HomeMy WebLinkAbout14. 17-282 JUNE 13, 2017 17-282 RESOLUTION
(CARRIED 7-0 LOST LAID OVER WITHDRAWN )
PURPOSE: APPROVE CHANGE ORDER NO. 1 FOR PUBLIC WORKS
CONTRACT NO. #16-09 WATER MAIN RELAY AND
INSTALLATION (-$32,018.57)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
Carl Bower & Sons
N1844 Maloney Road
Kaukauna, WI 54130
Net Decrease to contract: ($32,018.57)
PURPOSE: See attached Change Order.
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Acct. Nos. 311-0410-7480-00000 Sidewalk Construction Fund
317-0410-7480-03304 Special Assessment Fund — Sidewalks
315-0410-7480-00000 Street Improvement Fund — Streets
317-0410-7480-03301 Special Assessments Fund — Streets
541-1810-1799-00000 Water Utility— Construction in Progress
317-0410-7480-03303 Special Assessments Fund —Water
551-1910-1799-00000 Sewer Utility— Construction in Progress
317-0410-7480-03302 Special Assessments Fund — Sewer
561-2010-1799-00000 Storm Utility— Construction in Progress
317-0410-7480-03305 Special Assessments Fund — Storm Water
r,A
City
of
Oshkosh
Ike[ ►Vit laZW8, KV,i
TO: Honorable Mayor and Members of the Common Council
FROM: Steven M. Gohde, Assistant Director of Public WorksS f)
DATE: June 8, 2017
RE: Change Order No. 1 for Public Works Contract No. 16-09
Water Main Relay and Installation, Carl Bowers & Sons Construction Co., Inc. (-$32,018.57)
BACKGROUND
Change Order No. 1 for Contract 16-09 is scheduled for consideration by the Common Council at the June 13,
2017 meeting. The contract was originally awarded to Carl Bowers & Sons Construction Co., Inc. in July of 2016.
This change order is for additional services provided.
ANALYSIS
Following is a summary of the significant changes to each section of the CIP:
• Streets — Final quantities adjusted to match field conditions.
• Storm Sewer — Final quantities adjusted to match field conditions.
• Sanitary Sewer — Final quantities adjusted to match field conditions.
• Water Main — Final quantities adjusted to match field conditions. There was a design change to install
the water services to the front of walk instead of back of walk, which reduced costs.
FISCAL IMPACT
Contract Section
Change Order Amount
New Contract Total
CIP Budget Amount
Street/Sidewalk
$3,934.26
$143,215.26
$200,000.00
Storm Sewer
$3,875.99
$14,483.99
$15,000.00
Sanitary Sewer
$1,985.48
$146,618.48
$205,000.00
Water Main 1
-$41,814.301
$500,429.70
$1,245,000.00
Totals 1
-$32,018.571
$804,747.43
$1,665,000.00
Adequate funds are available in the relating sections of the 2016 Capital Improvement Budget.
RECOMMENDATIONS
I recommend approval of Change Order No. 1 to Contact No. 16-09 in the amount of -$32,018.57 to Carl Bowers
& Sons Construction Co., Inc.
Approved:
Mark A. Rohloff
City Manager
SMG/tlt
1:\ Engineering \2016 CONTRACrS\16-09 Wtr Mn Relay & Installation\Project_Information\Correspondence\Memo \16-09 Memo for CO #1-"-17.docn
TO: CARL BOWERS & SONS
N1844 MALONEY ROAD
KAUKAUNA, WI 54130
CHANGE ORDER #1
DATE: JUNE 2, 2017
Your present contract with the City of Oshkosh, Contract No. 16-09, awarded July 26, 2016, is hereby
amended and changed as follows:
NET INCREASE TO:
SECTION I - PAVING
$3,934.26
NET INCREASE TO:
SECTION II - STORM SEWER
$3,875.99
NET INCREASE TO:
SECTION III - SANITARY SEWER
$1,985.48
NET DECREASE TO:
SECTION IV - WATER MAIN
($41,814.30)
NET DECREASE TO CONTRACT
($32,018.57)
SECTION I
SECTION 11 SECTION III
SECTION IV
(PAVING)
(STORM) (SANITARY)
(WATER)
TOTALS
BID TOTAL $251,624.90
$10,611.01 $128,301.77
$446,228.25
$836,765.93
CO #1 $3,934.26
$3,875.99 $1,985.48
($41,814.30)
($32,018.57)
CONTRACT TOTAL $255,559.16
$14,487.00 $130,287.25
$404,413.95
$804,747.36
CITY OF OSHKOSH
BY:
City Manager
City Clerk
Approved and accepted:
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin,
under the within Change Order.
