HomeMy WebLinkAbout47. Oshkosh Corporation Development UpdateTO: Honorable Mayor & Members of the Common Council
Mark Rohloff, City Manager
FROM: Allen Davis, Community Development Director
DATE: December 7, 2017
RE: Oshkosh Corporation Global Headquarters Construction, Public Improvements,
Tax Increment Finance Plan, Timeline
Public Improvements
The traffic consultant, KL Engineering, has started work on the Traffic Impact Analysis. Traffic
counts and turning movements are currently underway. The data collection phase will continue
in December. Staff has tentatively planned for a Joint meeting of the City Council, Plan
Commission and Traffic Review Board to review the results and proposed improvements for
January 30, 2018.
City staff has begun work on preliminary design of the infrastructure. Staff and Oshkosh
Corporation representatives will be meeting with WisDNR staff regarding permitting needs for
the project. In anticipation of the permitting requirements, an archeologist has been on the site
and identified location and the plan for excavating any area that may be disturbed during
construction.
Staff has also been working with a surveyor to create the new lots required for the public and
private development. The draft Certified Survey map will be presented to the Plan Commission
on December 19, 2017 for action.
Tax Increment Finance Plans
Staff and Ehlers began work on a Pay -go - Tax Increment Finance Plan #34 for the Oshkosh
Global Headquarters. A draft will be ready in December for review. In addition, a Tax
Increment Finance Plan #35 for the Oshkosh Avenue Corridor Redevelopment is in the early
stages of development. Staff expects to have a draft of the Oshkosh Avenue Corridor
Redevelopment TIF ready for review in December.
City Hall, 215 Church Avenue P.O. Box 1130 Oshkosh, WI 54903-1130 920.236.5000 http://www.ci.oshkosh.wi.us
Development Agreement
Staff has done preliminary work on the Development Agreement, however, much of it depends
on the draft TIF Plans. Staff anticipates a closed session with Council at their January 9, 2018
meeting to review the draft Development Agreement elements and conditions.
Timeline
The attached Table identifies the various steps and actions for completing the permitting and
plan review phase of the Oshkosh Corporation Global Headquarters project.
City Hall, 215 Church Avenue P.O. Box 1130 Oshkosh, WI 54903-1130 920.236.5000 http://www.ci.oshkosh.wi.us
CC - City Council
PC - Plan Commission
JRB -Joint Review Board
OC - Oshkosh Corporation
Oshkosh Corporation/Oshkosh Avenue - City Actions during the development review process
CC
PC CC TID Plans
PC
JRB PC
CC PC CC
JRB
PC CC PC CC IPC CC
28 -Nov
5 -Dec 12 -Dec 16 -Dec
19 -Dec
1/2/2018 2 -Jan
9 -Jan 16 -Jan 1/23/2018 1/30/2018
2/6/2018 2/13/2018 2/20/2018 2/27/2018 3/6/2018 3/13/2018
TIF Plans Oshkosh Corp
Update Publish
Org Mtg Action
Action
Action
Oshkosh Ave.
Update Publish
Org Mtg Action
Action
Action
OC Purchase Agreement
Action
OC Development Agreement
Closed session
Action
OC Lot/CSM
I
Drafted
Action
Recorded by 12/31
CSM - Right of way
Action Action
Oshkosh Ave
Land Use Amend. ist reading
2nd reading
Oshkosh Corp
Land Use Amend.
Action 1st & 2nd reading
New Zoning Code
Workshop 2
Action
1st & 2nd reading
Rezone Oshkosh Ave Lots
Action
1st & 2nd reading
Rezone OC Lot
Action
1st & 2nd reading
Traffic Impact Analysis
lWorkshop
Completed
Oshkosh Corp General Dev, Plan
Workshop
Action Action
Oshkosh Corp Specific Dev. Plani I
ISubmit 2/5 Action Action
CC - City Council
PC - Plan Commission
JRB -Joint Review Board
OC - Oshkosh Corporation