January 4, 2019
Todd Dorner
Dorner, Inc.
PO Box 129
Luxemburg, WI 54217
RE: Change Order No. 1 (Final)
Contract 17-05
Dear Todd:
Enclosed is an executed copy of Change Order No. 1 (Final) between the City of Oshkosh and
Dorner, Inc. regarding the abovementioned project.
If you have any questions, please call our office at (920)236-5065.
Sincerely,
eaL6e—'(Th-j-
ames Rabe, P.E., CPESC
Director of Public Works RF7.
JAN 0 7 2019
JERAlt
CITY C" r . ' OFFICE
Enclosure: Change Order No. 1 (Final)
cc: Pam Ubrig, City Clerk (w/original)
Jennifer Messerschmidt, Assistant Finance Director (w/copy)
File (w/original)
I:\Engineering\2017CONTRACTS\17-052ndPaving\Project_Information\Contractlnfo\Change Orders\17- Page I of 1
05 Executed CO$1(Final)Ltr_1-419.docx
City Hall,215 Church Avenue P.O.Box 1130 Oshkosh,WI 54903-1130 http://www.ci.oshkosh.wi.us
TO: DORNER, INC. CHANGE ORDER#1 (FINAL)
PO BOX 129 DATE: DECEMBER 7,2018
LUXEMBURG,WI 54217
Your present contract with the City of Oshkosh,Contract No. 17-05, awarded March 28, 2017, is hereby amended
amended and changed as follows:
NET DECREASE TO SECTION I: ($579,541.42)
NET INCREASE TO SECTION I: $452,668.83
NET DECREASE TO CONTRACT ($126,872.59)
SECTION I TOTALS
BID TOTAL $6,270,243.32 $6,270,243.32
CO#1 ($126,872.59) ($126,872.59)
CONTRACT TOTAL $6,143,370.73 $6,143,370.73
CITY OF OSHKOSH
BY: ''''''••••—oa ----7��-l�6.,.f
City Man ger \.6...2
City Clerk
,� oved an a epted:
1L0/ on tractor
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh,Wisconsin,
under the within Change Order.
iRc . k,Ej-\_-\
Comptroll r
Approved as form:
Q_
City Atto
CONTRACT 17-05 CHANGE ORDER#1 (FINAL)
17-05
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Clearing;complete as Inch
1011 specified Diameter 30.00 42.00 12.00 $20.39 $244.68
Grubbing;complete as Inch
1021 specified Diameter 30.00 42.00 12.00 $12.24 $146.88
Removing pavement; Square
1100 complete as specified Yards 19,500.00 19,723.20 223.20 $2.45 $546.84
Removing railroad rails; Linear
1101 complete as specified Feet 1,600.00 825.00 -775.00 $3.06 ($2,371.50)
Removing railroad ties;
1102 complete as specified Tons 50.00 22.81 -27.19 $30.59 ($831.74)
Hauling removed concrete
pavement;complete as Square
1103A specified Yards 8,640.00 9,615.40 975.40 $0.01 $9.75
Hauling removed concrete
pavement;complete as Square
1103E specified Yards 8,000.00 10,107.80 2107.80 $0.51 $1,074.98
Stripping topsoil and
providing gravel lay down Lump
1104 area;complete as specified Sum 1.00 1.00 $45,887.00
Removing concrete and
asphalt sidewalk and
driveway;complete as Square
1120 specified Feet 72,450.00 76,969.80 4519.80 $0.41 $1,853.12
Unclassified excavation; Cubic
1200 complete as specified Yards 6,670.00 6,477.50 -192.50 $12.95 ($2,492.88)
Excavation special(paving);
1220 complete as specified Tons 850.00 0.00 -850.00 $20.39 ($17,331.50)
7"concrete pavement;with
5"CABC and grading; Square
1301 complete as specified Yards 5,665.00 5,725.50 60.50 $36.27 $2,194.34
8"concrete pavement;with
6"CABC and grading; Square
1311 complete as specified Yards 9,870.00 10,013.90 143.90 $38.74 $5,574.69
8"concrete pavement HES;
with 6"CABC and grading; Square
1313 complete as specified Yards 2,115.00 2,328.00 213.00 $42.31 $9,012.03
8"concrete pavement
doweled;with 6"CABC and
grading;complete as Square
