HomeMy WebLinkAbout06. 17-202APRIL 25, 2017
17-202 RESOLUTION
(CARRIED 7-0 LOST LAID OVER WITHDRAWN )
PURPOSE: APPROVE & SUBMIT WISCONSIN DEPARTMENT OF
NATURAL RESOURCES 2016 STORM WATER PROGRAM
ANNUAL REPORT
INITIATED BY: PUBLIC WORKS DEPARTMENT
STORM WATER UTILITY COMMITTEE RECOMMENDATION: Approved
BE IT RESOLVED by the Common Council of the City of Oshkosh that the Storm
Water Program Annual Report, having been reviewed, is approved, and the proper City
officials are authorized and directed to submit the Report to the Department of Natural
Resources.
City
of�
Oshkosh
MEMORANDUM
DATE: April 20, 2017
TO: Honorable Mayor and Members of the Com on Council
FROM: John Ferris, Civil Engineering Supervis
RE: Approve and Submit Wisconsin Depa tment of Natural Resources 2016 Storm Water
Program Annual Report
BACKGROUND
The City of Oshkosh received coverage under the Wisconsin Department of Natural Resources (WDNR) Municipal Separate Storm
Sewer System (MS4) General Permit on January 2, 2007. In May 2014, the City of Oshkosh received notification this coverage was
extended to include the newly -released version of the MS4 General Permit. This permit requires the City to comply with the
following six (6) minimum control measures (as mandated by the Federal Clean Water Act and the Environmental Protection
Agency):
1. Public Information and Education Plan
2. Public Involvement and Participation Program
3. Illicit Discharge Detection and Elimination Program
4. Construction Site Pollutant Control Program
5. Post -Construction Storm Water Management Program
6. Pollution Prevention Program (Prevent pollution from the daily operations of the City)
The Storm Water Utility Committee reviewed the Annual Report and recommended approval as discussed during their April 6,
2017 meeting.
ANALYSIS
The annual report contains information on the activities performed by the City of Oshkosh in compliance with the MS4 Permit
requirements. This report includes the completed WDNR form, as well as supplemental information the WDNR Form did not
have room to enter. The final year end financial data is still being compiled by the Finance Department, and the final 2016
expenditures may be slightly different than those shown in the table. City staff has more details available for the WDNR, should
they be requested.
FISCAL IMPACT
There is no anticipated fiscal impact from the approval of this resolution.
RECOMMENDATION
Staff recommends approval of the resolution.
Approved:
Mark ohloff
City Manager
1:\ Engineering\Storm Water Information\MS4 Permit Items\DNR Submittals\2016 Annual Report\2017 Resolution for 2016 Annual Report\2016 Annual Report Council Memo-420-17.docx
State of Wisconsin
Department of Natural Resources
dnr.wi.gov
Due by March 31, 2017
Annual Report under MS4
General Permit No. WI-SO50075-2
Form 3400-195 (R 11/16) Page 1 of 9
Notice: Pursuant to s. NR 216.07(8), Wis. Adm. Code, an owner or operator of a Municipal Separate Storm Sewer System (MS4) is required to
submit an annual report to the Department of Natural Resources (DNR) by March 31 of each year to report on activities for the previous
calendar year. This form is being provided by the DNR for the user's convenience. Personal information collected will be used for administrative
purposes and may be provided to the extent required by Wisconsin's Open Records Law [ss. 19.31-19.39, Wis. Stats.].
This form is for reporting on activities undertaken in calendar year 2016.
Instructions: Complete each section of the form. If additional space is needed, attach additional pages. Provide descriptions that explain the
program actions taken to comply with the general permit. Complete and submit the annual report by March 31, 2017, to the appropriate address
indicated on the last page of this form.
Name of Municipality Facility ID No. (FIN)
City of Oshkosh 1 31078
Mailing Address City State ZIP Code
215 Church Ave Oshkosh I W1 54903
County(s) in which Municipality is located Municipality Type: (select one)
Winnebago O County Q City 0 Village 0 Town 0 Other (specify)
Name of Municipal Contact Person Title
John Ferris Civil Engineer Supervisor
Mailing Address (if different from above) City State ZIP Code
215 Church Ave Oshkosh Wl 1 54903
Email Phone Number (include area code) Fax Number (include area code)
jferris(aci.oshkosh.wi.us (920) 236-5065 1 (920) 236-5068
Has the contact person changed in the last year? 0 Yes * No
l hereby certify that I am an authorized representative of the municipality covered under MS4 General Permit No. WI-SO50075-2 for
which this annual report is being submitted and that the information contained in this document and all attachments were gathered and
prepared under my direction or supervision. Based on my inquiry of the person or persons under my direction or supervision involved
in the preparation of this document, to the best of my knowledge, the information is true, accurate, and complete. / further certify that
the municipality's governing body or delegated representatives have reviewed or been apprised of the contents of this annual report. I
understand that Wisconsin law provides severe penalties for submitting false information.
Authorized Representative Printed Name Authorized Representative Title
Mark Rohloff City Manager
Signature of Authorized Representative Date
Email Phone Number (include area code) Fax Number (include area code)
mrohloffAci.oshkosh.wi.us 1 (920) 236-5000 (920) 236-5039
a. Describe the municipality's efforts to invite the municipal governing body, interest groups, and general public to review and comment
on the annual report.
The Annual Report has been posted on the City's Storm Water Utility Webpage, and has been reviewed and approved
at public meetings of the Storm Water Utility Committee and the Common Council. The general public, in addition to
members of interest groups and the elected official have the opportunity to comment at any of these meetings, as well
as arrange a meeting with the Department of Public Works staff to discuss comments.
b. Describe how the municipality has kept elected and municipal officials and appropriate staff (such as operators, department heads,
and those that interact with the public) informed of the municipal storm water discharge permit and its requirements.
Elected officials are kept apprised of the MS4 Permit and it's regulatory requirements, budgets, projects and other
stormwater related issues through Common Council workshops and through the City Manager's weekly newsletter.
The City of Oshkosh Storm Water Utility Committee is kept up to date through regular committee meetings. Staff are
kept apprised during routine conversations and staff meetings when necessary.
c. Has the municipality prepared or updated its own municipal -wide storm water management plan during the reporting year?
0 Yes * No
If yes, provide the title and date of storm water management plan and list any updates:
31078 City of Oshkosh Annual Report under MS4
FIN / Municipality Name General Permit No. WI-SO50075-2
Form 3400-195 (R11/16) Page 2 of 9
If yes, has the information been submitted to the Department? 0 Yes 0 No
During the reporting year, has the municipality entered into a written agreement with another municipality or a contract with another
entity to perform one or more of the conditions as provided under section 2.10 of the general permit? Yes 0 No
If yes, describe these cooperative efforts:
As member of NEWSC the City of Oshkosh benefits from the many public education and outreach activities that the
organization develops and sponsors. A list of NEWSC's public education and outreach activities for 2016 are listed in
Attachment A accompanying this form. The City has posted public eduction material developed by NEWSC that
instructs residents on how they can play a role in preventing pollution of stormwater runoff on its storm water utility
webpage.
If yes, has the information been submitted to the Department?
Q Yes 0 No
e. If the municipality has an intemet website, is there current information about or links provided to the MS4 general permit and/or the
municipality's storm water management program? Di Yes 0 No
If yes, provide web address:
http://www.ci.oshkosh.wi.us/Publlc—Works/Storm—Water—Utifity/
Part V. Evaluation of Permit Conditions (Section 2 of General Permit)
Minimum Control Measures: For each of the permit conditions listed below, provide an evaluation of program compliance with the
general permit.
1. Public Education and Outreach (Section 2.1 of General Permit)
Description of Program(s)
see 2016 MS4 Annual Report Supplemental Information Attachment B
Measurable Goal(s)
Result(s) Achieved
see 2016 MS4 Annual Report Supplemental Information Attachment B
Describe any planned
changes to program.
2. Public Involvement and Participation (Section 2.2 of General Permit)
Description of Program(s)
see 2016 MS4 Annual Report Supplemental Information Attachment B
Measurable Goal(s)
Result(s) Achieved
see 2016 MS4 Annual Report Supplemental Information Attachment B
Describe any planned
changes to program.
Illicit Discharge Detection and Elimination (Section 2.3 of General Permit)
Description of Program(s)
see 2016 MS4 Annual Report Supplemental Information Attachment B
Measurable Goal(s)
Result(s) Achieved
see 2016 MS4 Annual Report Supplemental Information Attachment B
Describe any planned
changes to program.
