HomeMy WebLinkAboutChange Order No. 1, Contract 16-20 City of Oshkosh December 7, 2016 Ms. Sue Wood Wood Sewer & Excavating E9238 County Road X New London, WI 54961 RE: Change Order No. 1 (Final) Contract 16-20 Dear Ms. Wood: Enclosed is an executed copy of Change Order No. 1 (Final) between the City of Oshkosh and Wood Sewer & Excavating regarding the abovementioned project. If you have any questions, please call our office at (920)236-5065. Sincerely, 2 11W es Rabe, P.E., CPESC SC& Director of Public Works JER/t1t Enclosure: Change Order No. 1 (Final) cc: Pam Uhrig, City Clerk (w/original) Tara Wendt, Assistant Finance Director (w/copy) File (w/original) I:\Engineering\2016 CONTRACrS\16-20 Mini Stonn Swr-Sturm Lat\Project_lnformation\Contract Page 1 of 1 Info\Change Orders\16-20 Executed CO Al Final Ltr�_12-7-16.docx City Hall,215 Church Avenue P.O. Box 1130 Oshkosh,WI 54903-1130 http://www.ci.oshkosh.wi.us TO: Wood Sewer& Excavating CHANGE ORDER #1 (FINAL) E9238 Cty Rd X DATE: November 18,2016 New London,WI 54961 Your present contract with the City of Oshkosh,Contract No.16-20,awarded May 24,2016,is hereby amended and changed as follows: NET INCREASE TO: SECTION I-PAVING $10,011.04 NET DECREASE TO: SECTION II-STORM SEWER ($978.80) NET DECREASE TO: SECTION III-SANITARY SEWER ($300.00) NET INCREASE TO CONTRACT $8,732.24 Section I Section II Section III (Paving) (Storm) (Sanitary) Totals Bid Total $87,834.00 $125,670.00 $300.00 $213,804.00 CO N1 $10,011.04 ($978.80) ($300.00) $8,732.24 Contract Total $97,845.04 $124,691.20 $0.00 $222,536.24 CITY OF OSHKOSH BY: City Manager i e k Approved and accepted: Contractor I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh,Wisconsin, under the within Change Order. JU:U Ac�L nm Comptroller Approve s to form: City Attorney CONTRACT 16-20 CHANGE ORDER#1 (FINAL) SECTION I-PAVING ITEM DESCRIPTION UNIT BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE 1100 Removing pavement; Square com tete ass ecified Yards 389.00 431.30 42.30 $10.00 $423.00 1110 Removing curb and gutter; Linear complete asspecified Feet 40.00 49.40 9.40 $5.00 $47.00 1120 Removing concrete and asphalt sidewalk and driveway;complete as Square specified Yards 1253.00 1,325.04 72.04 $2.00 $144.08 1308 7"concrete pavement removal and replacement; including sawing;pavement ties;integral curb and fine grading;turf restoration;and traffic control;complete as Square specified Yards 466.00 203.45 -262.55 $76.00 $19,953.80 1309 7"concrete pavement HES removal and replacement; including sawing;pavement ties;integral curb and fine grading;turf restoration;and traffic control;complete as Square specified Yards 138.00 347.40 209.40 $79.00 $16,542.60 1350 Pavement ties, complete as specified Each 16.00 18.00 2.00 $12.00 $24.00 1370 Turf restoration;complete as Square specified Yards 345.00 268.08 -76.92 $9.00 $692.28 1440 30"curb and gutter;T;with 5"CABC and grading; Linear complete asspecified Feet 40.00 49.40 9.40 $30.00 $282.00 1500 4"concrete sidewalk with 3" CABC and grading;complete Squre asspecified Feet 764.00 834.77 70.77 $6.00 $424.62 1510 6"concrete sidewalk/driveway/ramp with 3"CABC and grading; Square complete asspecified Feet 495.00 490.26 -4.74 $7.00 $33.18 1540 Curb ramp detectable warning field(natural/non- painted),complete as Square specified Feet 16.00 8.00 -8.00 $30.00 $240.00 1550 No.4 reinforcing rods- deformed,epoxy-coated, Linear complete asspecified Feet 155.00 210.00 55.00 $2.00 $110.00 1560 Drilled No.4 sidewalk tie bars -deformed,epoxy-coated, complete as specified Each 104.00 92.00 -12.00 $4.50 $54.00 1700 Sawing existing pavement, Linear complete asspecified Feet 685.00 727.10 42.10 $3.00 $126.30 i i € Page 1 of 3 I CONTRACT 16-20 CHANGE ORDER#1 (FINAL) ITEM DESCRIPTION UNIT BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE 1906 4"asphaltic pavement with 10"CABC and grading; Square complete as s ecified Yards 389.00 431.30 42.30 $49.00 $2,072.70 SECTION I-(BID ITEMS 1100-1906)-SUBTOTAL $20,196.30 ($20,973.26) ADDITIONAL WORK REQUIRED: CO#1 -SECTION I ITEM DESCRIPTION UNIT BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE 1-1710 Sawing concrete pavement full depth;complete as Linear specified Foot 0.00 177.00 177.00 $4.00 $708.00 1-10000 9"concrete pavement doweled;HES removal and replacement;including sawing;pavement ties; integral curb&grading; terracing&traffic control; Square com tete ass ecified Yards 0.00 120.00 120.00 $84.00 $10,080.00 ADDITIONAL WORK: CO#1 -(ITEMS 1-1710-1-10000)-SUBTOTAL $10,788.00 $0.00 NET INCREASE TO: SECTION 1 $10,011.04 SECTION 11-STORM SEWER ITEM DESCRIPTION UNIT BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE 2000 Furnish and install 6"storm Linear sewer,complete as specified Feet 35.00 26.20 -8.80 $70.00 $616.00 2001 Furnish and install 8"storm Linear sewer,complete as specified Feet 210.00 201.10 -8.90 $69.00 $614.10 2003 Furnish and install 12"storm Linear sewer,complete as specified Feet 160.00 153.50 -6.50 $75.00 $487.50 2006 Furnish and install 15"storm Linear sewer,complete as specified Feet 170.00 162.00 -8.00 $77.00 $616.00 2201 Furnish and install standard storm sewer manhole(4' diameter);complete as Vertical specified Feet 10.12 10.19 0.07 $500.00 $35.00 2237 Furnish and install Type 3 inlet(with 18"sump); complete as specified Each 1.00 1.00 $2,000.00 2400 Furnish and install 6"storm Linear sewer,complete as specified Feet 715.00 670.20 -44.80 $84.00 $3,763.20 2404 Furnish and install storm sewer marker balls,complete as specified Each 50.00 47.00 -3.00 $20.00 $60.00 2406 Furnish and install storm sewer clay dams;complete as specified Each 25.00 24.00 -1.00 $40.00 $40.00 2408 Furnish and install storm sewer lateral inlet;complete as specified Each 14.00 11.00 -3.00 1 $490.00 $1,470.00 Page 2 of 3 CONTRACT 16-20 CHANGE ORDER#1 (FINAL) ITEM DESCRIPTION UNIT BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE 2412 Slurry backfill(storm service); complete as specified Cubic Yards 10.00 0.00 -10.00 $80.00 $800.00 2508 Furnish; install;maintain;and remove Type D modified inlet protection;complete as specified Each 60.00 58.00 -2.00 $40.00 $80.00 2850 Connect to existing storm sewer main;complete as specified Each 2.00 4.00 2.00 $200.00 $400.00 2852 Connect to existing storm sewer lateral;complete as specified Each 1.00 1.00 $100.00 2854 Connect lateral to existing storm sewer main;complete as specified Each 13.00 17.00 4.00 $220.00 $880.00 2856 Connect to existing storm sewer manhole;complete as specified Each 2.00 2.00 $220.00 2858 Connect to existing storm sewer inlet;complete as specified Each 3.00 2.00 -1.00 $220.00 $220.00 SECTION II-(BID ITEMS 2014-2960)-SUBTOTAL $1,315.00 ($8,766.80) ADDITIONAL WORK REQUIRED: CO#1 - SECTION II ITEM DESCRIPTION UNIT BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE 1-20000 6"perforated drain tile; Linear complete as specified Foot 0.00 67.00 67.00 $19.00 $1,273.00 1-20001 Storm lateral repair on Bernheim Street for Charter; Lump complete as specified Sum 0.00 1 1.00 1.00 $5,200.00 $5,200.00 ADDITIONAL WORK: CO#1 -(ITEMS 20000-20006)-SUBTOTAL $6,473.00 $0.00 NET DECREASE TO: SECTION II ($978.80) SECTION 111-SANITARY SEWER ITEM DESCRIPTIONUNIT BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE 3114 Furnish and install external sanitary sewer manhole chimney seal; complete as specified Each 1.00 0.00 -1.00 $300.00 $300.00 SECTION 111-(BID ITEMS 3114)-SUBTOTAL $0.00 ($300.00) NET DECREASE TO: SECTION 111 ($300.00) NET INCREASE TO SECTIONS I,11,&III $38,772.30 NET DECREASE TO SECTIONS I, 11,&111 ($30,040.06) NET INCREASE TO CONTRACT: $8,732.24 Page 3 of 3