1314A specified Yards 4,020.00 0.00 -4,020.00 $41.70 ($167,634.00)
8"concrete pavement
doweled;HES;with 6"CABC
and grading;complete as Square
1315 specified Yards 750.00 4,745.50 3995.50 $45.06 $180,037.23
Concrete pavement gaps;
1334 complete as specified Each 4.00 3.00 -1.00 $1,020.00 ($1,020.00)
Crushed aggregate base
course;complete as
1340 specified Tons 4,200.00 132.83 -4,067.17 $12.03 ($48,928.06)
Pavement ties;complete as
1350 specified Each 85.00 166.00 81.00 $7.14 $578.34
Drilled dowel bars; 1";
1352 complete as specified Each 100.00 44.00 -56.00 $10.20 ($571.20)
Page 1 of 15
CONTRACT 17-05 CHANGE ORDER#1 (FINAL)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
No.4 reinforcing rods-
deformed,epoxy-coated; Linear
1550 complete as specified Feet 5,300.00 5,880.00 580.00 $1.22 $707.60
Drilled No.4 sidewalk tie bars
-deformed,epoxy-coated;
1560 complete as specified Each 390.00 267.00 -123.00 $3.57 ($439.11)
Furnish and install tree;
1600 complete as specified Each 2.00 0.00 -2.00 $407.88 ($815.76)
Locate existing property
monuments;complete as
1650 specified Each 55.00 65.00 10.00 $152.96 $1,529.60
Replace existing property
monuments;complete as
1652 specified Each 33.00 24.00 -9.00 $50.99 ($458.91)
Sawing existing pavement; Linear
1700 complete as specified Feet 1,760.00 1,979.20 219.20 $1.84 $403.33
Sawing concrete pavement
full depth;complete as Linear
1710 specified Feet 745.00 1,074.00 329.00 $2.24 $736.96
Tack coat;complete as
1900 specified Gallons 155.00 28.00 -127.00 $5.06 ($642.62)
5"asphaltic pavement MT
with 10"CABC and grading; Square
1905 complete as specified Yards 540.00 527.40 -12.60 $39.77 ($501.10)
5"asphaltic transition MT
with 10"CABC and grading; Square
1910 complete as specified Yards 215.00 283.50 68.50 $40.93 $2,803.71
4"asphaltic transition LT with
10"CABC and grading; Square
1911 complete as specified Yards 85.00 97.90 12.90 $37.38 $482.20
5"asphaltic surface MT with
6"CABC and grading; Square
1915 complete as specified Yards 1,240.00 1,110.10 -129.90 $34.37 ($4,464.66)
4"asphaltic surface LT with
6"CABC and grading; Square
1916 complete as specified Yards 135.00 231.50 96.50 $36.41 $3,513.57
2"asphaltic surface LT with
6"CABC and grading; Square
1917 complete as specified Yards 250.00 123.70 -126.30 $28.20 ($3,561.66)
Asphaltic cold weather Square
1918 paving;complete as specified Yards 215.00 0.00 -215.00 $38.71 ($8,322.65)
Furnish and install 10"storm Linear
2002 sewer;complete as specified Feet 160.00 215.00 55.00 $50.00 $2,750.00
Furnish and install 12"storm Linear
2003 sewer;complete as specified Feet 1,385.00 1,300.70 -84.30 $50.00 ($4,215.00)
Furnish and install 18"storm Linear
2009 sewer;complete as specified Feet 925.00 908.70 -16.30 $64.00 ($1,043.20)
Furnish and install 21"storm Linear
2012 sewer;complete as specified Feet 330.00 323.30 -6.70 $64.00 ($428.80)
Furnish and install 24"storm Linear
2015 sewer;complete as specified Feet 1,130.00 1,342.30 212.30 $72.00 $15,285.60
Furnish and install 30"storm Linear
2021 sewer;complete as specified Feet 390.00 84.60 -305.40 $99.00 ($30,234.60)
Furnish and install 36"storm Linear
2024 sewer;complete as specified Feet 60.00 0.00 -60.00 $104.00 ($6,240.00)
Page 3 of 15
CONTRACT 17-05 CHANGE ORDER#1 (FINAL)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Furnish and install 54"storm
