PURPOSE: AMEND 2017 CAPITAL IMPROVEMENT PROGRAM — FIELD
OPERATION FACILITY LANDSCAPING ($15,000.00)
INITIATED BY: CITY ADMINISTRATION
WHEREAS, the City Manager has prepared, submitted and recommended a
Capital Improvement Program for the year 2017, wherein is listed all anticipated revenue
and expenditures for said year, which program has been filed with the Common Council
and the City Clerk, and is available for public inspection; and
WHEREAS, it is necessary to amend the 2017 Capital Improvement Program to
add additional funding for the Field Operation Facility Landscaping to fully comply with
the Zoning Code requirements; and
WHEREAS, funds are available from the Major Equipment Replacement section
of the CIP from the purchase of two (2) tandem-axle dump trucks for the Streets Division
that came in under budget.
NOW, THEREFORE, BE IT RESOLVED by the Common Council of the City of
Oshkosh that the 2017 Capital Improvement Program, on file in the Office of the City
Clrk, is hereby approved with adjustments as listed in attached Exhibit "2".
r,A
City
of
Oshkosh
MEMORANDUM
TO: Honorable Mayor and Members of th/Con Council
FROM: James Rabe, Director of Public Works
DATE: June 8, 2017
RE: Amend 2017 Capital Improvement Program — Field Operation Facility Landscaping
BACKGROUND
At the July 26, 2016 meeting, the Common Council awarded the bid for Public Works Contract 16-26 to
Highway Landscapers, Inc. for Landscaping — Biofilters for the Public Works Field Operations Facility. The
bid award included only some of the potential alternatives bid with the project in order to stay within
available budget.
ANALYSIS
In order to fully comply with the Zoning Code requirements for landscaping, the Field Operations Facility
still has more landscaping to install. Future Capital Improvement Program (CIP) budgets will include a
request to install the remaining code -required landscaping materials.
This CIP amendment will move $15,000 from the Major Equipment Replacement section of the CIP to the
Property Improvements section of the CIP from the two (2) tandem -axle dump trucks for Streets Division
that came in under budget
FISCAL IMPACT
The fiscal impact of this resolution will shift approved budgetary funds from one section of the CIP to
another.
RECOMMENDATIONS
I recommend approval of the 2017 Capital Improvement Program amendment.
Approved,
Mark A. Rohloff
City Manager
JER/tit
I: \ Engineering\Tracy Taylor\Memos to Mayor & Common Council \ 2017\ Amend CIP - FoF Page 1 of 1
Landscaping 06-08-2017.docx
APPROVED AMENDMENT: 03.14.17 Res 17-116
Add: Convention Center Capital Project $1,500,000.00
Funded with State Trust Fund Loan, applied for March 2017 or
project contingency
APPROVED AMENDMENT: 04.11.17 Res 17-191
Add: Implement People of the Water Exhibit $130,000
Funded with Donations
PROPOSED AMENDMENT: 06.13.17 Res 17-293
Add: Landscaping for Field Operations Facility
Funded by mooing $15,000 from Major Equipment
to Property Improcements
2017 CAPITAL IMPROVEMENT PROGRAM ADJUSTMENTS
PROP. IMP. PARK
PAGE STREETS TRAFFIC EQUIPMENT IMPROV SIDEWALKS WATER SANITARY STORM
T$- $ - $ 1,500,000 $ - $ - $ - $ - $ -
$ - $ - $ - $ - $ - $ - $ - $ -
EXHIBIT 2
TOTAL
$ - $
- $ 130,000 $
- $
- $
- $ - $ -
$ 130,000
$ 1,630,000 $ - $ - $ - $ - $ - $ 1,63Q,000