HomeMy WebLinkAbout39. 17-443 AUGUST 22, 2017 17-443 RESOLUTION
(CARRIED 7-0 LOST LAID OVER WITHDRAWN )
AS AMENDED
PURPOSE: PROVIDE DIRECTION TO STAFF RELATING TO OREGON STREET
RECONSTRUCTION
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
WHEREAS, reconstruction of Oregon Street from West 61h Avenue to West 201h
Avenue is anticipated to be included in future Capital Improvements Budgets beginning in
2018; and
WHEREAS, there are three potential options recommended for Council
consideration for the reconstruction of Oregon Street:
1. Receffstniet the street at forty feet (409 firem face of eurb to face of eftrb-.
Provide two (2) ei-ghtfeet (89 wide Parking lanes and two (2) twelvefeet
(429 wide &4ving lanes
2. Receffstniet the street atfortyfeet(409 and widen the inter-sections of We
(2) ei-ghtfeet(89 wide parking lanes-, two (2) twelvefeet(429 wide driving
lanes and Provide the potential n1aintaiff the Separation of the right him
and stra�ot traffic lanes at West )t4 Avenue and West South Park Avenue.
3. Reconstruct street at the current width of forty four feet (44'). Provide two
(2)eight foot(8')wide parking lanes, two (2)fourteen foot(14')wide driving
lanes, and provide the potential to maintain the separation of the right turn
and straight traffic lanes at West 91h Avenue and West South Park Avenue.
WHEREAS, it is necessary to provide direction to staff to allow staff to prepare
designs for the street and estimate costs for the Capital Improvements Budget; and
WHEREAS, the City's Comprehensive Plan designates Oregon Street as an arterial
street; and
WHEREAS, the Comprehensive Plan generally provides that arterial streets are to be
reconstructed with four (4) twelve foot (12') driving lanes, two in each direction; and
*Bold &Italics Indicates Amendment
AUGUST 22, 2017 17-443 RESOLUTION
CONT'D
WHEREAS, the existing right of way will not accommodate four(4)twelve foot(12')
driving lanes, it is not feasible to acquire additional right of way in this location and it is
therefore necessary to make an exception to the Comprehensive Plan.
NOW, THEREFORE, BE IT RESOLVED by the Common Council of the City of
Oshkosh that the proper City officials are hereby directed to proceed with design of Oregon
Street as follows:
1. Reconstruct the street at forty feet (40') from face of curb to face of curb.
Provide two (2) eight foot (8') wide parking lanes and two (2) twelve foot
(12') wide driving lanes
2. Reconstruct the street at forty feet (40') and widen the intersections of West
91h Avenue and West South Park Avenue to forty four feet(44'). Provide two
(2) eight foot (8') wide parking lanes, two (2) twelve foot (12') wide driving
lanes and provide the potential maintain the separation of the right turn and
straight traffic lanes at West 91h Avenue and West South Park Avenue.
3. Reconstruct street at the current width of forty four feet (44'). Provide two
(2)eight foot(8')wide parking lanes, two (2)fourteen foot(14')wide driving
lanes, and provide the potential to maintain the separation of the right turn
and straight traffic lanes at West 91h Avenue and West South Park Avenue.
r,A
City
of
Oshkosh
MEMORANDUM
TO: Honorable Mayor and Members of the C Council
FROM: James Rabe, Director of Public Works
DATE: August 17, 2017
RE: Provide Direction to Staff Relating to Oregon Street Reconstruction
BACKGROUND
The Department of Public Works has been planning the construction of a deeper sanitary sewer within the Oregon Street
right-of-way to provide an increased level of service and to allow for additional development to the south. While evaluating
the sanitary sewer needs in this area, it became apparent the scope of the sewer work would require a complete reconstruction
of Oregon Street. A complete street reconstruction would allow for the storm sewer and water main to be reconstructed,
along with the sanitary sewer, and then construct new concrete pavement on Oregon Street.
The Department of Public Works previously presented the Common Council with three (3) options for consideration
regarding the street width for the Oregon Street reconstruction. These options have been presented in regards to the 2018
street reconstruction, but the option chosen for 2018 will likely impact the reconstruction of Oregon Street from West 6th
Avenue to West 2011, Avenue. Oregon Street, south of West 20th Avenue, is planned to retain four (4) lanes of vehicle traffic.
