HomeMy WebLinkAbout22. Demolition and remediation charges for arena developmentTO: Honorable Mayor & Members of the Common Council
Mark Rohloff, City Manager
FROM: Allen Davis, Community Development Director
DATE: June 30, 2017
RE: Demolition and remediation charges for Buckstaff property for arena
development; Statewide Razing/Advanced Asbestos Removal - $45,907 and
Vinton Construction- payment for crushed gravel $70,000
The Buckstaff demolition and remediation project remains under budget. As the attached table
indicates, the sources and uses of the demolition and remediation funds have been provided by
a number of sources, both private and public, due to the Settlement Agreement, grants, and the
City's Capital Improvement Programs for 2016-2017 allocated for blight removal.
Statewide Razing/Advanced Asbestos Removal. The additional asbestos removal work was
done in 2016 and was based on more asbestos being discovered in the Buckstaff buildings in the
course of demolition. The additional asbestos removal costs were paid from the Escrow Account
at the time. The final Statewide Razing bill of $45,907 will be paid from City's 2016 Blight
Removal CIP funds.
Vinton Construction. City crews excavated and hauled the Buckstaff foundations and other
masonry to a site where Vinton crushed the material into gravel. The crushed concrete and
masonry gravel can now be used by the City for other public works projects in the City, as
permitted. The cost of the concrete crushing is $70,000 and will be paid from the City's 2017
Blight Removal CIP funds.
After accounting for the two demolition and remediation charges for the Buckstaff demolition
and remediation project, the Buckstaff demolition and remediation project remains under
budget by about $50,000.
City Hall, 215 Church Avenue P.O. Box 1130 Oshkosh, WI 54903-1130 920.236.5000 http://www.ci.oslikosh.wi.us
IM
k �
n, r�
9 2 Rv.
Oshkosh
Uses/Sources
Bank/Cowie
Grants:
2016 City
2017 City
Total
CDBG &
Blight
Blight
WEDC
Removal
Removal
CIP
CIP
Building
$543,000
$308,000
$851,000
Demolition
CDBG
(Statewide
Razing/Advanced
Asbestos
Removal)
Additional
$46,000
$46,000
Asbestos
Removal and
Schmidt Title
Phase 1 & 2
60,000
5,000
$65,000
Environmental
Testing and
Reporting
(AECOM)
Environmental
94,000
51,000
$145,000
consulting-
+25,000
+25,000
Foundations and
VPLE (AECOM)
Outside Attorney
61,000
$61,000
Fees
Buckstaff
150,000
83,000
$243,000
Foundation
WEDC
($193,000
removal (DPW)
10,000
projected)
(Vinton)
CDBG
Total
$543,000
$468,000
$200,000
$225,000
$1,436,000