sewer casing pipe by
trenchless methods; Linear
2361 complete as specified Feet 80.00 0.00 -80.00 $750.00 ($60,000.00)
Furnish and install 6"storm
sewer lateral;complete as Linear
2400 specified Feet 1,680.00 1,748.50 68.50 $46.00 $3,151.00
Fumish and install 8"storm
sewer lateral;complete as Linear
2402 specified Feet 230.00 53.50 -176.50 $51.00 ($9,001.50)
Furnish and install storm
sewer marker balls;complete
2404 as specified Each 135.00 135.00 $25.00
Furnish and install storm
sewer clay dams;complete
2406 as specified Each 71.00 61.00 -10.00 $100.00 ($1,000.00)
Furnish and install storm
sewer lateral inlet;complete
2408 as specified Each 43.00 35.00 -8.00 $475.00 ($3,800.00)
Storm lateral inlet
adjustments;complete as
2414 specified Each 12.00 0.00 -12.00 $200.00 ($2,400.00)
Fumish;install;maintain;and
remove Type D modified inlet
protection;complete as
2508 specified Each 155.00 140.00 -15.00 $71.00 ($1,065.00)
Sediment removal-Type D
modified inlet protection;
2510 complete as specified Each 155.00 24.00 -131.00 $5.00 ($655.00)
Furnish;install; maintain;and
remove stone tracking pad;
2512 complete as specified Each 1.00 1.00 $1,275.00
Furnish;install;maintain;and
remove silt fence;complete Linear
2514 as specified Feet 500.00 0.00 -500.00 $2.55 ($1,275.00)
Furnish;install;maintain;and
remove stone bag;complete
2516 as specified Each 25.00 34.00 9.00 $5.00 $45.00
Furnish;install;maintain;and
remove 12"diameter
sediment logs;complete as Linear
2518 specified Feet 50.00 50.00 $5.00
Rock excavation;complete Cubic
2750 as specified Yards 50.00 0.00 -50.00 $0.01 ($0.50)
Abandon 8"-12"storm Linear
2800 sewer;complete as specified Feet 1,375.00 1,583.00 208.00 $7.00 $1,456.00
Abandon 15"and larger
storm sewer;complete as Linear
2802 specified Feet 1,240.00 1,384.00 144.00 $15.00 $2,160.00
Remove 30"and smaller
storm sewer;complete as Linear
2804 specified Feet 500.00 545.00 45.00 $15.00 $675.00
Remove 33"-60"storm Linear
2806 sewer;complete as specified Feet 40.00 100.00 60.00 $20.00 $1,200.00
Abandon storm sewer
manholes and inlets;
2810 complete as specified Each 8.00 14.00 6.00 $400.00 $2,400.00
Page 5 of 15
CONTRACT 17-05 CHANGE ORDER#1 (FINAL)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Furnish and install internal
sanitary sewer manhole
chimney seal extension;
3120 complete as specified Each 3.00 0.00 -3.00 $300.00 ($900.00)
Rebuild sanitary sewer
manhole(4'diameter); Vertical
3136 complete as specified Feet 20.00 5.20 -14.80 $400.00 ($5,920.00)
Furnish and install 8"x 6"
sanitary sewer factory wyes
or tees;complete as
3210 specified Each 35.00 34.00 -1.00 $77.00 ($77.00)
Furnish and install 10"x 6"
sanitary sewer factory wyes
or tees;complete as
3212 specified Each 7.00 6.00 -1.00 $162.00 ($162.00)
Furnish and install 12"x 6"
sanitary sewer factory wyes
or tees;complete as
3214 specified Each 28.00 15.00 -13.00 $152.00 ($1,976.00)
Furnish and install 6"sanitary
sewer"Insert-A-Tee"or"Kor-
N-Tee";complete as
3222 specified Each 9.00 18.00 9.00 $190.00 $1,710.00
Furnish and install 4"/6"
sanitary sewer lateral(relay); Linear
3234 complete as specified Feet 2,561.00 2,349.00 -212.00 $80.00 ($16,960.00)
Furnish and install 4"/6"
sanitary sewer riser(relay); Linear