Approved as to form:
City Attorney
Comptroller
CONTRACT 16-09 CHANGE ORDER #1
SECTION I - PAVING
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
UNIT
INCREASE IN
DECREASE IN
NUMBER
QUANTITY
QUANTITIES
INCREASE
DECREASE
PRICE
CONTRACTPRICE
CONTRACTPRICE
Removing pavement;
Square
1100
complete as specified
Yards
15.00
110.00
95.00
$20.00
$1,900.00
Removing concrete and
asphalt sidewalk and
driveway; complete as
Square
1120
specified
Feet
3,335.00
1,308.10
-2,026.90
$0.70
($1,418.83
7" concrete pavement
removal and replacement;
including sawing; pavement
ties; integral curb and fine
grading; turf restoration; and
traffic control; complete as
Square
1308
specified
Yards
500.00
570.00
70.00
$64.30
$4,501.00
8" concrete pavement
removal and replacement;
including sawing; pavement
ties; integral curb and fine
grading; turf restoration; and
traffic control; complete as
Square
1318
specified
Yards
410.00
435.43
25.43
$69.30
$1,762.30
Adjust manholes and inlets;
1360
complete as specified
Each
4.00
6.00
2.00
$250.00
$500.00
Turf restoration; complete as
Square
1370
specified
Yards
260.00
629.40
369.40
$7.00
$2,585.80
12" radius curb with 6" CABC
and grading; complete as
Linear
1410
specified
Feet
70.00
47.70
-22.30
$12.00
$267.60
30" curb and gutter; T; with
5" CABC and grading;
Linear
1440
complete as specified
Feet
420.00
82.20
-337.80
$28.00
$9,458.40
4" concrete sidewalk with 3"
CABC and grading; complete
Square
1500
as specified
Feet
4,630.00
1,096.40
-3,533.60
$4.50
$15,901.20
6" concrete sidewalk/
driveway/ramp with 3" CABC
and grading; complete as
Square
1510
specified
Feet
190.00
211.70
21.70
$5.25
$113.93
Curb ramp detectable
warning field (natural/non-
painted); complete as
Square
1540
specified
Feet
24.00
32.00
8.00
$30.00
$240.00
No. 4 reinforcing rods -
deformed; epoxy -coated;
Linear
1550
complete as specified
Feet
1,460.00
198.50
-1,261.50
$1.20
$1,513.80
Drilled No. 4 sidewalk tie bars
- deformed; epoxy -coated;
1560
complete as specified
Each
250.00
56.00
-194.00
$4.00
$776.00)
Sawing existing pavement;
Linear
1700
complete as specified
Feet
5,100.00
4,921.00
-179.00
$1.50
$268.50
Tack coat; complete as
1900
specified
Gallons
608.00
456.00
-152.00
$3.50
($532.00
HMA Pavement Type E-1.0;
1902
complete as specified
Tons
1,260.00
1,221.23
-38.77
$58.50
$2,268.05)
5" asphaltic pavement with
10" CABC and grading;
Square
1905
complete as specified
Yards
20.00
23.00
3.00
$48.50
$145.50
2" asphaltic pavement with
10" CABC and grading;
Square
1907
complete as specified
Yards
3,254.00
2,709.60
-544.40
$9.10
$4,954.04
Page 1 of 6
CONTRACT 16-09 CHANGE ORDER #1
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
UNIT
INCREASE IN
DECREASE IN
NUMBER
DESCRIPTION
UNIT
QUANTITY
QUANTITIES
INCREASE
DECREASE
PRICE
CONTRACT PRICE
CONTRACT PRICE
Asphaltic pavement milling;
Square
1950
complete as specified
Yards
8,530.00
8,452.20
-77.80
$1.95
($151.71)
1-10000
Prepare foundation for
Yards
0.00
1,649.77
1,649.77
-54.00
$18.00
$29,695.86
$2,052.00
asphaltic paving; complete as
Lump
1960
specified
I Sum
1.00
1.00
