HomeMy WebLinkAboutDorner Inc 17-12 Change Order No 1City
fV�
Oshkosh
September 29, 2017
Mr. Todd Dorner
Dorner, Inc.
PO Box 129
Luxemburg, WI 54217
RE: Change Order No. 1
Contract 17-12
Dear Mr. Dorner:
�I -Cl q :3-
Enclosed is an executed copy of Change Order No. 1 between the City of Oshkosh and Dorner,
Inc. regarding the abovementioned project.
If you have any questions, please call our office at (920)236-5065.
Sincerely,
es Rabe, P.E., CPESC
Director of Public Works
JER/tlt
Enclosure: Change Order No. 1
cc: Pam Ubrig, City Clerk (w/original)
Tara Wendt, Assistant Finance Director (w/copy)
File (w/original)
1-\ Engineering \2017 CONTRACTS \ 17-12 W tr Mn Relays \ Project_Information \ Contract Info \ Change
Orders\ 17-12 Executed CO #1 Ltr 9-29-17.docx
City Hall, 215 Church Avenue P.O. Box 1130 Oshkosh, WI 54903-1130 http://www.ci.oshkosh.wi.us
Page 1 of 1
TO: Domer, Inc.
PO Box 129
Luxemburg, WI 54217
CHANGE ORDER #1
DATE: August 30, 2017
Your present contract with the City of Oshkosh, Contract No. 17-12, awarded June 13, 2017, is hereby
amended and changed as follows:
NET INCREASE TO: SECTION 1 $116,607.05
NET INCREASE TO CONTRACT $116,607.05
SECTION I TOTALS
BID TOTAL $1,978,062.15 $1,978,062.15
CO #1 $116,607.05 $116,607.05
CONTRACT TOTAL $2,094,669.20 $2,094,669.20
CITY OF OSHKOSH
BY:
- City Manager-
City
anagerCity Clerk
prove a d accepted:
Contractor
certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin,
under the within Change Order.
Comptroller
Approved a ,tq form:
dfy A r y
CONTRACT 17.12 CHANGE ORDER #1
SECTION I - ADDITIONAL WORK REQUIRED: CO #1 (W PACKER AVENUE)
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
UNIT
INCREASE IN
NUMBER
QUANTITY
QUANTITIES
INCREASE
DECREASE
PRICE
CONTRACT PRICE
Removing pavement;
Square
1-1100
complete asspecified
Yards
0.00
142.00
142.00
$8.15
$1,157.30
Removing concrete and
asphalt sidewalk and
driveway; complete as
Square
1-1120
specified
Feet
0.00
395.00
395.00
$0.60 1
$237.00
Unclassified excavation,
Cubic
1-1200
complete asspecified
Yards
0.00
112.00
112.00
$14.30
$1,601.60
8" concrete pavement
removal and replacement;
including sawing; pavement
ties; integral curb and fine
grading; turf restoration; and
traffic control; complete as
Square
1-1318
specified
Yards
0.00
1,320.00
1,320.00
$55.60
$73,392.00
Pavement ties; complete as
1-1350
specified
Each
0.00
45.00
45.00
$9.00
$405.00
Adjust manholes and inlets;
1-1360
complete asspecified
Each
0.00
8.00
8.00
$210.00
$1,680.00
12" radius curb with 6" CABC
and grading; complete as
Linear
1-1410
specified
Feet
0.00
65.00
65.00
$9.50
$617.50
30" curb and gutter; 8"; with
6" CABC and grading;
Linear
1-1442
complete asspecified
Feet
0.00
10.00
10.00
$23.75
$237.50
Sidewalk curb; complete as
Linear
1-1460
specified
Feet
0.00
15.00
15.00
$25.00
$375.00
6" concrete sidewalk/
driveway /ramp with 3" CABC
and grading; complete as
Square
1-1510
specified
Feet
0.00
355.00
355.00
$5.70
$2,023.50
Curb ramp detectable
warning field (natural/non-
painted); complete as
Square
1-1540
specified
Feet
0.00
8.00
8.00
$30.60
$244.80
Drilled No. 4 sidewalk tie
bars - deformed; epoxy -
coated; complete as
1-1560
specified
Each
0.00
8.00
8.00
$5.10
$40.80
Sawing existing pavement,
Linear
1-1700
complete asspecified
Feet
0.00
11.50
11.50
$2.30
$26.45
Sawing concrete pavement
full depth; complete as
Linear
1-1710
specified
Feet
0.00
1,130.00
1,130.00
$3.07
$3,469.10
Base aggregate dense; 3/4";
1-1800
complete asspecified
Tons
0.00
215.00
215.00
$13.30
$2,859.50
Tack coat; complete as
1-1900
specified
Gallons
0.00
10.00
10.00
$7.00
$70.00
Asphaltic cold weather
paving; complete as
Square
1-1918
specified
Yards
0.00
145.00
145.00
$15.00
$2,175.00
4" asphaltic surface MT with
8" concrete base course;
Square
1-1920
complete asspecified
Yards
0.00
145.00
145.00
$75.00
$10,875.00
Furnish and install 12" storm
Linear
1-2003
sewer; complete asspecified
Feet
0.00
38.00
38.00
$60.00
$2,280.00
Furnish; install; maintain; and
remove Type D modified inlet
protection; complete as
1-2508
specified
Each
1 0.00
1 9.00
1 9.00
$75.00
$675.00
Sediment removal - Type D
modified inlet protection;
1-2510
complete asspecified
Each
0.00
9.00
9.00
$5.00
$45.00
Page 1 of 2
CONTRACT 17-12 CHANGE ORDER #1
ITEM
CONTRACT
INSTALLED
NET
NET
UNIT
INCREASE IN
NUMBER
DESCRIPTION
UNIT
QUANTITY
QUANTITIES
INCREASE
DECREASE
PRICE
CONTRACTPRICE
Furnish; install, maintain; and
remove stone bag; complete
1-2516
as specified
Each
0.00
9.00
9.00
$5.00
$45.00
Abandon 15" and larger
storm sewer; complete as
Linear
1-2802
specified
Feet
0.00
325.00
325.00
$25.00
$8,125.00
Remove storm sewer
manholes and inlets;
1-2812
lcomplete asspecified
Each
1 0.00
1.00
1.00
1
$550.00
$550.00
Connect to existing storm
sewer main; complete as
1-2850
specified
Each
0.00
2.00
2.00
$550.00
$1,100.00
Connect to existing storm
sewer manhole; complete as
1-2856
specified
Each
0.00
1.00
1.00
$1,300.00
$1,300.00
Furnish and install external
sanitary sewer manhole
chimney seal; complete as
1-3114
specified
Each
0.00
2.00
2.00
$500.00
$1,000.00
SECTION I - (ADDITIONAL WORK REQUIRED: CO #1 ITEMS 1-1100 to 1-3114) - SUBTOTAL $116,607.05
NET INCREASE TO: SECTION 1 $116,607.05
Page 2 of 2