4. Construction Site Pollutant Control (Section 2.4 of General Permit)
Description of Program(s)
see 2016 MS4 Annual Report Supplemental Information Attachment B
Measurable Goal(s)
Result(s) Achieved
see 2016 MS4 Annual Report Supplemental Information Attachment B
31078 City of Oshkosh
FIN / Municipality Name
any planned
to program.
5. Post -Construction Storm Water Management (Section 2.5 of General Permit)
Annual Report under MS4
General Permit No. WI-SO50075-2
Form 3400-195 (R11/16) Page 3 of 9
Description of Program(s)
see 2016 MS4 Annual Report Supplemental Information Attachment B
Measurable Goal(s)
Result(s) Achieved
Describe any planned
changes to program.
6. Pollution Prevention (Section 2.6 of General Permit)
Description of Program(s)
see 2016 MS4 Annual Report Supplemental Information Attachment B
Measurable Goal(s)
Result(s) Achieved
Describe any planned
changes to program.
• Storm Water Management Facilities (Section 2.6.1 of General Permit)
List any new municipality owned or operated structural storm water management facilities (ponds, biofilters, etc.) added in the
last year.
1. Fernau Watershed North Main Street Area Stormwater Detention Basin
2. Senior Center Permeable Pavement and Biodetention swale
SW Industrial Park Stormwater Detention Basins A, B and C
4. Aviation Industrial Park Stormwater Detention Basin
5. Dept of Public Works Field Operations Facility - bioswales and subsurface wet detention
Routine Inspection and Maintenance (Section 2.6.2 — 2.6.4 of General Permit)
Does the municipality have an inspection and maintenance program for installed structural storm water management facilities?
* Yes O No
Describe the inspection and maintenance program and any activities that have occurred for structural storm water
management facilities in 2016. If available, attach any additional information on the inspection and maintenance program.
Each City owned stormwater management facility is inspected annually. The inspection documents repairs needed
(erosion or structural), accumulated litter to be removed, condition of vegetation and presence of invasive species
and damage from muskrats and other burrowing animals. The City has an annual nuisance animal trapping
contract to remove the animals from City facilities. During 2016 the City contracted with Applied Ecological to
survey 16 City owned facilities and to make recommendations on how to better manage the native vegetation at
each site.
Describe the street sweeping and catch basin cleaning efforts, and the disposal of waste.
see 2016 MS4 Annual Report Supplemental Information attached
• Winter Road Management Activities (Section 2.6.5 of General Permit)
Provide the name, title, and phone number of the individual(s) with overall responsibility for winter roadway maintenance.
Kevin Uhen, Public Works Field Operations Manager, 920-232-5382
31078 City of Oshkosh Annual Report under MS4
FIN / Municipality Name General Permit No. WI-SO50075-2
Form 3400-195 (R11/16) Page 4 of 9
Describe the types of products used for winter road management (e.g. deicing, pre -wetting, salting, etc.).
Brine for deicing and pre -wetting salt.
Salt
Report the amount of product used by month over the last winter season (approx. November 2015 through April 2016)
o Nov
2015
Salt
0 tons
Brine
0 gallons
o Dec
2015
Salt
400 tons
Brine
6,000 gallons
o Jan
2016
Salt
992 tons
Brine
6,000 gallons
o Feb
2016
Salt
854 tons
Brine
6,000 gallons
o March
2016
Salt
863 tons
Brine
0 gallons
o April
2016
Salt
60 tons
Brine
0 gallons
o Nov
2016
Salt
0 tons
Brine
0 gallons
o Dec
2016
Salt
1,686 tons
Brine 12,142
gallons
Report the snow disposal locations, if applicable.
2333 Bowen, across from 450 N. Campbell Rd., 2449 State Road 44, Global Pkwy, across from 2786 Algoma
Blvd.
Describe anti -icing, equipment calibration, and salt reduction strategies.
The City of Oshkosh minimizes the use of deicing materials (salt and brine) by limiting its use during the winter
and with frequent routine calibration of all equipment used to apply the material following manufacturers
specifications annually and throughout the season to make sure only the prescribed amount of salt is applied to the
streets.
Describe any other additional data or information used to evaluate the winter road management activities.
none
• Leaf Management (Section 2.6.6 of General Permit)
Describe the management of leaves and grass clippings.
Fall Loose Leaf Collection: Fall Loose Leaf Collection runs for 6 consecutive weeks, starting October 10, 2016
and ending November 18, 2016. Collection is scheduled for the day after garbage day for each neighborhood. In
2016, 4,135 manhours was spent operating 25 to 30 vehicles to pick up 2,481 tons of leaves. The Leaves were
hauled to a local landscape firm for composting.
• Municipal Pollution Prevention (Section 2.6.7 of General Permit)
Provide the location (street address) of each facility (municipal yards and/or maintenance facilities) and contact information
(name, title, and phone number) for the individual(s) with overall responsibility for each facility.
see Attachment F
DPW Field Operations - Draft SWPPP
DPW Wastewater Treatment Plant - No Exposure
DPW Water Treatment Plant - No Exposure
The Storm Water Utility is working with the Parks and Transportation Departments to budget and develop
SWPPPs for their facilities.
Map(s) included? QQ Yes Q No - Include a map of each facility, drawn to scale and include the following features:
■ Location of major activities and storage areas
■ Identification of drainage patterns, potential sources of storm contamination and discharge points.
■ Identification of nearby receiving waters or wetlands
■ Identification of connections to the permittees's MS4
Describe the housekeeping activities and best management practices installed at municipal yards and/or maintenance facilities
to reduce or eliminate storm water contamination.
See Draft SWPPP prepared for the Field Operations.
31078 City of Oshkosh
FIN / Municipality Name
Annual Report under MS4
General Permit No. WI-SO50075-2
Form 3400-195 (R11/16) Page 5 of 9
Discuss recommendations for improvements to current storm water management practices at the facility(s) and provide a
timeline for installation and/or implementation of these recommendations.
There are three (3) City sponsored facilities that will be constructed during 2017-2018.
South Park Lagoon Reconstruction: South Park is a bottle neck for all of the stormwater runoff from Stringham
Watershed. To improve the management of stormwater passing through the park the existing lagoons will be
enlarged and deepened to provide flood relief to downstream areas that have a history of flooding. The new
layout of the lagoons will increase the annual removal of TSS to approximately 72 tons (a reduction of 62% of the
annual loads) and 290 pounds of phosphorus (a 59% reduction in annual loads).
Westowne Wet Basin Expansion: Doubles the size of an existing basin designed to increase the annual TSS load
reduction to approximately 70% from a commercial area just south of highway 21.
Parkway Dry Basin Construction: Is a dry pocket wetland in a residential area designed primarily to reduce
neighborhood flooding, but will achieve some water quality benefits.
The City's 5 -Year CIP has an additional three (3) more that will be constructed between 2018 and 2021, provided
funding is available.
Provide information on facility inspections. Identify and address potential sources of storm water contamination.
see 2016 MS4 Annual Report Supplemental Information attached
Describe the municipal facility(s) employee training on storm water pollution prevention (frequency, duration, objectives,
percentage of employees trained this year, etc.).
Currently employees have been instructed on the proper handling of materials as a routine on-the-job training. As
an outcome of the SWPPP development effort in 2016, a formal training session(s) will be developed in 2017
where all employees will receive training annually to refresh their knowledge of proper procedures.
Describe the spill prevention and response procedures in place at the municipal facility(s).
Currently employees have been instructed on spill response when a new employee starts or when a new policy is
adopted. As an outcome of the SWPPP development effort in 2016, a formal training session(s) will be developed
in 2017 where all employees will receive training annually to refresh their knowledge of proper safety procedures.
7. Storm Water Quality Management (Section 2.7 of General Permit)
Has the municipality completed a pollutant -loading analysis to assess compliance with the 20% TSS reduction developed urban
area performance standard? 0 Yes Q No
If yes, provide the following: Model used WinSLAM Version 10.0 Reduction (%) 32
If no, include a description of any actions the municipality has undertaken during 2016 to help achieve the 20% standard.
8. Storm Sewer System Map (Section 2.8 of General Permit)
Describe any changes or updates to the storm sewer system map made in the reporting year. Provide an updated map if any
changes occurred during the reporting year.
Storm Sewer and Storm Water Management Facilities constructed during the past year have been updated in the
City's GIS. Updated maps are included with this submittal.