$17,000.00
SECTION I - (BID ITEMS 1100-1960) - SUBTOTAL $11,748.53 ($37,510.13)
SECTION I - ADDITIONAL WORK REQUIRED: CO #1
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
UNIT
INCREASE IN
DECREASE IN
NUMBER
QUANTITY
QUANTITIES
INCREASE
DECREASE
PRICE
CONTRACT PRICE
CONTRACT PRICE
Excavation (8" thick);
including rock; complete as
Square
1-10000
specified
Yards
0.00
1,649.77
1,649.77
-54.00
$18.00
$29,695.86
$2,052.00
SECTION I - (ADDITIONAL WORK REQUIRED: CO #1 - ITEM 1-10000) - SUBTOTAL $29,695.86 $0.00
NET INCREASE TO: SECTION 1 $3,934.26
SECTION II - STORM SEWER
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
UNIT
INCREASE IN
DECREASE IN
NUMBER
QUANTITY
QUANTITIES
INCREASE
DECREASE
PRICE
CONTRACT PRICE
CONTRACT PRICE
Furnish and install 6" storm
sewer lateral; complete as
Linear
2400
specified
Feet
90.00
36.00
-54.00
$38.00
$2,052.00
Furnish and install storm
sewer marker balls; complete
2404
as specified
Each
8.00
4.00
-4.00
$30.00
$120.00)
Furnish and install storm
sewer clay dams; complete
2406
as specified
Each
4.00
2.00
-2.00
$30.00
$60.00
Furnish and install storm
sewer lateral inlet; complete
2408
as specified
Each
2.00
1.00
-1.00
$400.00
($400.00)
Furnish; install; maintain; and
remove Type D modified inlet
protection; complete as
2508
specified
Each
41.00
15.00
-26.00
$90.00
$2,340.00)
Sediment removal - Type D
modified inlet protection;
2510
complete as specified
Each
41.00
0.00
-41.00
$1.00
($41.00
Furnish; install; maintain; and
remove stone tracking pad;
2512
complete as specified
Each
1.00
0.00
-1.00
$0.01
($0.01)
Furnish; install; maintain; and
remove stone bag; complete
2516
as specified
Each
30.00
0.00
-30.00
$10.00
$300.00
Furnish; install; maintain; and
remove 12" diameter
sediment logs; complete as
Linear
2518
specified
Feet
20.00
0.00
-20.00
$10.00
$200.00
Connect to existing storm
sewer lateral; complete as
2852
specified
Each
3.00
2.00
-1.00
$400.00
$400.00
Page 2 of 6
CONTRACT 16-09 CHANGE ORDER #1
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
UNIT
INCREASE IN
DECREASE IN
NUMBER
DESCRIPTION
UNIT
QUANTITY
QUANTITIES
INCREASE
DECREASE
PRICE
CONTRACT PRICE
CONTRACT PRICE
Storm sewer utility line
opening (ULO); complete as
Linear
2914
specified
Each
1.00
0.00
-1.00
$600.00
$600.00
SECTION II - (BID ITEMS 2400-2914) - SUBTOTAL $0.00 ($6,513.01)
SECTION II - ADDITIONAL WORK REQUIRED: CO #1
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
UNIT
INCREASE IN
DECREASE IN
NUMBER
QUANTITY
QUANTITIES
INCREASE
DECREASE
PRICE
CONTRACT PRICE
CONTRACT PRICE
Install storm sewer; manhole
and inlet on Sawyer Street;
Linear
3000
time and materials; complete
Lump
850.00
798.00
-52.00
$82.00
($4,264.00)
1-20000
as specified
Sum
0.00
1.00
1.00
$10,389.00
$10,389.00
SECTION II - (ADDITIONAL WORK REQUIRED: CO #1 - ITEM 1-20000) - SUBTOTAL $10,389.00 $0.00
NET INCREASE TO: SECTION 11 $3,875.99
SECTION III - SANITARY SEWER
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
UNIT
INCREASE IN
DECREASE IN
NUMBER
QUANTITY
QUANTITIES
INCREASE
DECREASE
PRICE
CONTRACT PRICE
CONTRACT PRICE
