HomeMy WebLinkAbout09. 18-474 SEPTEMBER 11, 2018 18-474 RESOLUTION
(CARRIED 6-1 LOST LAID OVER WITHDRAWN )
PURPOSE: APPROVE AMENDMENT NO. 2 TO PROFESSIONAL SERVICES
AGREEMENT WITH AECOM TECHNICAL SERVICES, INC. FOR
CONSTRUCTION MONITORING AND DOCUMENTATION
SERVICES FOR MARION ROAD WATER TOWER
REPLACEMENT ($8,705.00)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
WHEREAS, the City previously entered into a professional services agreement
with AECOM Technical Services, Inc. for construction monitoring and documentation
services for the Marion Road Water Tower Replacement Project; and
WHEREAS, additional services were necessary to complete the project related to
fence support pier construction, documentation of the disposal of impacted groundwater,
documentation of the contractor's time to remove foundations, documentation of
impacted soil stockpiles and parking lot subgrade preparation and asphalt paving.
NOW, THEREFORE, BE IT RESOLVED by the Common Council of the City of
Oshkosh that the proper City officials are authorized and directed pursuant to Section
12-16 of the Municipal Code to enter into an amended agreement with AECOM Technical
Services, Inc.
BE IT FURTHER RESOLVED that the appropriate City officials are authorized and
directed to take those steps necessary to implement the terms and conditions of the final
agreement.
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Acct. No. 0541-1810-1799-00000 Water Utility- Construction in Progress
City
of�
Oshkosh
MEMORANDUM
TO: Honorable Mayor and Members of the on Council
FROM: James Rabe, Director of Public Works
DATE: September 6, 2018
RE: Approve Amendment No. 2 to Professional Services Agreement for Construction Monitoring and
Documentation Services for Marion Road Water Tower Replacement / AECOM Technical
Services, Inc. (AECOM) ($8,705)
BACKGROUND
A professional services agreement for environmental and engineering services for construction monitoring
and documentation services for the Marion Road Water Tower replacement was approved by the Common
Council on September 13, 2016. An amendment to this agreement was approved by Council on September
25, 2017. During the course of this project, additional engineering -related services were requested by City
staff.
ANALYSIS
The additional services requested included increased documentation and material testing related to the fence
support pier construction; additional site visits to document proper disposal of impacted groundwater to
sanitary sewer, to document the Contractor's time and materials effort to remove the former water tower
foundations; and to provide manifests for disposal of impacted soil stockpiled on the site during construction
activities; and documentation of the parking lot subgrade preparation and asphalt paving.
FISCAL IMPACT
The proposed cost of this amendment is not to exceed $8,705. This will raise the total agreement amount to
$118,982.50. Funding is available within the Capital Improvements Program (CIP) for this amendment.
Various CIP years have allocated a total of $4,933,150 for this project. This amendment will increase the total
project cost, including construction, engineering, environmental, and other ancillary costs to approximately
$4,856,000.
RECOMMENDATIONS
Chapter 12 of the Municipal Code of the City of Oshkosh provides that professional services of a specialized
nature, including engineering services, may be procured without the use of formal, sealed quotes. I have
reviewed the amendment and in accordance with Section 12-16 of the Code, I am hereby recommending the
Common Council approve this amendment.
Approved,
Mark A. Rohloff
City Manager
L\ Engineering \2016 CONTRACTS \ 16-22 Marion Rd W tr Twr Repl \ Project_lnformation \ Correspondence \ Memo \ 16-22 AECOM-CRS CA #2_9-6-1 S.docx
F-4
Mr. James Rabe, PE, CPESC
Director of Public Works
City of Oshkosh
215 Church Avenue
Oshkosh, WI 54901
AECOM
558 North Main Street
Oshkosh, WI 54901
aecom.com
Date
August 20, 2018
AECOM Project No.
60520583
Amendment Request Number 2 for Construction Monitoring and Documentation Services to
City Contract 16-22, Marion Water Tower Replacement, City Resolution Number 16-448
Dear Mr. Rabe,
AECOM Technical Services, Inc. (AECOM) is requesting an amendment to the agreement dated
September 8, 2016, (AECOM Proposal No. OPP-542187) and Amendment 1 dated July 13, 2017, for
Construction Monitoring and Documentation Services Related to City of Oshkosh Contract 16-22 Marion
Road Water Tower Replacement. This amendment request is for additional effort required to complete the
Construction Monitoring and Documentation. The additional effort includes:
Increase in documentation and materials testing related to the fence support pier construction,
including additional subcontracted laboratory material testing services.
a. The original scope of work included construction in normal weather conditions. The fence piers
are constructed out of a combination of masonry, brick, mortar and grout which are very
temperature sensitive. Since the contractor completed the work in winter conditions (i.e. below
freezing temperatures) additional documentation, field and laboratory testing were initiated in an
effort to assure Project Document compliance. Approximately 43 hours of additional field
documentation, office work, and $500 of subcontracted laboratory costs were required. This
work item was not included in the original scope of work.
