No 104938
BUILDING PERMIT - APPLICATION AND RECORD
Owner WITZEL AVE CENTER LLC
Create Date
1 0/20/2003
Designer
Contractor
R J ALBRIGHT INC.
Category
232 - Alteration Stores & Customer Service
Plan
Type
18 Building
0 Sign
0 Canopy
0 Fence
0 Raze
Zoning
Class of Const:
Size
Unfinished/Basement 0 Sq.Ft. Rooms 0 Height 0 Ft.
Finished/Living ~ Sq. Ft. Bedrooms 0 Stories
Garage ~ Sq. Ft. Baths 0
U Projection 1
Canopies
0
Signs
0
Foundation
8 Poured Concrete 0 Floating Slab
0 Concrete Block 0 Post
0 Pier
0 Treated Wood
0 Other
Occupancy Permit
Not Required
Flood Plain
Height Permit
Park Dedication
# Dwelling Units
0
# Structures
0
2069 Witzel/ Alteration to create white box for this tenant space. H&R Block.
Use/Nature
of Work
HVAC Contractor
Plumbing Contractor
Electric Contractor
Fees: Valuation
$27,000.00
Plan Approval
$0.00 Permit Fee Paid
$116.00 Park Dedication
$0.00
Issued By:
Date 1 0/23/2003
Final/O.P. 00/00/0000
U Permit Voided 1
In the performance of this work I agree to perform all work pursuant to rules governing the described construction.
While the City of Oshkosh has no authority to enforce easement restrictions of which it is not a party, if you perform the work
described in this permit application within an easement, the City strongly urges the permit applicant to contact the easement
holder(s) and to secure any necessary approvals before starting such activity.
Signature
Date
Address
5711 GREEN VALLEY RD
Agent/Owner
OSHKOSH
WI 54904 - 0000 Telephone Number
231-8635
To schedule inspections please call the Inspection Request line at 236-5128 noting the Address, Permit Number, Type of
Inspection (i.e. Footing, Service, Final, etc.), Access into Building if Secure (how do we gain entry), your Name and Phone
Number. Unless specified otherwise, we will assume the project is ready at the time the request is received. Work may
continue if the inspection is not performed within two business days from the time the project is ready.
Buildings, HVAC Compliance Statement SBD-9720
This form is required to be submitted by the supervising professional (architect, engineer, HVAC designer or electrical
designer) observing construction of projects within buildings with total areas exceeding 50,000 cubic feet or greater and
bleachers (Comm 50.10/Comm 61.50). Failure to submit this form may result in penalties as specified in Comm
50.26/Comm 61.23 andlor local ordinances.
General Instructions: Prior to the initial occupancy of new buildings or additions and the final occupancy of
altered existing buildings, submit this completed and signed form to:
. The municipal building inspection office and
. Safety and Buildings, 10541 N Ranch Road, Hayward, WI 54843
Personal information you provide may be used for secondary purposes [Privacy Law, s. 15.04 (1 )(m)l
nla (City of Oshkosh)
1. PROJECT INFORMATION: Please fill in the fOllowing with information from your plan approval letter.
Transaction ID Number
Site Number nla
Site location (number & street)
0 city 0 Village
2069 Witzel Avenue
0 Town Of
Oshkosh
2. PURPOSE OF THIS STATEMENT: (Check Box A, B, C, or D to indicate purpose and complete any other
applicable boxes and information. Attach additional pages if necessary).
Check those which apply: 0 Building Object ID# nla
0 Lighting Object ID#
0 Partial Completion H & R Biock (tenant space)
Description of Portion Completed
Aj 0 Statement of Substantial Compliance
To the best of my knowledge. belief, and based on onsite observation, construction of the following building andlor HV AC items
applicable to this project have been completed in substantial compliance with the approved plans and specifications.
County of
Winnebago
0 HVAC Object ID#
0 BUILDING/LIGHTING ITEMS
1. Struciural system including submittal and erection of all building
components (trusses, precast, metal building, etc.)
2. Fire protection systems (sprinklers, alarms, smoke detectors)
designed, installed, and tested (including forward flow 0'1 back flow
devices) by appropriately registered professional..
3. Shaft and stairway enclosure
4. Exits including exit and directional lights
5. Fire-resistive construction, enclosure of "azards, fire walls, labeled
doors, class of construction, fire stoppod penetrations
6. Sanitation system (toilets, sinks, dlinking facilities)
7. Barrier-free inciuding Comm 18 elevators and lifts
8. Energy envelope requirements
9. All conditions of building plan approval and applicable variances
The following items are not in compliance and must be addressed:
10. Exterior lighting & control requirements
11. interior lighting & control requirements
12. All conditions of lighting plan approvai
and applicable variances
0 HVAC ITEMS
1. HVAC system including final test
2. All conditions of HVAC plan approval
and applicable variances
Bj 0 Statement of Noncompliance
Due to the following listed violations, this project is not ready for occupancy:
Cj 0 Supervising Professional Withdrawn From Project (Use A or B above to indicate project status as of this date.)
Dj 0 Project Abandoned
3. SUPERVISING PROFESSIONAL SIGNATURE FOR:
0 Building 0 HVAC 0 Lighting Ste hen Gries.
Name (please print or type)
Phone #
920-722-2445
Customer 10#
260804
Signature
SBD-9720 (R.OlI2003)
CITY HALL
Inspection Services Div
215 Church Avenue
~POBOX1130
Oshkosh WI
~ 54903-1130
OfHKOfH
ON .H> WA»R
City of Oshkosh
October 20th, 2003
Stephen Gries
307 S Commercial St
Neenah, WI 54956
Andy Dumke
601 Oregon St Ste A
Oshkosh, WI 54902
Re:
Tenant Space Alterations, Type B Occupancies
2069 Witzel Ave - H & R Block
2071 Witzel Ave - Check Into Cash
File # J5-l06-1O03
The above-reference plans have been stamped CONDITIONALLY APPROVED based upon
review for confonnance to the current edition ofthe Wisconsin Administrative Building and
Heating, Ventilating and Air Conditioning Code, chapters COMM 61-65 - These plans have
NOT been reviewed for confonnance to the Plumbing Code (chs. COMM 81-86), the Electrical
Code (ch.COMM 16) and any COMM code not specifically mentioned. This approval is not a
Building Pennit. Necessary city pennits must be secured before commencing work.
You are hereby advised that the owner, as defined in Chapter 101.01 (I) of the Wisconsi;n State
Statutes, is responsible for all code requirements not specifically cited herein- Code .
requirements are set forth in Chapters 61 through 65 of the rules of the Department of
Commerce.
The building will be inspected during construction and a final inspection will be made after
completion to insure compliance with city and state codes.
The architect, professional engineer, builder or owner shall keep at the building as evidence of
approval, one set of plans bearing the stamp of approval.
COMM 64.02 This approval does not include heating and ventilating. Such plans are required to
be submitted and approved prior to installation of such equipment.
H & R Block meets the requirements for one exit, therefore emergency illumination is not
required.
Check Into Cash is required to have 2 exits, therefore it must comply with all emergency
illumination requirements-
Be advised, a $100.00 Plan Submittal fee is due. It will be collected from RJ Albright at Pennit
issuance.