Furnish and install 8" sanitary
sewer (relay); complete as
Linear
3000
specified
Feet
850.00
798.00
-52.00
$82.00
($4,264.00)
Furnish and install 10"
sanitary sewer (relay);
Linear
3002
complete as specified
Feet
75.00
78.00
3.00
$90.00
$270.00
Furnish and install 10"
sanitary sewer drop;
Vertical
3062
complete as specified
Feet
3.00
3.10
0.10
$450.00
$45.00
Furnish and install standard
sanitary sewer manhole (4'
diameter); complete as
Vertical
3100
specified
Feet
30.30
27.00
-3.30
$270.00
$891.00)
Furnish and install external
sanitary sewer manhole
chimney seal; complete as
3114
specified
Each
2.00
0.00
-2.00
$400.00
$800.00)
Furnish and install internal
sanitary sewer manhole
chimney seal; complete as
3118
Ispecified
Each
1 2.00
0.00
-2.00
$300.00
$600.00)
Furnish and install 8" x 6"
sanitary sewer factory wyes
3210
or tees; complete as specified
Each
12.00
17.00
5.00
$80.00
$400.00
Furnish and install 6" sanitary
sewer "Insert -A -Tee" or "Kor-
N-Tee'; complete as
3222
specified
Each
3.00
0.00
-3.00
$150.00
$450.00
Furnish and install 4'16"
sanitary sewer lateral (relay);
Linear
3234
complete as specified
Feet
425.00
228.00
-197.00
$68.00
($13,396.00)
Furnish and install sanitary
sewer lateral marker balls;
3236
complete as specified
Each
24.00
28.00
4.00
$30.00
$120.00
Furnish and install clay dams;
3238
com fete as specified
Each
12.00
15.00
3.00
$100.00
$300.00
Page 3 of 6
CONTRACT 16-09 CHANGE ORDER #1
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
UNIT
INCREASE IN
DECREASE IN
NUMBER
QUANTITY
QUANTITIES
INCREASE
DECREASE
PRICE
CONTRACT PRICE
CONTRACT PRICE
Furnish and install connection
1-30000
to existing 8" mains; complete
Each
0.00
13.00
13.00
$350.00
$4,550.00
3300
as specified
Each
6.00
8.00
2.00
$600.00
$1,200.00
1-30001
Furnish and install connection
Feet
0.00
2,947.20
2,947.20
-4.50
$1.00
$2,947.20
$540.00
to existing 10" mains;
3302
complete as specified
Each
3.00
4.00
1.00
$1,000.00
$1,000.00
Furnish and install sanitary
Linear
1-30003
sewer concrete collars;
Feet
0.00
2,360.70
2,360.70
-7.00
$1.50
$3,541.05
$525.00
3330
complete as specified
Each
2.00
0.00
-2.00
$0.01
($0.02
:Furnish
Rock excavation; complete as
Cubic
3600
specified
Yards
75.00
0.00
2.00
-75.00
$0.01
$370.00
($0.75)
4004]specified
Closed circuit televising;
Linear
2,805.00
2,743.00
-62.00
$82.65
($5,124.30)
3700
complete as specified
Feet
925.00
0.00
-925.00
$2.00
$1,850.00)
1-30005
Abandon 8" sanitary sewer;
Linear
0.00
1.00
1.00
$1,000.00
$1,000.00
3802
complete as specified
Feet
40.00
39.00
-1.00
$6.00
$6.00
SECTION III - (BID ITEMS 3000-3802) - SUBTOTAL $3,335.00 ($22,257.77)
SECTION III - ADDITIONAL WORK REQUIRED: CO #1
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
UNIT
INCREASE IN
DECREASE IN
NUMBER
QUANTITY
QUANTITIES
INCREASE
DECREASE
PRICE
CONTRACT PRICE
CONTRACT PRICE
Sanitary main televising
1-30000
launch; complete as specified
Each
0.00
13.00
13.00
$350.00
$4,550.00
Sanitary main televising;
Linear
1-30001
complete as specified
Feet
0.00
2,947.20
2,947.20
-4.50
$1.00
$2,947.20
$540.00
Sanitary lateral televising
