October 2, 2017
Mr. Tom Ptaschinski
Ptaschinski Construction, Inc.
W7352 STH 33
Beaver Dam, WI 53916
RE: Change Order No.1 (Final)
Contract 17-17
Dear Mr. Ptaschinski:
BNL -1
Enclosed is an executed copy of Change Order No. 1 (Final) between the City of Oshkosh and
Ptaschinski Construction, Inc. regarding the abovementioned project.
If you have any questions, please call our office at (920)236-5065.
Sincerely,
?es Rabe, P.E., CPESC '
Director of Public Works
JER/tlt
Enclosure: Change Order No. 1 (Final)
cc: Pam Ubrig, City Clerk (w/original)
Tara Wendt, Assistant Finance Director (w/copy)
File (w/original)
1:\ Engineering\2017 CONTRACTS \ 17-17 Hemlock Ct-Fraser Dr\ Project_Information\Contract Info \Change
Orders\17-17 Executed CO #1 (Final Ltr)-10-2-17.docx
City Hall, 215 Church Avenue P.O. Box 1 130 Oshkosh, WI 54903-1130 http://www.ci.oshkosh.wi.us
Page 1 of 1
TO: PTASCHINSKI CONSTRUCTION, INC. CHANGE ORDER #1 (FINAL)
W7352 STH 33 DATED: SEPTEMBER 12, 2017
BEAVER DAM, WI 53916
Your present contract with the City of Oshkosh, Contract No. 17-17, awarded February 14, 2017, is hereby
amended and changed as follows:
DECREASE TO: SECTION 1 ($245.27)
SECTION I TOTALS
BID TOTAL $169,180.99 $169,180.99
CO #1 ($245.27) ($245.27)
CONTRACT TOTAL $168,935.72 $168,936.72
CITY OF OSHKOSH
BY:
City Manager
City Clerk
Approved an ccepte
1hp
(doJ
ntractor
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin,
under the within Change Order.
Comptroller
Approved asorm:
City Attorney.
CONTRACT: 17-17 CHANGE ORDER # 1
SECTION I
ITEM
DESCRIPTION
UNIT
BID
INSTALLED
NET
NET
UNIT
INCREASEIN
DECREASEIN
NUMBER
QUANTITY
QUANTITIES
INCREASE
DECREASE
PRICE
CONTRACTPRICE
CONTRACTPRICE
Removing curb and gutter;
Linear
1110
complete asspecified
Feet
2010.00
2,005.70
-4.30
$2.00
$8.60
Removing concrete and
asphalt sidewalk and
driveway, complete as
Square
1120 1
specified
Feet
1750.00 1
1,364.70
-385.30 1
$0.50
$192.65
Unclassified excavation;
Cubic
1200
complete asspecified
Yards
690.00
657.10
-32.90
$12.00
$394.80
7" concrete pavement; base
in place and grading;
Square
1300
complete asspecified
Yards
3045.00
3,014.20
-30.80
$37.22
$1,146.38
Crushed aggregate base
course; complete as
1340
specified
Tons
10.00
10.00 1
$10.00
Adjust manholes and inlets;
1360
complete asspecified
Each
20.00
17.00
-3.00
$300.00
$900.00
Turf restoration on Fraser
Square
1370A
Drive; complete asspecified
Yards
511.50
495.20
-16.30
$6.91
$112.63
Turf restoration on Hemlock
Square
1370B
Court; complete as specified
Yards
738.50
1,162.40
423.90
$6.91
$2,929.15
12" radius curb cut with 6"
CABC and grading; complete
Linear
1410
asspecified
Feet
142.00
147.10
5.10
$10.00
$51.00
30" curb and gutter, 7' with
5" CABC and grading,
Linear
1440
complete as specified
Feet
12.00
10.60
-1.40
$25.00
$35.00
gutter; 8"; with 6" CABC and
grading; complete as
