MEMORANDUM
TO: Honorable Mayor and Members of the Common Council
FROM:
Mark A. Rohloff, City Manager_
DATE:
February 8, 2018
RE: Report of Public Works Construction Contract Change Orders
Approved by City Manager in 2017
Section 12-8 (F) (1) of the Municipal Code of the City of Oshkosh provides that changes orders that are within
the approved budget; less than $25,000;and less than 15% of the original contract amount can be
approved by the City Manager. Change orders that do not meet any one of the above criteria require
approval by the Common Council.
During meetings in 2017, Council expressed an interest in receiving information about construction
contract change orders that did not require approval by the Council. Attached to this memo is a list of
change orders for construction contracts managed by the Department of Public Works that were
approved by the City Manager in accordance with Section 12-8 (F) (1) of the Municipal Code.
Please contact me if you have any questions.
MAR/jer
I:\ Engineering\Tracy Taylor\Memos to Mayor & Common Council\2018\2017 Change Orders_2-8-18.docx
2017 Public Works Construction Contract
Change Orders Approved by City Manager
Contract
Contractor
Amount
Change
Order
Number
Council
Action
Resolution
15-11
Wood Sewer
($52,893.19)
CO #1— Final
No
16-03
PTS Contractors
($85,483.19)
CO #1— Final
No
16-06
Al Dix
($35,364.09)
CO #1— Final
No
16-26
Highway Landscapers
$14,541.00
CO #1 - Final
No
16-30
Insituform Tech
($7,363.04)
CO #1 - Final
No
17-17
Ptaschinski Construction
($245.27)
CO #1 -Final
No