1-30002
launch; complete as specified
Each
0.00
61.00
61.00
$100.00
$6,100.00
Sanitary lateral televising;
Linear
1-30003
complete as specified
Feet
0.00
2,360.70
2,360.70
-7.00
$1.50
$3,541.05
$525.00
Sanitary lateral push cam
:Furnish
televising; complete as
1-30004
specified
Each
0.00
2.00
2.00
$185.00
$370.00
4004]specified
Mobilization for unmarked
Feet
2,805.00
2,743.00
-62.00
$82.65
($5,124.30)
sanitary lateral; complete as
Lump
1-30005
specified
Sum
0.00
1.00
1.00
$1,000.00
$1,000.00
Remove and replace sanitary
manhole; time and materials;
Lump
1-30006
complete as specified
Sum
0.00
1.00
1.00
$2,400.00
$2,400.00
SECTION III - (ADDITIONAL WORK REQUIRED: CO #1 - ITEMS 1-30000 - 1-30006) - SUBTOTAL $20,908.25 $0.00
NET INCREASE TO: SECTION III $1,985.48
SECTION IV - WATER MAIN
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
UNIT
INCREASE IN
DECREASE IN
NUMBER
QUANTITY
QUANTITIES
INCREASE
DECREASE
PRICE
CONTRACT PRICE
CONTRACT PRICE
Furnish and install 4" ductile
iron water main (relay) with
polywrap; complete as
Linear
4000
specified
Feet
10.00
5.50
-4.50
$120.00
$540.00
Furnish and install 6" ductile
iron water main (relay) with
polywrap; complete as
Linear
4002
specified
Feet
260.00
253.00
-7.00
$75.00
$525.00
and install 8" ductile
:Furnish
iron water main (relay) with
polywrap; complete as
Linear
4004]specified
Feet
2,805.00
2,743.00
-62.00
$82.65
($5,124.30)
Page 4 of 6
CONTRACT 16-09 CHANGE ORDER #1
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
UNIT
INCREASE IN
DECREASE IN
NUMBER
QUANTITY
QUANTITIES
INCREASE
DECREASE
PRICE
CONTRACT PRICE
CONTRACT PRICE
Furnish and install 12" ductile
iron water main (relay) with
polywrap and TR Flex
restrained joints; complete as
Linear
4009
specified
Feet
25.00
18.00
-7.00
$130.00
$910.00
Furnish and install 1" water
service (relay); complete as
Linear
4036 Ispecified
Feet
1,650.00
1,372.00
-278.00
$40.00
($11,120.00)
Furnish and install 2" water
service (relay); complete as
Linear
4040
specified
Feet
20.00
0.00
-20.00
$71.00
$1,420.00
Furnish and install 1"
corporation and stop box;
4048
complete as specified
Each
53.00
50.00
-3.00
$300.00
($900.00
Furnish and install 2"
corporation and stop box;
4053
complete as specified
Each
1.00
0.00
-1.00
$1,000.00
($1,000.00)
Furnish and install water
service clay dams; complete
4055
as specified
Each
57.00
56.00
-1.00
$75.00
$75.00
Furnish and install
connections to existing 4"
water main; complete as
4056
specified
Each
1.00
1.00
$1,100.00
Furnish and install
connections to existing 6"
water main; complete as
4058
specified
Each
5.00
4.00
-1.00
$1,400.00
($1,400.00
Furnish and install
connections to existing 8"
water main; complete as
4060
Ispecified
Each
1.00
1.00
$1,500.00
Furnish and install
connections to existing 12"
water main; complete as
4064
specified
Each
4.00
2.00
-2.00
$1,800.00
($3,600.00)
Furnish and install 8" x 4"
water main tee; complete as
4109
specified
Each
1.00
1.00
$325.00
Furnish and install 8" x 6"
water main tee; complete as
4110
specified
Each
7.00
8.00
1.00
$400.00
$400.00