31078 City of Oshkosh
FIN / Municipality Name
Annual Report under MS4
General Permit No. WI-SO50075-2
Form 3400-195 (R11/16) Page 6 of 9
Part VI. Fiscal Analysis
a. Provide a fiscal analysis that includes the annual expenditures for 2016, and the budget for 2016 and 2017. A table to document
fiscal information is provided on page 8.
see completed table below
b. What financing/fiscal strategy has the municipality implemented to finance the requirements of the general permit?
® Storm water utility ❑ General fund ❑ Other
c. Is adequate revenue generated to implement the storm water management program and meet permit requirements?
Q Yes Q No
Please provide a brief summary of the municipality's financing/fiscal strategy and any additional information that will assist the
Department in understanding how storm water management funds are being generated to implement and administer the storm water
management program.
The City of Oshkosh Storm Water Program is funded primarily with user fees. Currently the rate is $148.88 per year
and is billed quarterly. The user fees also cover debt on capital improvements. The City has been successful in
securing grants from DNR and FEMA to help defer some of the cost of capital construction and watershed planning.
Part VII. Inspections and Enforcement Actions
Note: If an ordinance listed below has been submitted to the Department previously and has not been amended since that
time, a copy does not need to be submitted again. If the ordinance was previously submitted, indicate such in the space
provided.
a. Has the municipality amended its illicit discharge detection and elimination ordinance in accordance with subsection 2.3.1 of the
general permit during the reporting year?
Q Yes *No
If yes, attach copy or provide web link to ordinance:
b. Has the municipality amended its construction site pollutant control ordinance in accordance with subsection 2.4.1 of the general
permit during the reporting year? Q Yes *No
If yes, attach copy or provide web link to ordinance:
c. Has the municipality amended its post -construction storm water management ordinance in accordance with subsection 2.5.1 of the
general permit during the reporting year? Q Yes *No
If yes, attach copy or provide web link to ordinance:
d. Has the municipality adopted any other ordinances it has deemed necessary to implement a program under the general permit
(e.g., pet waste ordinance, leaf management/yard waste ordinance, parking restrictions for street cleaning, etc.) during the
reporting year?
Q Yes Q No
If yes, attach copy or provide web link to ordinance:
e. Provide a summary of available information on the number and nature of inspections and enforcement actions conducted during the
reporting period to ensure compliance with the ordinances described in a. to d. above.
see 2016 MS4 Annual Report Supplemental Information attached
Part Vill. Water Quality Concerns
a. Does any part of the MS4 discharge to an outstanding resource water (ORW) or exceptional resource water (ERW) listed under s.
NR 102.10 or 102.11, Wis. Adm. Code? (A list of ORWs and ERWs may be found on the Department's Intemet site at:
hftp://dnr.wi.gov/topic/surfacewater/orwerw.html) Q Yes *No
If yes, list:
b. Does any part of the MS4 discharge to an impaired waterbody listed in accordance with section 303(d)(1) of the federal Clean Water
Act, 33 USC § 1313(d)(1)(C)? (A list of the most current Wisconsin impaired waterbodies may be found on the Department's
Internet site at: http://dnr.wi.gov/water/impairedsearch aspx?status=303d) *Yes Q No
If yes, complete the following:
31078 City of Oshkosh Annual Report under MS4
FIN / Municipality Name General Permit No. WI-SO50075-2
Form 3400-195 (R 11/16) Page 7 of 9
• Impaired waterbody to which the MS4 discharges:
Lake Winnebago, Fox River and Lake Butte des Morts
Description of actions municipality has taken to comply with section 1.5.2 of the MS4 general permit for discharges of pollutant(s)
of concern to an impaired waterbody:
Fox River: Listed for PAHs. There are no current discharges that would contribute to this pollutant.
Lake Butte des Morts: Listed for Mercury, PCBs, Sediment, and Phosphorus. Mercury is atmospheric
deposition, which the City cannot implement a means to reduce. PCBs are no longer used in industrial processes
along the river, and thus there are no longer discharges that would contribute to this pollutant. Sediment is being
addressed on a City -Wide basis, as required by the MS4 Permit. Phosphorus reductions will be associated with
the reduction in sediment on a City -Wide basis. Phosphorus is being addressed under the I&E plan to get
residents to reduce the use of phosphorus based fertilizers on their lawns. The City of Oshkosh is prepared to
develop a plan to reduce phosphorus and will do so once the TMDL for the Upper Fox River Basin is complete,
and the requirements are known.
Lake Winnebago: Listed for Mercury, Sediment, and Phosphorus. Mercury is atmospheric deposition, which the
city cannot implement a means to reduce. Sediment is being addressed on a City Wide basis, as required by the
MS4 Permit. Phosphorus reductions will be associated with the reduction in sediment on a City Wide basis.
Phosphorus is being addressed under the I&E Plan to get residents to reduce the use of phosphorus based
fertilizers on their lawns. The City of Oshkosh is prepared to develop a plan to reduce phosphorus and will do so
once the TMDL for the Upper Fox River Basin is complete, and the requirements are known.
c. Identify any known water quality improvements in the receiving water to which the MS4 discharges during the reporting period.
none
d. Identify any known water quality degradation in the receiving water to which the MS4 discharges during the reporting period and
what actions are being taken to improve the water quality in the receiving water.
none
e. Does any part of the MS4 discharge to an approved Total Maximum Daily Load (TMDL) area (Section 1.5.4 of the general permit)?
Q Yes Q No
If yes, fill out below. If no, disregard.
Required reporting for TMDLs approved prior to the effective date of the permit for 2016:
Name of TMDL:
Date TMDL approved?
Map(s) included? Q Yes O No - Submit a storm sewer system map (may be the same map submitted under section V.6. of
this form), which includes the TMDL reachshed boundaries and associated acreage within the municipality, and the MS4
drainage boundaries and associated acreage within the municipality.
ProposedPart IX. ..
Describe any proposed changes to the storm water management program being considered for 2017 and the schedule for
implementing those changes. Proposed program changes must be consistent with the requirements of the general permit.
Construction of improved stormwater management faculties in the City's South Park.
Improvements to City's Storm Water Utility Website that will provide more information to public.
Partner with local Rotary Club on a number of public participation activities.
Any other municipal storm water program information for inclusion in the Annual Report regarding their storm water program may be
added here or attached.
31078 City of Oshkosh
FIN / Municipality Name
Fiscal Analysis Table. Complete the fiscal analysis table provided below.
Annual Report under MS4
General Permit No. WI-SO50075-2
Form 3400-195 (R11/16) Page 8 of 9
Program Element
g
Annual Expenditure
2016
Budget
2016 2017
Source of Funds
Public Education and Outreach
$86,449
$99,372
$111,144
Storm Water Utility Fees
Public Involvement and
$86,449
$99,372
$111,144
Storm Water Utility Fees
Participation
Illicit Discharge Detection and
$325,036
$363,256
$377,792
Storm Water Utility Fees
Elimination
Construction Site Pollutant Control
$103,485
$119,274
$138,246
Storm Water Utility Fees
Post -Construction Storm Water
$127,753
$145,689
$170,286
Storm Water Utility Fees
Management
Pollution Prevention
$1,400,174
$1,558,505
$1,584,100
Storm Water Utility Fund
Wastewater Utility Fund
Water Utility Fund
General Fund
Storm Water Quality Management
(including pollutant -loading
$449,905
$503,064
$521,940
Storm Water Utility Fees
analysis)
Storm Sewer System Map
$29,122
$31,698
$38,448
Storm Water Utility Fees
Other:
$847,917
$960,570
$1,005,300
Storm. Water Utility Fees
31078 City of Oshkosh
FIN / Municipality Name
Annual Report under MS4
General Permit No. WI-SO50075-2
Form 3400-195 (R11/16) Page 9 of 9
Ashland
Langlade
DNR Service Center
Adams
Marathon
Barron
Lincoln
Attn: Storm Water Program
Buffalo
Monroe
Bayfield
Oneida
5301 Rib Mountain Rd.
Chippewa
Pepin
Burnett
Polk
Wausau, WI 54401
Clark
Pierce
Douglas
Price
Phone: (715) 359-4522
Crawford
Portage
Florence
Rusk
Dunn
St. Croix
Forest
Sawyer
Eau Claire
Trempealeau
Iron
Taylor
Jackson
Vernon
Vilas
Juneau
Wood
Washburn
La Crosse
Brown
Marquette
DNR Northeast Region
Columbia
Calumet
Menominee
Attn: Storm Water Program
Dane
Door
Oconto
2984 Shawano Ave.
Dodge
Fond du Lac
Outagamie
Green Bay, WI 54313
Grant
Green Lake
Shawano
Phone: (920) 662-5100
Green
Kewaunee
Waupaca
Iowa
Manitowoc
Waushara
Marinette
Winnebago
Kenosha
Sheboygan
DNR Service Center
Milwaukee
Walworth
Attn: Storm Water Program
Ozaukee
Washington
141 NW Barstow Street,
Racine
Waukesha
Room 180
Waukesha, WI 53188
(262) 574-2100
DNR Service Center
Attn: Storm Water Program
5301 Rib Mountain Rd.
Wausau, WI 54401
Phone: (715) 359-4522
Jefferson
DNR South Central Region
LaFayette
Attn: Storm Water Program
Richland
3911 Fish Hatchery Rd.
Rock
Fitchburg, WI 53711
Sauk
Phone: (608) 275-3266
doom Em
No -w r Z'
Zr boom
� W
No MEME
Tr MEN
ME
a a . ■ a ■ ■ M ■ =I --m • ■ WO ■
r MENMEN
'
No ME
■ ■ ME
ATTACHMENT A
City of Oshkosh
NEWSC Outreach Activities 2016
NEWSC Outreach Activities 2016
Exhibiting:
2/13-14/16 Northeast Wisconsin Sport Fishin' Show in Oshkosh, (approx. 200 reached)
5/7/16 Bird Fest at Menominee Park & the Masonic Center in Oshkosh
Rain Barrel Workshops:
9/10/16 Oshkosh Rain Barrel Workshop at Leach Amphitheater in Oshkosh
Presentations:
4/23/16 STEM SCIENCE CAMP outreach at UW -Oshkosh Halsey Science Hall (various
grades/ages)
Watershed Cleanup:
4/30/16 Over 430 volunteers
Social Media:
Facebook over 417 likes
Meetings:
Monthly Winnebago Lakes Council meetings every 3rd Wednesday
Media
4/17 /16 through 4/30/16 Radio advertising on 91.1 The Avenue for the Watershed Cleanup (8x a day)
httj2s://cIyj2.it/itrj2mbc
4/21/16 Post Crescent for Watershed Cleanup A -Z Guide to Earth Day (Letter W)
http://www.postcrescent. com/story/news/2016/04/21/earth-day-2016-a-to-z-guide/83304418/
4/25/16 TV Spot on WBAY Channel 5 (5:45am and 9:15am)
4/25/16 Front page of the Post Crescent for Watershed Cleanup
http://www.postcrescent.com/story/news/2016/04/25/alliance-hold-fox-wolf-watershed-cleanup/83511012/
4/30/16 Two TV spots on Fox 11 morning -of cleanup (7:45 & 8:45), TV spot on WBAY Channel 5,
TV spot on NBC
ATTACHMENT B
City of Oshkosh
2016 MS4 Annual Report Supplemental Information
Section V. Permit Conditions
A. Minimum Control Measures:
1. Public Education and Outreach
a. Fox Wolf Watershed Alliance: The City of Oshkosh received an Impact Award from the
Fox Wolf Watershed Alliance for being a Watershed Hero. James Rabe, Director of Public
Works was on hand to receive the award as well as David Patek, former Director of Public
Works, Mark Rohloff, City Manager and Steve Cummings, Mayor. These gentlemen are
responsible for making of City's storm water program one of the best in the State of
Wisconsin. The conference was held in Oshkosh on March 1- 2, 2016.
b. Utility Bill Flyer: A utility bill flyer on storm water management and discharge of grass
to streets was included with the utility bills that went out at the end of April.
1 2016 Fox -Wolf Watershed Hero Award [
n
�4-
Ra
Fox - i;1`01 f
r
City of Oshkosh
Stormwater Utility
if%a�ors.FaAo�.ur
c. Storm Water Utility Brochure: The content of the general Storm Water Utility brochure
was updated for 2016 and was distributed to various locations throughout the City.
d. WAFSCM Award: For the second year in a row James Rabe and the City of Oshkosh
recognized for Excellence in Project, Design & Implementation.
Ar
Oshkosh
DATE: October 7, 3016
TCIc Honorable Mayor and C++mitten Council
FROM: :dark Rohloff, City Manager
SU'BJEC'T- WEEKLY IEWStEI IEK
The Wisconsin D"Ameni of TransFrrrtautm Ilx"i
anrfounwd a public involvement meefing to dixuc, pntc
Oregcw0ackson Stmt Bridge in the city of Oshkosh. The mmh
CMt*ier 13, 2016, frnrfn 5 to 6:30 pm,, at the Csshkosh Svnior,
Buildinr, Zit N. CampEull Road, Ushkosh A brief presentation
.,lw,n hoow to follow rhe purp:.e of this meeting; i, to ,how
attematnes that have tttn developed to date, and discuss th-
Frt*tct map,, evhubit..tivd di+ptays will he available for public
stall will he available hs explain I$n pcocntial improvements ant
i+encs+nraked til ath•nd thv mrVlinl; TO learn more altaht the stuely
05f11:O5II NOMINATED ECdR EXCELLENCE Public Works Din -cur Jame-. Rah• +va.
nofdrld that 0%hkc1sh had ttt•n rw+minatc.i h1r an award at tix- Wisconsin Assochation for
Floodplain. Stormwaler. and Coastal Management (WAF5061) Annual Confererhtr. The City of
Oshkcrslt Armory Area Stet R-tentiun Hawn pr(*-ct was selected to reeive the 2016 WAFSCM
Excellence in Project Design or Implementation Award. In 2015 the Sa%%,ver Creek Dredging
prapat neeelxed the Excellence in Project Design or Implementation Award. Pnyecis and
awards like this do rwif happen without a significant amount of effort. Tlnre were many people
that contributed to the %icer°., at this grujecf, and Air Raty asks that you :share hi, thank, for
making this a sfrcccssful, award worthy project_ Tice award will be presented on No%vmber loth
at fix- 2016 %VAFc" Annual Conference, If y0ij twvtr any gtt<+ikm% ploiw conlaet Public
Works Director, lames RaW-
e. Online Mapping: In 2016 the City rolled out a new interactive ESRI ArcGIS online
mapping application to display projects that have been completed by the Storm Water
Utility. Each project has multiple photographs illustrating the project at different phases
of construction and a brief text describing the project.
2. Public Involvement and Participation
a. Storm Water Utility Website: The Storm Water Utility developed a new page layout in
2016 on the City's Website. The new look strived to be more consumer friendly and
contained added additional content that citizens needed to sign up for storm water utility
credits and the City's mini -storm program. The Storm Water Utility Engineering
Supervisor works with the Information Technology Division staff to ensure that items
pertaining to the Storm Water Utility that may be of interest to the general public are
posted. The url for the Storm Water Utility webpage is:
http://www.ci.oshkosh.wi.us/Public Works/Storm Water Utility[
b. Storm Water Utility Committee: In 2016, the Storm Water Utility Committee held public
meetings on: January 14, February 18, March 24, April 21, , June 2, August 18, September
15, October 20, November 17 and December 15. All Storm Water Utility Committee
meetings are open to the general public, and are publicly noticed in accordance with state
statutes. A link to the Storm Water Utility Committee agendas and minutes can be found
on the City's Storm Water Utility webpage.
c. Annual Report Outreach: The 2015 MS4 Annual Report was discussed at the February 18
March 24 and the April 21 Storm Water Utility Committee Meetings. The report was also
posted to the Storm Water Utility webpage. The Common Council reviewed and voted to
approve the report at their April 26thmeeting.
d. UWO-Public Policy: City staff worked four students from the University of Wisconsin -
Oshkosh public policy class to develop policies for the City of Oshkosh that would
promote greater use of green infrastructure practices in the management of storm water.
The students, Shantel Brundidge, Gregory Gauthier, Kelly Hamilton and Lindsay
McClintock presented their proposed policy to the Oshkosh City Council, and staff, May
25, 2016.
e. Build Your Own Rain Barrel: On Saturday, September 10, 2016, Silver Star Brands, City
of Oshkosh, and 4imprint sponsored an event to educate the community on ways to Live
Green in every aspect of their lives. The event took place at the Leach Amphitheater in
Oshkosh. There were activities for children, food for purchase, live music and
educational booths from vendors to provide information on energy conservation,
resource preservation, recycling, adopting pets, and green transportation.
f. Ground Control Workshops: The City of Oshkosh conducted Ground Control
Workshops that were attended by contractors of 30 municipal projects during 2016. All
contractors and their subcontractors are required to attend, so some contractors have
attended our workshops more than once over the years. At each workshop, City staff
reviewed the erosion control requirements that would be enforced during construction.