3235 complete as specified Feet 98.00 33.00 -65.00 $95.00 ($6,175.00)
Furnish and install sanitary
sewer lateral marker balls;
3236 complete as specified Each 148.00 151.00 3.00 $25.00 $75.00
Furnish and install clay
3238 dams;complete as specified Each 75.00 73.00 -2.00 $100.00 ($200.00)
Furnish and install
connection to existing 8"
3300 mains;complete as specified Each 3.00 2.00 -1.00 $500.00 ($500.00)
Furnish and install
connection to existing 10"
3302 mains;complete as specified Each 3.00 3.00 $600.00
Furnish and install
connection to existing 12"
3304 mains;complete as specified Each 4.00 5.00 1.00 $700.00 $700.00
Furnish and install
connection to existing 18"
sanitary sewer mains;
3308 complete as specified Each 2.00 2.00 $1,440.00
Furnish and install
connection to existing 24"
sanitary sewer mains;
3312 complete as specified Each 3.00 1.00 -2.00 $3,530.00 ($7,060.00)
Furnish and install 10"
sanitary sewer open cut
casing pipes;complete as Linear
3404 specified Feet 160.00 236.00 76.00 $125.00 $9,500.00
Furnish and install 16"
sanitary sewer open cut
casing pipes;complete as Linear
3408 specified Feet 20.00 14.00 -6.00 $160.00 ($960.00)
Page 7 of 15
CONTRACT 17-05 CHANGE ORDER#1 (FINAL)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Furnish and install 16"ductile
iron water main(relay)with
polywrap;complete as Linear
4010 specified Feet 295.00 277.00 -18.00 $129.00 ($2,322.00)
Furnish and install 1"water
service(relay);complete as Linear
4036 specified Feet 1,987.00 1,621.50 -365.50 $53.00 ($19,371.50)
Furnish and install 1-1/4"
water service(relay); Linear
4037 complete as specified Feet 281.00 380.00 99.00 $55.00 $5,445.00
Furnish and install 1-1/2"
water service(relay); Linear
4038 complete as specified Feet 96.00 193.00 97.00 $57.00 $5,529.00
Furnish and install 2"water
service(new);complete as Linear
4046 specified Feet 240.00 116.00 -124.00 $61.00 ($7,564.00)
Furnish and install 1"
corporation and stop box;
4048 complete as specified Each 59.00 51.00 -8.00 $580.00 ($4,640.00)
Furnish and install 1-1/4"
corporation and stop box;
4050 complete as specified Each 7.00 10.00 3.00 $950.00 $2,850.00
Furnish and install 1-1/2"
corporation and stop box;
4051 complete as specified Each 3.00 4.00 1.00 $1,000.00 $1,000.00
Furnish and install 2"
corporation and stop box;
4053 complete as specified Each 5.00 3.00 -2.00 $1,300.00 ($2,600.00)
Furnish and install water
service clay dams;complete
4055 as specified Each 70.00 66.00 -4.00 $100.00 ($400.00)
Furnish and install
connections to existing 4"
water main;complete as
4056 specified Each 2.00 5.00 3.00 $1,500.00 $4,500.00
Furnish and install
connections to existing 6"
water main;complete as
4058 specified Each 4.00 1.00 -3.00 $1,575.00 ($4,725.00)
Furnish and install
connections to existing 8"
water main;complete as
4060 specified Each 12.00 9.00 -3.00 $1,600.00 ($4,800.00)
Furnish and install
connections to existing 10"
water main;complete as
4062 specified Each 6.00 5.00 -1.00 $2,000.00 ($2,000.00)
Furnish and install
connections to existing 16"
water main;complete as
4066 specified Each 3.00 3.00 $3,000.00
Furnish and install 8"x 6"
water main tee;complete as
4110 specified Each 4.00 3.00 -1.00 $452.00 ($452.00)
Furnish and install 8"x 8"
water main tee;complete as
4111 specified Each 5.00 4.00 -1.00 $460.00 ($460.00)
