. Our
understanding is that the City of Oshkosh will also issue a Purchase Order. Please reference the AECOM proposal
number, OPP-899022, in the Purchase Order that is forwarded to the AECOM Oshkosh Office. We are looking
forward to working with you and providing assistance with this project.
If you have any questions or need to clarify a point, please call any of the undersigned at 920-235-0270.
Yours sincerely,
COM Tech cal Services, Inc.
Paul Timm -- Kevin Brehm, P.E.
Account Manager Associate Vice President 01Ti
Enclosure: Authorization
K:\PROPOSAL\City of Oshkosh\OPP-899022_Timmerman Well Replacement\OPP-899022_Timmerman
Well Replacment Proposal.docx 3/4
AECOM
558 N Main Street
Oshkosh,Wisocnsin 54901
920.236.6710
Authorization
December 20, 2018
I hereby certify that the necessary provisions have been made to pay the liability, which will accrue under this contract.
I hereby authorize AECOM to proceed with the scope of work for the Replacement of Piezometer PZ-10 at
Timmerman Landfill as described in AECOM's proposal OPP-899022 dated December 20, 2018, with a budget
authorization of$15,000 under the general terms and conditions specified in the proposal.
P--7,4" 41--11--f"6-- ( /3`.1 I/
Sign ture Date
Mark A Rohloff
Print Name
City Manager
_______„ :
Title/0 anization - _
Ili . l . i '2/ ( ___D --Dc ) al
Signature 1 Date
Pamela R. Ubrig
Print Name
City Clerk
Tit rganization
/AO/
at r Date
Lynn A. Lorenson
Print Name
City Attorney
Title/Organization
,� RA 1I311q
Signature Date
Trena Larson
Print Name
Director of Finance
Title/Organization
K:\PROPOSAL\City of Oshkosh\OPP-899022_Timmerman Well Replacement\OPP-899022_Timmerman
Well Replacment Proposal.docx 4/4