Staff stressed the importance of maintain proper erosion control practices at all times and
In paltnership with
Silver Star
B R A N D S ArOshkosh
Presents
LIVE
GrePn
Please join us for the Live Green Event!
Visit with local businesses and organizations to learn
more about how to live a more sustainable lifestyle.
Saturday, September 10th
12:00-4:00 p.m.
Leach Amphitheater, Oshkosh WI
OPEN TO THE PUBLIC • FREE ADMISSION
Rain or shine - under tents
Live music by The Royal Blue Band
Also sponsored by
4lmprint • �—
Vendors:
Habitat for Hiunallity ReStore
Studio 3
Sadoff Metal Recycling
LIW-Exteilsioll
Growing Oshkosh
Titan Gold Composting
Oshkosh Sustainability Advisory Board
Shorelalld Preservation
Oshkosh Food Co -Op
Oshkosh Area Humane Society
Norwex
Fox Wolf Watershed Alliance
Wild Ones
Audubon
Master Gardeners
And more!
KIDS ACTIVITIES:
Face painting ($i)
Make and take a
light switch cover
and more!
50/50 RAFFLE • REUSABLE TUMBLERS TO THE FIRST 500 GUESTS
Food available for purchase
4�� &llf GROWING
OSH (COSH
Fundraiser/scrap materials drive:
Bring in acceptable materials to Sadoff Metal
Recycling located at 36 E 10th Avenue in Oshkosh
now through Saturday, September 17th.
Mention that you would like to donate funds to
Growing Oshkosh. A check will be presented to them
with any proceeds.
Fox - WOLF
AM WATFR SHM A i I I A NC'F
Make a rain barrel:
Register online to make a rain barrel at the event
with the Fox Wolf Watershed Alliance. Cost is $35.
City of Oshkosh residents can then apply for a
credit on their water bill. More details on how to
apply will be available at the event.
the penalties if the Contractors are found to be in non compliance. A total of 21
individuals participated in the four workshops.
3. Illicit Discharge Detection and Elimination
a. Outfall Program: During the fall of 2016, OMNNI Associates, Inc. (OMNNI) assisted the
City of Oshkosh with inspecting the outfalls in the City's municipal separate storm sewer
system (MS4) for potential illicit discharges. The 2015 revision to the City's Ongoing
Screening Program implemented the "priority outfall" concept that was introduced by the
WDNR in a March 2012 guidance document. Results of the inspections are summarized
in the City of Oshkosh Ongoing Screening Summary Report- 2016 Inspection Year
(January 8, 2016). The current MS4 map of the City of Oshkosh consists of 425 outfalls
including:
4. 95 major outfalls
5. 237 minor outfalls
6. 93 supplemental outfalls
OMNNI inspected 98 outfalls (and an additional 85 upstream manholes) of the
approximately 425 MS4 outfalls identified in the City. All 46 priority outfalls were
inspected along with a sampling of the non-priority major outfalls and the non-priority
non -major outfalls. The inspections consisted of a visual screening along with a chemical
analysis of any dry -weather flow that was present. The inspections revealed 71 outfalls
were unlikely as having a potential of past illicit discharges, 27 outfalls with evidence of
having a potential of an illicit discharge and none with any obvious illicit discharge.
Of the manholes inspected 26contained significant amounts of floating debris (plastic
bottles, foam packaging, paper and other solid wastes) that were classified as potential
illicit discharges. City crews removed the debris and the manholes and the City will
continue to monitor the manholes for debris. All 41 storm sewers are submerged by the
water levels in Lake Winnebago. It is most likely that floatables that are washed off the
street and into the storm sewer may be becoming trapped in these manholes where lake
levels are above the top of the pipe.
Two outfalls were classified as potential for something other than gross solids. The
manhole between East 9thAvenue and Pioneer Drive (03-81) contained an oil sheen and
elevated ammonia, which had be observed at this outfall in 2009, 2010 and 2014.
Investigation have concluded that this is caused by the build up over many years of diesel
fuel and not the result of a single spill or leak from a storage tank. Elevated pH was again
observed in storm sewer discharging to the Nolte Avenue detention basin. The City of
Oshkosh plugged a storm lateral in 2015 that was believed to be the source of the elevated
pH. The lateral appeared to be a lateral from a concrete plant. The pH is anticipated to
decline with time but will continue to be monitored.
Based on the information collected during the screening, the proposed ongoing screening
program will undergo revisions based on Wisconsin Department of Natural Resources
(WDNR) 2012 guidance documents. The updated plan will then be submitted to the
Wisconsin Department of Natural Resources (WDNR) and used in future screening
programs. Future screening programs will be based on the sampling of approximately
100 outfalls annually based on an overall classification of sampling priorities:
48 priority outfalls
80 non-priority major outfalls
297 non-priority non -major outfalls
b. City Enforcement: In April a utility bill flyer went out informing residents of the adverse
impacts (clogging of the collection system and nutrient loading to area water bodies) of
grass clippings accidentally and intentional being left on City streets. During 2016 the
City issues 44 warnings that continued practice of discharging grass clippings into the
roadway could potentially result in a fine.
c. Recorded Incidents: City staff responded to five (5) single incidents of reported illicit
discharges in the City of Oshkosh. In each case City staff took action to prevent the
incident from reoccurring and reported it to authorities when it was called for. The
incidents were reported to the Storm Water Utility Committee September 15, 2016
(Attachment C).
i. Anchorage Channel Illegal Dumping: During routine inspection of City
storm facilities staff discovered construction debris dumped on the bank of the
City's Harrison Ditch. The investigation led to the identification of the
violator, a contractor working for WPS. City staff worked with WPS and had
the contractor remove the material and restore the vegetated bank.
ii. UWO Biogas System: In August, the University of Wisconsin - Oshkosh
Biogas Facility experienced a failure of one of its pumps with resulted in 6,500
to 7,000 gallons of percolate to flow down its driveway and into the City's
storm sewer system. The City became aware of the spill several days later and
reported the incident to the appropriate authorities at DNR. The University
stated that they had cleaned up the spill and that no percolate had entered the
City's storm sewer. City crews were dispatched to the spill site to thoroughly
clean the remaining material on the street and in the storm catchbasins.
iii. Sawdust Days Grounds: City crews monitoring the cleanup of Menominee
Park after Sawdust Days found City storm inlet had not only been used as
trash receptacles but also a place for vendor to dump grease from their fryers.
City crews used vacuum truck to remove the debris and more stringent
controls and penalties will be placed on the event organizers for 2017.
iv. Taco Bell: City inspectors happen to pass Taco Bell when a worker happened
to be seen dumping dirty wash water from their mop bucket into a storm inlet.
The restaurant was immediately notified and a letter was sent putting the
restaurant on notice that further violations could result in a financial forfeiture.
v. Hydraulic Oil Spill: A neighbor dropped off a video at City Hall showing a
truck that they claimed had experienced a break in one of its hydraulic lines.
An unknown quantity of hydraulic fluid was spilled on the street. The
incident was immediately reported to the fire department, as required.
Further investigation revealed that the incident had occurred many days prior
to it being reported. Regardless, City crews spread oil dry on the area
impacted and later swept up the material. There was no evidence that the
hydraulic fluid had made it to the storm sewer system.
4. Construction Site Pollutant Control
a. Municipal Construction Inspection: The City inspects all municipal construction projects
on a weekly basis, and after rainfall events in excess of one half inch in twenty four hours.
The Contractor is issued orders to repair any deficiencies in the implementation of the
Erosion and Sediment Control Plan within 24 hours. The City utilizes a mapping grade
handheld GPS unit to locate any deficiencies in the erosion and sediment control
practices, and provide the contractor a map of the locations needing repair. The City also
inspects all municipal construction projects that remain "open' over winter to ensure that
practices are in place and functional as the ground begins to thaw.
b. Commercial Construction Inspection: The City inspected 105 Commercial / Industrial
developments for compliance with their Erosion and Sediment Control Plans on average 1
to 2 times throughout the construction season. Any deficiencies noted in the
implementation of the Erosion and Sediment Control Plan was noted in a letter emailed to
each construction manager. Additionally, the City responds to numerous citizen
complaints due to erosion and sediment control. These complaints are notably after storm
events when tracking from construction sites frequently occurs. As with "random"
inspections, a summary inspection letter is sent to the construction manager for the site.
c. Erosion Control Enforcement: City staff performed a total of 312 construction site erosion
and sediment control inspections for all city construction projects in 2016. A total of 19
Notice of None Compliance letters were issued during the 2016 construction season. City
inspectors were usually able to work with contractor to resolve deficiencies before they
left the construction site.
