HomeMy WebLinkAboutAECOM Proposal No. 381501, Resolution No. 15-285 ' .
AECOm
°-mSCOM 558 North Main Street
Oshkosh,vwmoo`
"vcnm.cvm
�
Dote
February 27, 2017
AECOK8 Project No
'
60427918
Mr. James Rabe, PE, CPESC
Director ofPublic Works ��� � � 2D17
City ofOshkosh ' �~ � ~ ^~''
215Church Avenue
|/| nTDP PO���CVyO��8
PDBox 113O
||{O1, 9V1SC0 N '
Oshkosh, VN548O3-113O
Amendment Request Number 1 for Continued Environmental Investigation and Gas Well
Monitoring etK|enmotand Paulus Quarries
Dear Mr. Robe,
AECOPWTechnical Services, Inc. (AECOyN) is requesting an amendment tothe agreement dated May 27,
2U15 (4ECON1Proposal Number[)PP'3815O1). City Resolution No15-2D5. This amendment request io
for additional services completed to date and for continued monthly monitoring of the gas monitoring vve||a
through the first quarter of2O17. Work that has been conducted todate that ioconsidered outside ofthe
original scope of work includes:
Work Item Budgeted Aotmap
Sample Existing LFQWells (3) 1 4; these wells are now incorporated into
continuous monthly sampling
Draft Landowner Notification Loder 1 3 (per requests of City staff)
Subcontract Excavator and Document O 2rounds (11 total pits) excavated prior to
Test Pits LFGvveU installation
Subcontract Driller and Document Well 4-8 Wells 1Dwells installed during two separate
Installation mobilizations bydriller
Conduct Pump Tests of Selected LFG O 3 (with discussion and agreement from City
Wells to Investigate LFG Quantity staff)
Conduct Monthly Monitoring ofLFGWells O 17months (November 2O15-March 2O17)
Technical Memorandum O Technical Memorandum -Jonuary 13. 2017
N0NR |nterface O Prepare Project Summary
Please note these out of scope demo have been initiated and/or completed booed on conversations and in
agreement byCity staff. The purpose oflisting these items iotwofold: 1)toprovide arevised scope cf
work to our original proposal, and; 2)to request additional compensation where necessary. Additional
compensation is only being requested for continued site monitoring, preparation ofaTechnical
N1emonsndum, and interfacing with thoVVDNR. All other out-of-scope items were completed within the
original budget by utilizing funding from tasks in the original proposal that were completed under budget.
This amendment was prepared based on the following assumptions:
* Monthly Monitoring will continue through the end ofMarch 2O17
v Technical Memorandum dated January 27, 2017 is complete
n\Pmacm01'Amenoment
� . ^
AECOM
* Anticipated VVONRInterface will beconducted inthe first quarter of2U17
Addffioi�ial Moriti"fly Monitoring
AECOM proposes to continue monthly methane monitoring activities based on original discussions with
VVDNRpersonnel and inaneffort tocollect LFGsystem design data.
At each gas monitoring well, initial percent of the LEL of methane(percent LEL methane), percent
methane gas(percent methane), percent oxygen (percent 02), percent of carbon dioxide(percent COA
and groundwater levels will bemeasured. The LEL iothe minimum concentration ofeparticular
combustible gas orvapor necessary bosupport its combustion inair. The LEL ofmethane gas io5Y6
methane byvolume. Observations (such as ground condition, barometric pressure, and monitoring well
conditions)will also berecorded.
After initial readings are recorded, monitoring wells will be purged with a pump at a rate of two liters per
minute. Continuous percent LEL methane iohnbemeasured aethe well iopurged. Afinal reading will ba
recorded when consecutive methane readings are within±10Y6LEL. Final measurements include percent
LEL methane, percent methane gas, percent COe. and percent Ou. The length oftime required toachieve
the final reading iotypically unique toeach well.
VVehave been completing this work since April 2O1G. VVehave been requested byCity staff tocontinue
monitoring through March 2O17.
Monthly labor costs to perform the monitoring range from approximately$300 to$1,600 per month. This
variation in monthly costs is based on weather and site conditions which impact the efficiency ofthe field
odeff. These costs also include the rental oftesting equipment. Please note wohave been scheduling the
sampling events to coincide with Knapp Street Quarries and Timmerman Landfill projects to eliminate
multiple shipping charges, reduce rental fees for the monitoring equipment, and provide a single
equipment charge for the use ofanAECOyNtruck and other field equipment. The total estimated cost for
these additional services ieapproximately$12.00O.
TechrOcal Me00oranduni
AECOM staff prepared a Technical Memorandum which provides a summary of background, investigation
results, comparison of design options, budgetary capital cost estimate, and recommendations. The
intended purpose ofthis memorandum was toprovide City staff with remedial options and cost
comparisons. |iwill beutilized for consideration cf financial options and budget preparation.