Furnish and install 10"x 4"
water main tee;complete as
4118 specified Each 1.00 0.00 -1.00 $557.00 ($557.00)
Page 9 of 15
CONTRACT 17-05 CHANGE ORDER#1 (FINAL)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Furnish and install 6"water
main gate valve;complete as
4401 specified Each 16.00 14.00 -2.00 $1,000.00 ($2,000.00)
Furnish and install 8"water
main gate valve;complete as
4402 specified Each 24.00 15.00 -9.00 $1,367.00 ($12,303.00)
Furnish and install 10"water
main gate valve;complete as
4403 specified Each 14.00 13.00 -1.00 $1,848.00 ($1,848.00)
Furnish and install 16"water
main gate valve;complete as
4405 specified Each 2.00 2.00 $7,000.00
Furnish and install 16"x 10"
tapping valve and sleeve;
4457 complete as specified Each 1.00 1.00 $6,200.00
Furnish and install hydrant;
4500 complete as specified Each 14.00 12.00 -2.00 $3,350.00 ($6,700.00)
Jack and bore 24"steel water
main casing pipe;complete Linear
4702 as specified Feet 80.00 0.00 -80.00 $500.00 ($40,000.00)
Furnish and install 2"water
main casing pipe;complete Linear
4712 as specified Feet 70.00 0.00 -70.00 $50.00 ($3,500.00)
Furnish and install 4"water
main casing pipe;complete Linear
4714 as specified Feet 100.00 120.00 20.00 $75.00 $1,500.00
Furnish and install 8"water
main casing pipe;complete Linear
4718 as specified Feet 25.00 30.00 5.00 $100.00 $500.00
Furnish and install 16"water
main casing pipe;complete Linear
4724 as specified Feet 65.00 42.00 -23.00 $150.00 ($3,450.00)
Furnish and install 20"water
main casing pipe;complete Linear
4728 as specified Feet 30.00 14.00 -16.00 $170.00 ($2,720.00)
Furnish and install 24"water
main casing pipe;complete Linear
4730 as specified Feet 50.00 50.00 $175.00
Fumish and install 30"water
main casing pipe;complete Linear
4732 as specified Feet 25.00 15.00 -10.00 $275.00 ($2,750.00)
Rock excavation;complete Cubic
4800 as specified Yards 25.00 0.00 -25.00 $0.01 ($0.25)
Abandon water main on
Dickinson Avenue;complete Lump
4900 as specified Sum 1.00 1.00 $2,600.00
Abandon water main on
Maricopa Drive;complete as Lump
4902 specified Sum 1.00 1.00 $5,500.00
Abandon water main on East
Murdock Avenue;complete Lump
4904 as specified Sum 1.00 1.00 $4,500.00
Abandon water main on New
York Avenue;complete as Lump
4906 specified Sum 1.00 1.00 $3,500.00
Remove water main; Linear
4920 complete as specified Feet 675.00 250.00 -425.00 $37.00 ($15,725.00)
Page 11 of 15
CONTRACT 17-05 CHANGE ORDER#1 (FINAL)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Furnish and install Type 2
5502B Base;complete as specified Each 7.00 8.00 1.00 $790.00 $790.00
Furnish and install pull box
(steel);24"x 42";complete
5018C as specified Each 4.00 4.00 $663.00
Adjust pull box;complete as
5025C specified Each 4.00 0.00 -4.00 $127.00 ($508.00)
Furnish and install 2"
Schedule 40 PVC;complete Linear
5120C as specified Feet 40.00 64.00 24.00 $5.10 $122.40
Furnish and install pulling Linear
5299C twine;complete as specified Feet 40.00 0.00 -40.00 $2.04 ($81.60)
Furnish and install Type 2
5502C Base;complete as specified Each 7.00 7.00 $790.00
SECTION I(BID ITEMS 1011 -5502C)-SUBTOTAL: $433,204.10 ($1,012,745.52)
NET DECREASE TO SECTION: ($579,541.42)
ADDITIONAL WORK REQUIRED:CO#1
ITEM DESCRIPTION UNIT BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