Through all three (3) of these options, on -street parking remains in place. The three (3) options presented to the Council are:
1. Reconstruct the street at forty feet (40') from face of curb to face of curb. Provide two 8' wide parking lanes and two
12' wide driving lanes.
2. Reconstruct the street at forty feet (40') and widen the intersections of West 9th Avenue and West South Park Avenue
to forty four feet (44'). Provide two 8' wide parking lanes, two 12' wide driving lanes, and provide the potential to
maintain the separation of the right turn and straight traffic lanes at West 9th Avenue and West South Park Avenue.
3. Reconstruct street at the current width of forty four feet (44'). Provide two 8' wide parking lanes, two 14' wide
driving lanes, and provide the potential to maintain the separation of the right turn and straight traffic lanes at West
9th Avenue and West South Park Avenue.
ANALYSIS
The City of Oshkosh Comprehensive Plan states that arterial streets, such as Oregon Street, are to be reconstructed with twelve
foot (12') wide driving lanes. The twelve foot (12') wide driving lane is the maximum width included within the
Comprehensive Plan. The Comprehensive Plan also provides that parking lanes should be eight feet (8) in width. Utilizing
the guidance and direction of the Comprehensive Plan, which has been adopted by the Common Council, Oregon Street, with
two (2) driving lanes and two (2) parking lanes, should be constructed at forty feet (40') in width.
Private utility companies have significant underground infrastructure within the Oregon Street right-of-way. These
companies need the City design to determine what facilities they need to relocate as a part of the construction project. Delays
in providing the design could delay the ability of the private utility companies to complete their work, thus causing delays in
the completion of the City's project.
/ I:\Engineering\2018 CONTRACTS\18-052nd Paving\ Project -Information\ Correspondence\ Memo\ 18- Page 1of2
05 CC Memo -Direction on Oregon St Width_8-17-17.docx
FISCAL IMPACT
Engineering Division staff estimate the total cost for the street paving portion of the project for the 44' wide option to be
approximately $1,615,000 and the 40' option to be approximately $1,394,000. The City will recover a portion of the cost of
street reconstruction from adjacent property owners in accordance with the City's Special Assessment Policy. The special
assessment rate to adjacent non-residential properties is currently estimated to be approximately $42.20/foot of frontage
higher for the 44' wide option than the 40' wide option. This estimate is based upon the 2017 special assessment rates. The
2018 rates will not be available until late 2017 or early 2018.
RECOMMENDATIONS
In order for staff to proceed with the design of Oregon Street, and get information to the private utility companies in order
for them to design any infrastructure changes they need to make, it is important for the Council to give direction to the
Engineering Division staff at this time.
Approved,
Mark Rohloff
City Manager
JER/tlt
IA Engineering \201 8 CONTRACTS\18-05 2nd Paving\ Project_Information \Correspondence\ Memo\ 18- Page 2 of 2
05 CC Memo -Direction on Oregon St Width_8-17-17.docx
44' WIDE OPTION
OREGON STREET PAVEMENT CROSS SECTION
60' RIGHT OF WAY
8' 44' FACE TO FACE PAV'T 8'
5' o cn
�Q
WALKa C'9 8' PARKING
.5, LANE
14'TRAVEL
LANE
o � 5'
�- a
or
14' TRAVEL 8' PARKING < WALK
LANE LANE 5,
40' WIDE OPTION
OREGON STREET PAVEMENT CROSS SECTION
60' RIGHT OF WAY
10' 40' FACE TO FACE PAV'T 10'
5' PAV'T PAV'T 5'
WALK OR GRASS 8' PARKING 12' TRAVEL 12' TRAVEL 8' PARKING GRASS OR WALK
LANE LANE LANE LANE
OREGON ST AND 9TH AVE
INTERSECTION CONCEPT 40/40 OPTION
OREGON ST AND 9TH AVE
INTERSECTION CONCEPT 44/40 OPTION
OREGON ST AND SOUTH PARK AVE
INTERSECTION CONCEPT 40/40 OPTION
OREGON ST AND SOUTH PARK AVE
INTERSECTION CONCEPT 44/40 OPTION