HomeMy WebLinkAboutSouth Park Lagoon Reconfiguration
South Park Lagoon Reconfiguration
Scope of work – In general follows the South Park Master Plan
Water Shed Approx. 700 acres
Lagoon Reconstruction Approx. Total Cost $3,000,000
Storm Water $2,475,000
Parks $200,000
Transportation $325,000
Parking lot reconstruction
New storm sewer, lights, pavement, concrete, entrance/exist, landscaping
Parking old 31 with 2 handicap - new 42 with 6 handicap stalls
Lagoon Reconstruction
Sediment Removal – 11,000 Cyds or 19,100 tons
Excavation – 24,500 cyds clean soil
Clay Liner 11,500 cyds.
Construction
Two concrete spill ways
Historic Bridge repair
Overlook
Nine stone out-cropping
4,888 syds pavement path
33,000 SY Top soil
Shore Line 3,000 LF coir logs and plants
Two fountains
Three fish cribs
Elevation Average Water Level
West Lagoon 752’ NWL full 753 top of east weir, 753.5 = 8 Acre feet or 2,606,808 gallons.
Depth 11 feet NML
Central Lagoon
Depth 9 feet NWL
East Lagoon 750’ – Full 753 = 1.82 acre feet or 606,082 gallons
6 feet