Additional site visits to document proper disposal of impacted groundwater to sanitary sewer.
a. The Contractor and all the subcontractors had to be reminded at each dewatering event that all
groundwater had to be discharged to the sanitary sewer in compliance with the Sanitary
Discharge Permit. Accurate documentation records are required to verify sanitary discharge
costs. Approximately 8 hours of additional field documentation was required.
Additional site visits to document the contractor time and materials effort to remove the former water
tower foundations.
a. During demolition of the former water tower, the foundations were discovered to be significantly
larger than the available record drawings indicated. The Contractor requested a lump sum
change order due to that change in conditions. The Contractor was instructed to proceed with
removal under a time and materials basis. In an effort to verify and track the costs, additional
documentation of the foundation removal was required. Approximately 10 hours of field
documentation and office work was required. This work item was not included in the original
scope of work.
Additional site visits to provide manifests for disposal of impacted soil stockpiled on the site during
construction activities. Approximately 8 hours of additional field documentation was required.
Additional impacted soil was generated during final site grading and was not originally anticipated the
original scope of work. This material could not be reused on site and because it was solid waste it
had to be disposed of at a licensed landfill in compliance with the material management plan.
Documentation of the parking lot subgrade preparation and asphalt paving. Approximately 4 hours of
field documentation was required. This work item was not included in the original scope of work.
K:\Projects\60520583_Marion Road Water Tower CM\100-CONTRACT\110-CLIENT
CONTRACT\60520583 Amendment 2.docx 1/4
A=COM
We are requesting that the budget be increased by $8,705. This increase in budget will cover the
additional services required to complete the project.
The services provided will be performed in accordance with the Negotiated Fee Schedule and conditions
of the General Conditions of Service — City of Oshkosh, April 2009, which are expressly incorporated into,
and are an integral part of, our agreement for professional services.
If you have any questions or need to clarify a point, please call any of the undersigned at
920-236-6718.
Yours sincerely,
chnical Services, Inc.
Jaul F. Timm
Senior Account Manager
encl: Amendment to Agreement
Authorization
ON 0.0 d
Kevin L. Brehm, P.E. (WI)
Associate Vice President
2A
U*11100M
Amendment No. 2
Construction Monitoring and Documentation Services
Marion Road Water Tower Replacement 16-22
AECOM Project No. 60520583
City of Oshkosh Resolution No. 16-448
RETURN TO: AECOM
558 North Main Street
Oshkosh, WI 54901
Attention: Paul Timm
SUMMARY: Original ContractAmount:
Total Previous Amendments:
Amount this Amendment:
Revised Contract Amount
Task # DESCRIPTION
558 N Main Street
Oshkosh, Wisconsin 54901
920.236.6710
Date: August 20, 2018
$79,590.00
$30,687.50
$8,705.00
$118,982.50
AMOUNT
1 Fence Documentation $5,445
2 Impacted groundwater disposal documentation $920
3 Removal of oversized foundation documentation $1,200
4 Solid Waste soil disposal documentation $680
5 Parking lot documentation $460
TOTAL $8,705
K:\Projects\60520583_Marion Road Water Tower CM\100-CONTRACT\110-CLIENT
CONTRACT\60520583 Amendment 2.docx 3/4
A U't III o� Ilr III z at III o, rIII
August 20, 2018
I hereby certify that the necessary provisions have been made to pay the liability which will accrue under
this contract.
I hereby authorize AECOM to proceed with the scope of work outlined in Amendment 2, to amend
AECOM's proposal OPP-542187, dated September 8, 2016 and Amendment 1 dated July 13, 2017 for
additional Construction Monitoring and Documentation Services related to the proposed Marion Road
Water Tower Replacement Contract 16-22 with a revised budget authorization of $118,982.50 under the
general terms and conditions specified in the proposal.
Signature
Mark A Rohloff
Print Name
City Manager
Title/Organization
Signature
Pamela R. Ubrig
Print Name
City Clerk
Title/Organization
Signature
Lynn A. Lorenson
Print Name
City Attorney
Title/Organization
Signature
Trena Larson
Print Name
Director of Finance
Title/Organization
Date
Date
Date
Date