HomeMy WebLinkAboutProposed Review Schedule 2018 2018 Potential Projects - Staff Recommendations
Street Name Location Facility Type Action Required Schedule
W New York Between Jackson Street and Main
Avenue Street Sharrow Approved Spring 2018
Wisconsin Street North of Bridge to Irving Avenue Bike Lanes Approved Spring 2018
Michigan Street 41h Avenue to 2011,Avenue Sharrow -26 Approved Spring 2018
Washington
Avenue Main Street to Train tracks Sharrow Approved Fall 2018
Smith Avenue Vineland Street to N Main Street Bike Lanes TRAB, Bike/Ped, CC TBD
N Main Street Murdock Avenue to Snell Road Bike Lanes TRAB, Bike/Ped, CC TBD
12th Avenue Ohio Street to Main Street Sharrow Bike/Ped TBD
Tentative Review Schedule-2018 Plan Implementation
Smith Street and N Main Street Bike Lanes
• February 151h-Bike and Ped Meeting-Identified Potential routes
• March 13th-TRAB Meeting-Staff update on Smith Avenue and N Main Street bike lanes-
no action-no resident mailing
• March 15th Bike and Ped Meeting-Take action on recommended routes
• March 1 -send out resident letter for public meeting
• March 22nd-Public Input Meeting-Resident Mailing
• April 10th TRAB Meeting-Take action based on the March 151h Bike and Ped
Recommendations and public input meeting
• April 19th-Bike and Ped Meeting-More review as needed
• April 24th Common Council Meeting-1yt Reading
• May 8th Common Council Meeting-2nd Reading
• Summer 2018-Potential Installation