The cost was$4.77O. This cost was developed by time incurred by the AECOM team consisting of 4 hrs.
Paul Timm,Account Manager, 6 hrs. Cliff Shierk, RE., Project Manager, 0 hrs., Don Pirrung, RE., Senior
Landfill Design Manager, and 8 hrs., Paul Wintheiser, RE., Senior Landfill Gas Design Engineer and 2
hours Betty Seifert, staff assistant. . Please note that nocosts were incurred for the AECOPNstaff that
attended the meeting with City staff onDecember 14. 201G.
WIMR hiriterface
AECOM recommends preparing a project update to be presented to the new WDNR project manager.The
Technical Memorandum discussed above would be modified to provide a more comprehensive summary
ofthe investigation and monitoring results todate. VVeanticipate conducting efollow-up meeting with the
WDNR manager to discuss the results and recommendations provided in the project update.
The anticipated cost for this is$7,000. The project update will be prepared by Cliff Shierk and Paul Timm.
The meeting with WDNR will be attended by Cliff Shierk, Paul Timm, and either Don Pirrung or Paul
VVinthmioero|ong with City staff.
The services provided will be performed in accordance with the 2017 Negotiated Fee Schedule and
conditions of the General Conditions of Service—City of Oshkosh,April 2009, which are expressly
xAP /onastouarry/n,eaouuxnm1oo'oowrn*ornn1-Amendment
1m0427918_monaomnuPuumsovumes-Amenomenm.uvnx xa
A=COM
incorporated into, and are an integral part of, our agreement for professional services. AECOM can begin
providing these services immediately upon receipt of the signed Amendment Authorization Form
(attached).
r If you have any questions or need to clarify a point, please call Mr. Paul Timm at 920-236-6718.
Your incere
Clifford R. Shierk, P klin . Brehm, P.E. 1
Project Engineer Associate Vice President
encl: Amendment to Agreement
Authorization
KAProjects\60427918 Kienast Quarry Investigation\100-CONTRACT\101-Amendment
1\60427918_KienastA_ PaulusQuarries_Amendment1.docx 3/5
AECOM
AECOM
558 North Main Street,Oshkosh,WI 54901
T920.236.6718 F920.235.0321
Amendment to Agreement
Amendment No. 1
Environmental and Engineering Services for the Former Kienast and Paulus Quarries
City of Oshkosh,Wisconsin
AECOM Project No.60427918
City of Oshkosh Resolution No. 15-285
RETURN TO: AECOM Date: February 27, 2017
558 North Main Street
Oshkosh, WI 54901
Attention: Paul Timm
i
SUMMARY: Original Contract Amount: $116,000
Amount this Amendment: $23,770
Revised Contract Amount $139,770
i
Amendment# DESCRIPTION AMOUNT
1 Monthly Monitoring (17 Months) including
j labor and equipment $12,000
Technical Memorandum from 1/27/17 WDNR
Interface $4,770
WDNR Interface/Memorandum $7,000
TOTAL $23,770
E
I
I
I
F
i
K:\Projects\60427918_Kienast Quarry Investigation\100-CONTRACT\101-Amendment
1\60427918_KienastAndPaulusQuarries_Amendmentl.docxK:\Projects\60427918_Kienast Quarry
Investigation\100-Contract\101-Amendment 1\60427918_Kienastandpaulusquarries_Amendmentl.Docx
't
II
I
^
AECOM
4ECo
nneNorth Main Street,Oshkosh,WI 5*801
Toon2mo.e710 poou.2onoao1
Amendment to Agreement Authorization
February 27. 2O17
1 hereby certify that the necessary provisions have been made to pay the liability which will accrueunder
this contract.
I hereby authorize AECOM to proceed with the scope of work outlined in Amendment 1,to amend
AECOM's proposal OPP-381501, dated May 27, 2015 for Environmental and Engineering Services
Related to the Former Kienast and Paulus Quarries, Oshkosh,Wisconsin of$139,770 under the general
terms and conditions specified inthe proposal.
'Signatbre Date
Mark ARoh|oO
Print Name
City Manager
"'y"atu'" ' ~~~
Pamela R. Ubhg; '
Print Name
City Clerk
�ig6�/m \ / / Date
Lynn A. Lonsneon;
Print Name
Qty Attorney
&�Ar�
Date
TreneLomon
Print Name
Director ofFinance
n\Pmvm4r 1o_xietouarry/mmm/nunonnno'uowrnAcrnn1-^manument
1\60*2791m m` op / uuuume�Amenomenn.uuuxx:\p�emymo4xre1m Quarry
m"aaoo�/vnnoo'oonm�x1o1'xmonoment 1m0427918_«/enuatanuvaumonuu,nes-Amunumann.oncx