5. Post -Construction Storm Water Management
a. Staff completed 172 private site development plan reviews through the course of 2016,
spending approximately 381 hours on those plan reviews.
6. Pollution Prevention
a. Catchbasin and Storm Sewer Cleaning: Approximately 1,071 person -hours were spent
cleaning and removing sediment from catch basins during 2016. A total of 129,426 feet of
storm sewers were cleaned and 193,847 feet of storm sewers were televised in 2016.
b. Street Sweeping: Approximately 17,148 curb miles of street sweeping occurred in 2016.
There are approximately 280 miles of street in the City of Oshkosh. Each mile of street
equals 2 curb miles (1 on each side of the street). The approximately 17,148 curb miles of
street sweeping equates to sweeping each street approximately 30 times throughout the
year. Street sweeping starts in April and May and continues into November in an average
year. Because of the unseasonably warm weather some street sweeping activities
continued into December. A total of 956 tons of debris from the street sweeping program
was hauled to landfill in 2016.
c. New Wet Basin: The construction of the Fernau Watershed North Main Street Area
Stormwater Detention Basin was substantially completed November 2016. Final
landscaping and the planting of the literal shelf will occur in the spring of 2017. That
facility will remove approximately 24 ton of TSS that previously would have been
discharged to Lake Winnebago.
d. New Wet Basin: Planting of the vegetation at the 9� & Washburn Area Wet Detention
Basin was completed during the spring of 2016. The vegetation is critical to the basins
stability and its pollutant removal capability.
e. New Wet Basins: Four (4) wet basins were constructed by the City but not funded by the
Storm Water Utility. Three were construction in the City's new SW Industrial Park and
the forth was constructed for a new aviation business park that was jointly constructed by
the City of Oshkosh and Winnebago County.
f. Watershed Planning: Work continued on the Storm Water Management Plans for Fernau
Avenue, Stringham, Gallups/Merritts and Stevens Watersheds. The plans have identified
management strategies for resolving the flooding and storm water quality issues of the
watershed that have resulted in the planning and/or design of two (2) storm basins in the
Fernau Watershed and one (1) in the Stringham Watershed.
g. Design of New Facilities: The design was completed on the Lagoon in the City's South
Park. Construction is planned to begin in the early summer of 2017 and should be
completed the spring of 2018. Plans and specification were also prepared for the Libbey /
Nicolet Area Stormwater Management Basin, which is scheduled to be constructed in
2018.
7. Winter Road management Activities:
a. Road Salt application vehicles are calibrated per the manufacturer's recommendations.
The Streets Division Supervisors have pavement temperature sensors equipped in their
trucks, to monitor the temperature of the pavement to ensure that salt is not being applied
when it will not be beneficial.
8. Municipal Facilities:
Inventory of Municipal Storm Water Facilities
(source: 2016 facility inventory map)
Number
City Facility
Location
1
9th & Washburn Basin
Behind 1015 S Washburn St
2
Armory Wet Basin
1415 Armory PI
3
Baldwin Basin
Intersection of E. New York Ave and Broad St
4
Fair Acres
Across the street from 121 W Murdock Ave
5
James Rd Basin
At the intersection of W Waukau Avenue and
James Road
6
Melvin Ave Storm Lift Station
In Menominee Park at the end of Siewert Trail
7
E Nevada Ave Storm Lift Station
In Menominee Park at the end of E Nevada Ave
8
North High Pond
1100 W Smith Ave
9
NW Industrial Park Basin
Just east of 3110 Progress Dr
10
S Oakwood Basin
Near the intersection of S Oakwood Rd and
Badger Ave
11
SW Industrial Park Basin -Middle
North of the intersection of Global Pkwy and
Atlas Ave
12
SW Industrial Park Basin -West
East of the end of Global Pkwy
13
SW Industrial Park Basin -East
North of 2900 Atlas Ave
14
Tipler Pond
325 S Eagle St
15
Westhaven Basin
Across the street from 1530 Westhaven Circle
16
City Hall Detention Vault
Beneath the main north parking lot at City Hall
17
South Park Ponds
NW corner of W South Park Ave and Ohio St
18
SW Industrial Park Basin -A
Global Parkway - SW
19
SW Industrial Park Basin -B
Global Parkway - NE
20
SW Industrial Park Basin -C
Global Parkway - NW
21
Aviation Industrial Park Basin
SE corner of W Ripple Ave and Aeroinnovate
Way
22
Fernau Watershed Area Basin
Across the street from 3300 N Main St
23
Sr Center Bioswale/Permeable
Pavement
200 N Campbell Rd
9. Best Management Practices:
a. Housekeeping: City crews annually clean and remove sediment from all of the catch
basins. For the first six weeks after spring snow melt all streets are swept weekly. Then
during the remaining cleaning season, the City performs street cleaning of the majority of
City Streets every other week spring through fall. The downtown streets are cleaned at a
weekly frequency. The City uses four (4) vacuum assisted, high efficiency, street cleaners
and one (1) mechanical broom sweeper. Approximately 17,148 curb miles of streets were
swept in 2016, removing approximately 956 tons of debris from the streets.
b. Annual Inspection: Engineering Division Staff inspects each of the City's 17 storm water
BMP annually. By the end of 2016 the number of facilities increased to 23. These
inspections focus on potential structural damage to the facility due to erosion, rodents,
vandalism, or other causes. Any deficiencies noted are repaired as quickly as possible. In
the case of rodent damage, the site is then evaluated for potential actions to reduce the
rodent population.
c. Routine Inspection: The City of Oshkosh Streets Division inspects the major storm water
BMP's after each major rain event. These inspections look for any evidence of damage,
plugging or other concerns. Any deficiencies noted are repaired as quickly as possible.
d. Maintenance of Lift Stations: The City Waste Water Treatment Plant Staff maintain all
pump stations in the City of Oshkosh (waste water and storm water). The City has two
large storm water pump stations. The Melvin Avenue Storm Water Pump Station is
located on Siewert Trail in Menominee Park and the Lake View Pump Station, which is
located in Menominee Park at the end of E. Nevada Drive. The stations are monitored 24
hours a day, 7 days a week, 365 days a year via radio telemetry by operations staff at the
Waste Water Treatment Plant. The stations are visually inspected on a weekly basis by a
Maintenance Mechanic. The backup power generator is tested 3 to 4 times per year. The
backup power generator was serviced by the supplier's maintenance staff.
e. Nuisance Animal Control: The City of Oshkosh contracted with Bezio Animal Control
(Pulaski, WI) to conduct nuisance animal inspections and trapping at all wet detention
basins owned and operated by the Storm Water Utility. The management of nuisance
animals (muskrats for example) is vital to ensure the long term stability of the natural
vegetation in the City's many detention basins. In addition to the wet detention basins,
Bezio Animal Control performed monthly inspections of the berm at the James Road Area
Detention Basin. If the inspections showed evidence of burrowing animals, trapping
activities were initiated to remove the burrowing animals and reduce/eliminate the
potential damage threat to the berm.
ATTACHMENT C
City of Oshkosh
2016 Reported Illicit Discharge to City of Oshkosh MS4
Storm Water Utility
Illicit Discharges - 2016 y
Biogas System Spill 8-14-2016
Percolate
P H: 910
NH, soo l,soomg/L B
High —n.
Wastewater
PH 68
NH,: 12-45 mg/L
-'- High B—n,
NHS
Chronic Toxicity
J -0.02 mg/L NH,
Acute Toxicity
-o.lmg/L
Aoorox Load
1001b NH,
3/27/2017
Anchorage Channel Illegal Dumping
May 2016 at Fox Valley Heat Treat by K&S Electrical
z�
Biogas System
OSHKOSHBiogas
plant has a 370kW CHP unit designed to run 24/7.
Supplies approximately 8 percent of the University's electricity
sasn�e, ss��_�omce�.sa�
'. r msm�iai. a�as nose
.r."rt rave Fresh Waste
i
Digested Waste
- Sold as a Soil
9n9 �a7 mntlense6e perms
Manx Amendment
-1.
