HomeMy WebLinkAboutItem II PLAN COMMISSION STAFF REPORT FEBRUARY 5,2019 ITEM II: PUBLIC HEARING:ZONE CHANGE FROM HEAVY INDUSTRIAL (HI) TO HEAVY INDUSTRIAL WITH A PLANNED DEVELOPMENT OVERLAY(HI-PD) AND GENERAL DEVELOPMENT PLAN APPROVAL FOR INDUSTRIAL USE LOCATED NORTH OF THE RAILROAD TRACKS EAST/WEST OF CLAIRVILLE ROAD AND STATE HIGHWAY 91 INTERSECTION. COMMONLY KNOWN AS THE SOUTHWEST INDUSTRIAL PARK GENERAL INFORMATION Applicant/Owner: City of Oshkosh—Department of Community Development Action(s) Requested: The applicant requests a zone change from the existing Heavy Industrial District(HI) to Heavy Industrial with a Planned Development Overlay(HI-PD) and approval for a General Development Plan for the Southwest Industrial Park. Applicable Ordinance Provisions: The Zoning Ordinance does not establish criteria relative to appropriateness of changing zoning from one classification to another but relies on the Comprehensive Plan and good planning principles. Planned Development standards are found in Section 30-387 of the Zoning Ordinance. Property Location and Type: The subject area is currently zoned Heavy Industrial(HI) and consists of multiple parcels encompassing approximately 260 acres,located within the City's Southwest Industrial Park.The subject area consists of land designated for industrial development. The surrounding area consists of agricultural,residential and institutional uses. The 2040 Comprehensive Land Use Plan recommends Industrial use for the subject area. Subject Site Existing Land Use Zoning Vacant land&Transload Facility HI Adjacent Land Use and Zoning Existing Uses Zoning North_....... Family&Institutional uses....................................—................__.............SR-3,.._I,A-2(County)...._......................._.........._...................._ South Industrial uses HI,I, ................._........_........__........_........_..........................__...._..._.......---.............__..........__....—....__......__.........................._.......__................._....__..................._................................................................. _--._...._..---...................._............_.................._ East Industrial uses and vacant land RH,HI ............_....._...---.......... __....................__...........................-................................._.........._......-- .._...........................__......._...............__._......................._.................................................................._............----...._...................._......_._.._..._......._. West Vacant land A-2(County) Page 1 Comprehensive Plan Land Use Recommendation > Land Use 2040 Land Use Recommendation Industrial ANALYSIS Use/General Development Standards The intent of the proposed Planned Development is to aid in the development of the Southwest Industrial Park(SWIP). Since the completion of the transload facility the City has been an increased interest in rail related businesses inquiring about property located within the industrial park. In order to help facilitate that development and be considerate of the properties surrounding the SWIP,the Department of Community Development is proposing to rezone the remaining City owned property to include a Planned Development Overlay and establish a baseline General Development Plan. Staff has identified several Base Standard Modifications(BSM) which should assist in developing the industrial park. These BSM's would apply park wide and any future development would be allowed to take advantage of them. First, staff is suggesting to reduce the front yard setback, specifically for vehicle access drives to 20' opposed to the 30' required by code. Industrial uses and specifically rail related industrial uses typically have a greater demand on maneuverability within the site and allowing a 10' reduction for access drive will allow for greater flexibility in developing site layouts. In order to offset this reduction, staff suggests any development which wishes to utilize the reduced setback provide 40 points of street frontage landscaping opposed to the 30 points typically required. In essence,this is a 33%reduction in setback for a 33%increase in required landscaping. These types of uses also typically have more rail spurs than a typical industrial development. In order to aid in the development of these types of uses, staff suggests a condition allowing rail spurs to be permitted within side and rear yard setbacks. Again,this provides greater flexibility in developing site layouts that require rail spurs. Staff is proposing a condition be added requiring all final landscaping plans shall be approved by the Department of Community Development and the Department of Community Development shall have the authority to reallocate the required landscaping points to those areas that are most impactful on adjacent developments. Staff is requesting this condition be added as the unique site layouts and types of uses that may be located within the industrial park can potentially have very different impacts on adjacent properties. This will allow staff the flexibility to work with developers to mitigate possible impacts on adjacent properties without burdening developers with additional landscaping costs/requirements. Finally, to aid in timely development of the industrial park staff is proposing a final condition be added allowing the Department of Community Development to waive the required Specific Implementation Plan(SIP)for any development which meets all the above requirements in conjunction with all other base code requirements. If an applicant is able to meet all base code ITEM II-Rasone.GDP STVIP 2 Page 2 requirements and the additional requirements listed within the General Development Plan the applicant would be permitted to proceed to Site Plan Review FINDINGS/RECOMMENDATION/CONDITIONS In its review and recommendation to the Common Council on an application for a Planned Development district, staff