Furnish and install 6" x 8"
water main cross; complete
4182
as specified
Each
2.00
2.00
$550.00
Furnish and install 8" x 12"
water main cross; complete
4191
as specified
Each
1.00
1.00
$900.00
Furnish and install 4" 45
degree water main bend;
4235
complete as specified
Each
2.00
2.00
$200.00
Furnish and install 6" 45
degree water main bend;
4236
complete as specified
Each
14.00
4.00
-10.00
$225.00
($2,250.00)
Furnish and install 8" 45
degree water main bend;
4237
complete as specified
Each
4.00
0.00
-4.00
$300.00
$1,200.00
Furnish and install 12" 45
degre water main bend,
4239
complete as specified
Each
4.00
2.00
-2.00
$600.00
$1,200.00
Page 5 of 6
CONTRACT 16-09 CHANGE ORDER #1
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
UNIT
INCREASE IN
DECREASEIN
NUMBER
QUANTITY
QUANTITIES
INCREASE
DECREASE
PRICE
CONTRACTPRICE
CONTRACTPR/CE
Furnish and install 8" x 6"
water main reducer; complete
4264
as specified
Each
1.00
1.00
2.00
$275.00
$1,200.00
Cut and cap existing 6" water
4352
main; complete as specified
Each
1.00
0.00
2.00
-1.00
$700.00
$3,000.00
$700.00
Cut and cap existing 8" water
4354
main; complete asspecified
Each
1.00
0.00
1.00
-1.00
$800.00
$500.00
($800.00
Cut and cap existing 12"
1-40003
water main; complete as
Each
0.00
2.00
2.00
$475.00
1 $950.00
4358
specified
Each
1.00
0.00
-1.00
$1,200.00
$1,200.00)
Furnish and install 4" water
main gate valve; complete as
4400
specified
Each
1.00
1.00
$1,000.00
Furnish and install 6" water
main gate valve; complete as
4401
specified
Each
12.00
9.00
-3.00
$1,200.00
($3,600.00
Furnish and install 8" water
main gate valve; complete as
4402
specified
Each
12.00
11.00
-1.00
$1,600.00
$1,600.00)
Furnish and install 12" water
main gate valve; complete as
4404
specified
Each
1.00
0.00
-1.00
$2,700.00
$2,700.00
Furnish and install 6" x 6"
tapping valve and sleeve;
4419
complete as specified
Each
1.00
0.00
-1.00
$2,500.00
$2,500.00)
Furnish and install hydrant;
4500
complete as specified
Each
8.00
7.00
-1.00
$3,500.00
$3,500.00
Abandon water main on W
5th Avenue; complete as
Lump
4900
specified
Sum
1.00
1.00
$2,000.00
SECTION IV - (BID ITEMS 4000-4900) - SUBTOTAL
SECTION IV - ADDITIONAL WORK REQUIRED: CO #1
$400.00 ($47,864.30)
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
UNIT
INCREASE IN
DECREASE IN
NUMBER
QUANTITY
QUANTITIES
INCREASE
DECREASE
PRICE
CONTRACT PRICE
CONTRACT PRICE
Furnish and install 12" 22.5
degree bends; complete as
1-4230
specified
Each
0.00
2.00
2.00
$600.00
$1,200.00
Install hydrant only; complete
1-40000
as specified
Each
0.00
2.00
2.00
$1,500.00
$3,000.00
Install 8" gate valve only;
1-40002
complete as specified
Each
0.00
1.00
1.00
$500.00
$500.00
Install 6" gate valve only;
1-40003
complete as specified
Each
0.00
2.00
2.00
$475.00
1 $950.00
SECTION IV - (ADDITIONAL WORK REQUIRED: CO #1 - ITEMS 1-4230 - 1-40003) - SUBTOTAL
NET DECREASE TO: SECTION IV
NET INCREASE TO SECTIONS I, ll, III, & IV
NET DECREASE TO SECTIONS I, II, III, & IV
NET DECREASE TO CONTRACT:
Page 6 of 6
$5,650.00 $0.00
($41,814.30)
$82,126.64
($114,145.21)
($32,018.57)