Percolate
8-14-2016 Spill Recirculation
Pump
Sawdust Days Grounds 7-5-2016
1
Taco Bell
1800 Jackson Street Dumping Wash Water into Storm Sewer
Hydraulic Oil Spill
Dump Truck Lost its Axle on Jackson Street
3/27/2017
Hydraulic Oil Spill
February 3, 2016 on Bay Street (approx. 5 gallons) by Reckers Towing
ATTACHMENT D
City of Oshkosh
2016 City of Oshkosh Projects Construction Erosion Control Site Inspections
City of Oshkosh, WI
Best Management Practice Report
2016 (January 01, 2016 To December 31, 2016)
4 Construction Site Pollutant Control
Responsible Staff / Position: James Rabe
Director of Public Works
(920) 236-5065
4.2 Construction Site ESC Inspection and Enforcement Procedures
Responsible Staff / Position
Required: Yes
John Ferris
Civil Engineering Supervisor
(920) 236-5065
Description
Adopt and maintain procedures for construction site inspection and enforcement of erosion and sediment control
measures. At a minimum, the procedures shall establish:
1. Municipal departments or staff responsible for construction site inspections and enforcement.
2. Construction site inspection frequency.
3. Construction site inspection documentation.
4. Enforcement mechanisms that will be used to obtain compliance.
Goals
4.2.1 ESC Inspection and Enforcement Procedures
Responsible Staff / Position Kris Lyons
Engineer Tech
(920) 236-5065
Description
Develop and maintain procedures for construction site erosion and sediment control inspection and
enforcement procedures as described. Review the procedures annually and update as needed to maintain
effectiveness and permit compliance.
Provide a copy of or reference to the current procedures each reporting period.
Planned: 2015 2016 2017 2018 2019 2020 2021
Complete:
Activity Date Name Description
04/14/2016 2270 Bowen St. Sediment Discharge Sediment left within ROW and not cleaned up at the
DR Hanson end of the working day. Had a phone conversation
with DR Hanson on 4-14-2016 regarding the
Page 1 of 20
4.2.2 Responsible Person - Construction Site Pollutant Control
Responsible Staff / Position Kris Lyons
Engineer Tech
(920) 236-5065
Description
Identify the municipal department or staff responsible for construction site inspection and enforcement
through the current reporting period.
Planned:
2015 2016 2017 2018 2019 2020 2021
Complete:
Activity Date
Name
Description
None
4.2.3 City Construction
Site ESC Inspection and Enforcement
Procedures
Responsible Staff / Position Kris Lyons
Engineer Tech
(920) 236-5065
Description
City Permitted
WDNR Sites ESC Inspections and Enforcement
Planned:
2015 2016 2017 2018 2019 2020 2021
Complete:
Activity Date
Name
Description
03/17/2016
16-03 Weekly 20160317
Weekly Inspection Report
03/23/2016
16-03 Weekly 20160323
Weekly Inspection Report
03/23/2016
16-04 Weekly 20160323
Weekly Inspection Report
03/30/2016
16-04 Weekly 20160330
Weekly Inspection Report
03/30/2016
16-03 Weekly 20160330
Weekly Inspection Report
04/01/2016
16-03 Rain Event 20160401
Rain Event Inspection Report
04/01/2016
16-04 Rain Event 20160401
Rain Event Inspection
04/07/2016
16-05 Weekly 20160407
Weekly Inspection Report
04/07/2016
16-04 Weekly 20160407
Weekly inspection report
04/07/2016
16-03 Weekly 20160407
Weekly Inspection Report
04/14/2016
16-03 Weekly 20160414
Weekly Inspection Report
Page 10 of 20
04/14/2016
16-04
Weekly 20160414
Weekly Inspection Report
04/14/2016
16-05
Weekly 20160414
Weekly Inspection Report
04/20/2016
16-05
Weekly 20160420
Weekly Inspection Report
04/21/2016
16-04
Weekly 20160421
Weekly Inspection Report
04/21/2016
16-03
Weekly 20160421
Weekly Inspection Report
04/27/2016
16-05
Weekly 20160427
Weekly Inspection Report
04/27/2016
16-03
Weekly 20160427
Weekly inspection report
04/28/2016
16-04
Weekly 20160428
Weekly Inspection Report
05/04/2016
16-05
Weekly 20160504
Weekly Inspection Report
05/05/2016
14-10
Weekly 20160505
Site inspection now that the contractor is back on
site doing warranty work.
05/11/2016
14-10
Weekly 20160511
Weekly Inspection
05/18/2016
14-10
Weekly 20160518
Weekly EC Inspection
05/18/2016
16-04
Weekly 20160518
Weekly EC Inspection
05/18/2016
16-05
Weekly 20160518
Weekly EC Inspection
05/18/2016
16-03
Weekly 20160518
Weekly EC
05/18/2016
16-16
Weekly 20160518
Weekly EC
05/25/2016
14-10
Weekly 20160525
Weekly & Final EC Inspection
05/25/2016
16-16
Weekly 20160525
Weekly EC Inspection
05/25/2016
16-05
Weekly 20160525
Weekly EC Inspection
05/25/2016
16-03
Weekly 20160525
Weekly EC Inspection
05/26/2016
16-04
Weekly 20160526
Weekly EC Inspection
05/31/2016
16-16
Rain Event 20160531
Rain Event Inspection
05/31/2016
16-04
Rain Event 20160531
Rain Event Inspection
05/31/2016
16-03
Rain Event 20160531
Rain Event Inspection
Page 11 of 20
05/31/2016
16-05
Rain
Event 20160531
Rain Event Inspection
06/01/2016
16-05
Rain
Event 20160601
Rain Event Inspection
06/01/2016
16-03
Rain
Event 20160601
Rain Event Inspection
06/01/2016
16-04
Rain
Event 20160601
Rain Event Inspection
06/01/2016
16-16
Rain
Event 20160601
Rain Event Inspection
06/06/2016
16-06
Rain
Event 20160606
Rain Event Inspection
06/06/2016
16-03
Rain
Event 20160606
Rain Event Inspection
06/06/2016
16-16
Rain
Event 20160606
Rain Event Inspection
06/06/2016
16-05
Rain
Event 20160606
Rain Event Inspection
06/06/2016
16-04
Rain
Event 20160606
Rain Event Inspection
06/09/2016
16-04
Weekly 20160609
Weekly EC Issue
Turbidity barrier needs to be fixed. Contractor is
aware.
Everything else was corrected while on site.
06/09/2016
16-05
Weekly 20160609
Weekly Inspection Report
06/09/2016
16-16
Weekly 20160609
Weekly EC Inspection
Needs to fix stone bags by boat launch. Contractor
is aware.
06/09/2016
16-03
Weekly 21060609
Weekly EC Inspection
06/09/2016
16-06
Weekly 20160609
Weekly Inspection
06/15/2016
16-01
Rain
Event 20160615
Rain Event Inspection
06/15/2016
16-06
Rain
Event 20160615
Rain Event Inspection
Pass
06/15/2016
16-03
Rain
Event 20160615
Rain Event
Pass
06/15/2016
16-16
Rain
Event 20160615
Rain Event
Pass
06/15/2016
16-05
Rain
Event 20160615
Rain Event
Missing inlet protection
06/15/2016
16-04
Rain
Event 20160615
Rain Event
Turbidity Barrier still isn't fixed completely. Has a
little gap at the seam that needs to be sealed
Page 12 of 20
Page 13 of 20
properly
06/23/2016
16-01 Weekly 20160623
Weekly EC Inspection
06/23/2016
16-03 Weekly 20160623
Weekly EC
06/23/2016
16-04 Weekly 20160623
Weekly EC
06/23/2016
16-16 Weekly 20160623
Weekly EC
06/23/2016
16-05 Weekly 21060623
Weekly EC
06/23/2016
16-06 Weekly 20160623
Weekly EC
06/27/2016
16-06 Rain Event 20160627
Rain Event
06/27/2016
16-05 Rain Event 20160627
Rain Event
06/27/2016
16-16 Rain Event 20160627
Rain Event
06/27/2016
16-04 Rain Event 20160627
Rain Event
06/27/2016
16-03 Rain Event 20160627
Rain Event
06/27/2016
16-01 Rain Event 20160627
Rain Event
06/30/2016
16-01 Weekly 20160630
Weekly EC
06/30/2016
16-03 Weekly 20160630
Weekly EC
06/30/2016
16-04 Weekly 20160630
Weekly EC
06/30/2016
16-05 Weekly 20160630
Weekly EC
06/30/2016
16-06 Weekly 20160630
Weekly EC
06/30/2016
16-16 Weekly 20160630
Weekly EC
07/07/2016
16-01 Weekly 20160707
Weekly EC
07/07/2016
16-03 Weekly 20160707
Weekly EC
07/07/2016
16-04 Weekly 20160707
Weekly EC
07/07/2016
16-05 Weekly 20160707
Weekly EC
07/07/2016
16-06 Weekly 20160707
Weekly EC
Page 13 of 20
07/07/2016
16-16 Weekly 20160707
Weekly EC
07/13/2016
16-01 Weekly 20160713
Weekly Inspection
07/13/2016
16-03 Weekly 20160713
Weekly Inspection
07/13/2016
16-06 Weekly 20160713
Weekly Inspection
07/13/2016
16-16 Weekly 20160713
Weekly Inspection
07/13/2016
16-05 Weekly 20160713
Weekly Inspection
07/13/2016
16-04 Weekly 20160713
Weekly Inspection
07/25/2016
16-01 Rain Event 20160725
Rain Event from the weekend
07/25/2016
16-03 Rain Event 20160725
Rain Event from the weekend
07/25/2016
16-04 Rain Event 20160725
Rain Event from the weekend
07/25/2016
16-05 Rain Event 20160725
Rain Event from the weekend
07/25/2016
16-06 Rain Event 20160725
Rain Event from the weekend
07/25/2016
16-16 Rain Event 20160725
Rain Event from the weekend
07/28/2016
16-01 Weekly 20160728
Weekly EC
07/28/2016
16-03 Weekly 20160728
Weekly EC
07/28/2016
16-04 Weekly 20160728
Weekly EC
07/28/2016
16-05 Weekly 20160728
Weekly EC
07/28/2016
16-06 Weekly 20160728
Weekly EC
07/28/2016
16-16 Weekly 20160728
Weekly EC
07/28/2016
16-20 Weekly 20160728
Arrived on site. No dewatering bag was being used
and no inlet protection was installed.