recommends the Plan Commission make the following findings based on the criteria established by Chapter 30-387(C)(6): (a) The proposed Planned Development project is consistent with the overall purpose and intent of this Chapter. (b) The proposed Planned Development project is consistent with the City's Comprehensive Plan and other area plans. (It is the responsibility of the City to determine such consistency.) (c) The proposed Planned Development project would maintain the desired relationships between land uses,land use densities and intensities, and land use impacts in the environs of the subject site. (d)Adequate public infrastructure is or will be available to accommodate the range of uses being proposed for the Planned Development project,including but not limited to public sewer and water and public roads. (e) The proposed Planned Development project will incorporate appropriate and adequate buffers and transitions between areas of different land uses and development densities/intensities. (f)The proposed Planned Development project design does not detract from areas of natural beauty surrounding the site. (g)The proposed architecture and character of the proposed Planned Development project is compatible with adjacent/nearby development. (h)The proposed Planned Development project will positively contribute to and not detract from the physical appearance and functional arrangement of development in the area. (i)The proposed Planned Development project will produce significant benefits in terms of environmental design and significant alternative approaches to addressing development performance that relate to and more than compensate for any requested exceptions/base standard modifications variation of any standard or regulation of this Chapter. (j) For Planned Development projects that are proposed to be developed in phases, the applicant can provide a timeline for development and can demonstrate that the project would be successful even if all phases were not or could not be completed. Staff recommends approval of the rezone and General Development Plan with the findings listed above and the proposed following conditions: 1. Base Standard Modification to reduce the front yard setback for access drives from 30' to 20'.Any development which chooses to utilize this reduction shall increase the required Street Frontage landscaping from 30 points per 100' of frontage to 40 points per 100' of frontage. 2. Base Standard Modification to allow rail spurs within the side and year yard setbacks. 3. Final landscaping plans shall be approved by the Department of Community Development and the Department of Community Development shall have the authority to reallocate the ITEM77-Remne.GDP SJY7P 3 Page 3 required landscaping points to those areas needed to mitigate possible impacts on adjacent properties or right of way. 4. The Department of Community Development shall be permitted to waive the required Specific Implementation Plan (SIP)for any development which meets all the above requirements in conjunction with all other base code requirements. ITEM II-Rersone.GDP S{VIP 4 Page 4 GDP/REZONE CYPRESS HOMES. FANTASTIC SIX LLC SW INDUSTRIAL PARK 1230 W COLLEGE AVE D N1844 MALONEY RD PC:02-05-19 APPLETON WI 54914 KAUKAUNA WI 54130 MARK A/LISA L BRZOSTOWSKI -OSHKOSH COMMUNITY YMCA OSHKOSH OFFICE BUILDING LLC 2164 MORNINGSTAR LN 324 WASHINGTON AVE 2990 UNIVERSAL ST C OSHKOSH WI54904 OSHKOSH WI54901 OSHKOSH WI 54904 STATE OF WISCONSIN CITY OF OSHKOSH WITTMAN AIRPORT OSH PO BOX 3530 PO BOX 1130 525 W 20TH AVE OSHKOSH WI 54903 OSHKOSH WI 54903 OSHKOSH WI 54902 TOWN OF NEKIMI TOWN OF ALGOMA TOWN CLERK TOWN CLERK 3790 PICKETT RD 15 N OAKWOOD RD OSHKOSH WI 54904 OSHKOSH WI 54904 Page 5 wum KIV7AUM i tali Oshkosh City Limit ,C y i F...................... ............ ..................... y .............. f l I n ....... ................... _.:. 91 ................... ................... I j E A' ^� r N 1 in=0.14mi Ulf1 in=720ft '� City of Oshkosh maps and data are intended to be used for general identification purposes only,and cif the City of Oshkosh assumes no liability for the accuracy of the information. Those using the cif Printing Date: 12/10/2018 information are responsible for verifying accuracy. For full disclaimer please go to CShk©S�l www.ci.oshkosh.wi.us/GlSdisclaimer Prepared by:City of Oshkosh,WI s JAGIS\Planning\Plan Commission Site Plan Map Template\Plan Commission Site Plan Map Template.mxd User:minak Page 6 _114 RAXLE �' I i �. MR2A. i t 0 Kl r SR-3 MR 121 SR-5�% SR-3i i �y i 0 A _ MR-12-PD MR-12 `..... �r SR-5 ; ...... —. - r� K --SR-5 _ 1. �.....: ........... ..... i ; — _ E.......-fRt..._.....` _.... ........ W J SR-3 I MR-12-PD ` MR-12 _,. _.........._ ............ MR 12 r- yrr. _ RH i � V r HI { .... .. ..................... .....__......_ p, �1............._._ r i BP__...........91 ....... r _ i BP�PD �....—._ ' MR-12-PD N tin=0.21mi 1in= 1,100ft ` City of Oshkosh maps and data are intended to be used for general identification purposes only,and €t� the City of Oshkosh assumes no liability for the accuracy of the information. Those using the Printing Date: 12/10/2018 information are responsible for verifying accuracy. For full disclaimer please go to ��QJ www.ci.oshkosh.wi.us/GISdisclaimer Prepared by:City of Oshkosh,WI JAGISTIanningRan Commission Site Plan Map TemplateRan Commission Site Plan Map Template.mxd User:minak Page 7 r W r K K�. i a i y s' a, r Y r r sx � � r N 1 in �n1J31 t.� r1� rlf^11i ° - 1 in=700 ft s City of Oshkosh maps and data are intended to be used for general identification purposes only,and the City of Oshkosh assumes no liability for the accuracy of the information. Those using the c>r information are responsible for verifying accuracy. For full disclaimer please go to Printing Date:12/10/2018 5t 1I/rNs t www.ci.oshkosh.wi.us/GlSdisclaimer Prepared by:City of Oshkosh,WI �, k JAGISTIanningRan Commission Site Plan Map TemplateRan Commission Site Plan Map Template.mxd User:minak Page 8