TM 5-11 Foundation wall
removal on New York; Lump
1-10000 complete as specified Sum 0.00 1.00 1.00 $2,478.00 $2,478.00
Extra time and materials to
install 4"HES concrete; Square
1-10001 complete as specified Feet 0.00 666.70 666.70 $0.20 $133.34
CO-13 Extra cost to heat the
concrete for sidewalks and
driveways;complete as Cubic
1-10002 specified Yard 0.00 225.50 225.50 $8.95 $2,018.23
CO-13 Extra time and
material to single layer cover
sidewalk and driveways; Square
1-10003 complete as specified Feet 0.00 3,028.50 3028.50 $0.55 $1,665.68
CO-13 Extra time and
material to double layer cover
sidewalk and driveways; Square
1-10004 complete as specified Feet 0.00 3,911.70 3911.70 $1.10 $4,302.87
CO-9 Extra cost to heat the
concrete for East Murdock
Avenue Paving;complete as Cubic
1-10005 specified Yard 0.00 1,535.00 1535.00 $3.45 $5,295.75
CO-9 Extra time and material
to single layer cover the
concrete for East Murdock
Avenue Paving;complete as Square
1-10006 specified Yard 0.00 6,028.30 6028.30 $1.75 $10,549.53
Extra time and materials to
install 18"HES curb and
gutter on East Murdock
Avenue;complete as Linear
1-10007 specified Feet 0.00 2,072.00 2072.00 $1.05 $2,175.60
Page 13of15
CONTRACT 17-05 CHANGE ORDER#1 (FINAL)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
TM 10-3 24"x18"Sanitary
sewer drop;complete as Lump
1-30005 specified Sum 0.00 1.00 1.00 $5,370.68 $5,370.68
TM 10-16 EJM Downtime for Lump
1-30006 AT&T conflict Sum 0.00 1.00 1.00 $8,738.80 $8,738.80
TM 10-16 EJM Downtime for Lump
1-30007 railroad not providing flagging Sum 0.00 1.00 1.00 $5,243.28 $5,243.28
TM 2-21 Sanitary spot repair Lump
1-30008 on Minerva Sum 0.00 1.00 1.00 $8,255.19 $8,255.19
Furnish and install 8"x 4"
water main tee;complete as
1-4109 specified Each 0.00 1.00 1.00 $444.00 $444.00
Furnish and install 6"90
degree water main bend;
1-4245 complete as specified Each 0.00 1.00 1.00 $230.00 $230.00
Furnish and install 8"90
degree water main bend;
1-4246 complete as specified Each 0.00 2.00 2.00 $295.00 $590.00
Furnish and install 6"x 4"
water main reducer;complete
1-4262 as specified Each 0.00 2.00 2.00 $225.00 $450.00
CO#2 temporary water
Maricopa;complete as Lump
1-40000 specified Sum 0.00 1.00 1.00 $18,100.00 $18,100.00
Furnish and install 24"casing
pipe by slipping through the
existing storm sewer: Linear
1-40001 complete as specified Feet 0.00 110.00 110.00 $200.00 $22,000.00
TM 4-28 Hit
unmarked/unknown 4"
watermain;complete as Lump
1-40002 specified Sum 0.00 1.00 1.00 $1,025.00 $1,025.00
TM 7-28 Fix a leaking Flare Lump
1-40003 Union;complete as specified Sum 0.00 1.00 1.00 $925.25 $925.25
TM 9-19 remove valves for
Muza Metal as the services
are not needed;complete as Lump
1-40004 specified Sum 0.00 1.00 1.00 $2,339.00 $2,339.00
TM 10-11 downtime for
watermain break on the
existing main;complete as Lump
1-40005 specified Sum 0.00 1.00 1.00 $1,876.25 $1,876.25
Furnish and install 6"casing
by slipping through the
existing storm sewer: Linear
1-50000 complete as specified Feet 0.00 105.00 105.00 $95.00 $9,975.00
ADDITIONAL WORK: CO#1 (ITEMS 1-10000-1-50000)-SUBTOTAL $452,668.83 $0.00
NET INCREASE TO CO#1: $452,668.83
NET INCREASE TO SECTION I $885,872.93
NET DECREASE TO SECTION I ($1,012,745.52)
NET DECREASE TO CONTRACT: ($126,872.59)
Page 15 of 15