Linear
1450
1 specified
Feet
90.00
1 85.80
-4.20
$14.00
$58.80
4" concrete sidewalk with 3"
CABC and grading, complete
Square
1
1500
asspecified
Feet
525.00
283.50
-241.50
1 $4.15
$1,002.23
6" concrete
sidewalk/driveway/ramp with
3" CABC and grading,
Square
1510
complete as specified
Feet
1625.00
1,443.20
-181.80
$4.65
$845.37
Curb ramp detectable
warning field (naturaUnon-
painted); complete as
Square
1540
ispecified
Feet
30.00
1 40.00
10.00
1 $25.00
$250.00
Drilled No. 4 sidewalk tie
bars, deformed, epoxy -
coated, complete as
1560
specified
Each
65.00
46.00
-19.00
$6.00
$114.00
Sawing existing pavement,
Linear
1700
complete asspecified
Feet
230.00
237.90
7.90
$1.50
$11.85
Tack coat; complete as
1900
1 specified
Gallons
12.00
1 12.00
1 $10.10
4" asphaltic pavement with
10" CABC and grading,
Square
1906
complete asspecified
Yards
9.00
6.80
-2.20
$70.70
$155.54
4" asphaltic transition with
10" CABC and grading,
Square
1911
complete as specified
Yards
167.00
164.90
-2.10
$27.27
$57.27
Furnish and install 18" storm
Linear
2009
sewer; complete asspecified
Feet
16.00
16.00
1
$112.00
Furnish and install 24" storm
Linear
2015
sewer; com fete asspecified
Feet
10.00
10.00
$120.00
Connect to existing storm
sewer main; complete as
2850
specified
Each
4.00
4.00
$250.00
Page 1 of 2
CONTRACT: 17-17 CHANGE ORDER # 1
ITEM
DESCRIPTION
UNIT
BID
INSTALLED
NET
NET
UNIT
INCREASE IN
DECREASE IN
NUMBER
DESCRIPTION
UNIT
QUANTITY
QUANTITIES
INCREASE
DECREASE
PRICE
CONTRACT PRICE
CONTRACT PRICE
Connect to existing storm
sewer manhole, complete as
2856
specified
Each
2.00
2.00
12.00
$200.00
$1,320.00
Furnish and install external
sanitary sewer manhole
chimney seal; complete as
Linear
3114
specified
Each
4.00
4.00
1 24.00
$600.00
1 $216.00
Furnish and install external
sanitary sewer manhole
chimney seal extension;
3116
lcomplete ass specified
Each
1.00
1.00
$200.00
Furnish and install 4"/6"
sanitary sewer lateral (relay);
Linear
3234
complete ass cified
Feet
20.00
20.00
$64.00
Furnish and install sanitary
sewer lateral marker balls;
3236
complete ass specified
Each
2.00
2.00
$75.00
SECTION I - (BID ITEMS 1100 - 3236 SUBTOTAL $3,242.00 ($5,023.27)
ADDITIONAL WORK REQUIRED: C.O. #1
ITEM
NUMBER
DESCRIPTION
UNIT
BID
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACTPRICE
DECREASEIN
CONTRACTPRICE
Furnish; install, maintain; and
remove Type D modified inlet
protection; complete as
1-2508
specified
Each
0.00
12.00
12.00
$110.00
$1,320.00
Furnish; install; maintain; and
remove 12" diameter
sediment logs; complete as
Linear
1-2518
Ispecified
Feet
1 0.00
1 24.00
1 24.00
$9.00
1 $216.00
ADDITIONAL WORK: C.O. #1 (ITEMS 1-2508 -1-2518) SUBTOTAL
$1,536.00 $0.00
NET DECREASE TO: SECTION 1
($245.27)
NET INCREASE TO SECTION 1
$4,778.00
NET DECREASE TO SECTION 1
($5,023.27)
NET DECREASE TO CONTRACT:
($245.27)
Page 2 of 2