The contractor was shut down when I saw this. They
were not permitted to start work until inlet protection
was installed and the pump removed.
The contractor was talked to about their lack of
action to do it right. They said it was a mistake and
wouldn't do it again. The owner of the company was
called about the issue and told that they need to take
corrective measures to make sure this doesn't
happen again.
Page 14 of 20
08/04/2016
16-01 Weekly 20160804
Weekly EC
08/04/2016
16-03 Weekly 20160804
Weekly EC
08/04/2016
16-04 Weekly 20160804
Weekly EC
08/04/2016
16-05 Weekly 20160804
Weekly EC
08/04/2016
16-06 Weekly 20160804
Weekly EC
08/04/2016
16-16 Weekly 20160804
Weekly EC
08/04/2016
16-20 Weekly 20160804
Site looked good. They are working on S. Meadow
St. All BMP's where in place at time of inspection
(inlet protection).
08/11/2016
16-01 Weekly 20160811
Weekly EC
08/11/2016
16-03 Weekly 20160811
Weekly EC
08/11/2016
16-04 Weekly 20160811
Weekly EC
08/11/2016
16-05 Weekly 20160811
Weekly EC
08/11/2016
16-06 Weekly 20160811
Weekly EC
08/11/2016
16-09 Weekly 20160811
The site looked okay. I, Kris, requested that the
contractor sweep where the saw cutting took place.
Jason, from Bower Construction, said that he would
take care of it. Inlet protection was installed in
working area. K&S also had inlet protection installed
where they were working.
08/11/2016
16-16 Weekly 20160811
Weekly EC
08/11/2016
16-20 Weekly 20160811
Contractor was working on Washington prepping for
pavement. Site was secure. Multiple locations
within the city have also been paved. The contractor
still needs to do final turf restoration in multiple
areas.
08/17/2016
16-01 Weekly 20160817
Weekly EC
08/17/2016
16-03 Weekly 20160817
Weekly EC
08/17/2016
16-04 Weekly 20160817
Weekly EC
08/17/2016
16-05 Weekly 20160817
Weekly EC
08/17/2016
16-06 Weekly 20160817
Weekly EC
Page 15 of 20
08/17/2016
16-09 Weekly 20160817
Weekly EC check.
Site looked good. Contractor was going to clean the
FL before the weekend and sweep the road.
08/17/2016
16-16 Weekly 20160817
Weekly EC
08/22/2016
16-16 Rain Event 20160822
Rain Event from Weekend
08/22/2016
16-09 Rain Event 20160822
Contractor had cleaned the FL and swept the road.
Contractor was also restoring terrace are that was
disturbed during water service connections.
Contractor is also prepping the road surface for
paving later this week to complete the work in phase
1.
08/22/2016
16-06 Rain Event 20160822
Rain Event from Weekend
08/22/2016
16-05 Rain Event 20160822
Rain Event from Weekend
08/22/2016
16-04 Rain Event 20160822
Rain Event from weekend
08/22/2016
16-03 Rain Event 20160822
Rain Event from weekend
08/22/2016
16-01 Rain Event 20160822
Rain Event from the weekend
08/25/2016
16-01 Weekly 20160825
Weekly EC
08/25/2016
16-03 Weekly 20160825
Weekly EC
08/25/2016
16-04 Weekly 20160825
Weekly EC
08/25/2016
16-05 Weekly EC 20160825
Weekly EC
08/25/2016
16-06 Weekly 20160825
Weekly EC
08/25/2016
16-09 Weekly 20160825
Site was okay. Contractor informed the inspector
before they started the inspection that there were
aware of missing IP and missing 2x4's in installed IP.
They said that they would get them installed asap.
The rest of the site was good condition.
08/25/2016
16-16 Weekly 20160825
Weekly EC
08/29/2016
16-01 Rain Event 20160829
Rain Event
08/29/2016
16-03 Rain Event 20160829
Rain Event
08/29/2016
16-04 Rain Event 20160829
Rain Event
08/29/2016
16-05 Rain Event 20160829
Rain Event
Page 16 of 20
08/29/2016
16-06 Rain Event 20160829
Rain Event
08/29/2016
16-09 Rain Event 20160829
Rain Event
Jason was still missing a few 2x4's. He had lumber
to cut to install but didn't he said. He was also
getting 1 extra IP installed that he missed. He was
informed to clean up the road at the end of the day.
08/29/2016
16-16 Rain Event 20160829
Rain Event
09/01/2016
16-01 Weekly 20160901
Weekly EC
09/01/2016
16-03 Weekly 20160901
Weekly EC
09/01/2016
16-04 Weekly 20160901
Weekly EC
09/01/2016
16-05 Weekly 20160901
Weekly EC
09/01/2016
16-06 Weekly 20160901
Weekly EC
09/01/2016
16-09 Weekly 20160901
Weekly EC
09/01/2016
16-16 Weekly 20160901
Weekly EC
09/08/2016
16-01 Weekly 20160908
Weekly / Rain Event
09/08/2016
16-03 Weekly 20160908
Weekly / Rain Event
09/08/2016
16-06 Weekly 20160908
Weekly / Rain Event
Final inspection for rehab area
09/08/2016
16-16 Weekly 20160908
Weekly / Rain Event
Final inspection. grass is growing
09/08/2016
16-04 Weekly 20160908
Weekly / Rain Event
09/08/2016
16-05 Weekly 20160908
Weekly / Rain Event
09/15/2016
16-05 Weekly 20160915
Weekly EC
09/15/2016
16-04 Weekly 20160915
Weekly
09/15/2016
16-03 Weekly 20160915
Weekly EC
09/15/2016
16-01 Weekly 20160915
Weekly EC
09/21/2016
16-01 Rain Event 20160921
Rain Event
09/21/2016
16-03 Rain Event 20160921
Rain Event
Page 17 of 20
09/21/2016
16-04 Rain Event 20160921
Rain Event
09/21/2016
16-05 Rain Event 20160921
Rain Event
09/21/2016
16-09 Rain Event 20160921
Rain Event
09/23/2016
16-01 Rain Event 20160923
Rain Event
09/23/2016
16-03 Rain Event 20160923
Rain Event
09/23/2016
16-04 Rain Event 20160923
Rain Event
09/23/2016
16-05 Rain Event 20160923
Rain Event
09/23/2016
16-09 Rain Event 20160923
Rain Event
09/29/2016
16-04 Weekly 20160929
Weekly EC
09/29/2016
16-03 Weekly 20160929
Weekly EC
09/29/2016
16-05 Weekly 20160929
Weekly EC
09/29/2016
16-01 Weekly 20160929
Weekly EC
09/29/2016
16-09 Weekly 20160929
Site needs some minor clean up at the 5th & Sawyer
intersection. Bill Bowers was contacted regarding
the clean up.
10/06/2016
16-01 Weekly 20161006
Weekly EC. Lots of issues that needed to be
addressed by end of day on Friday.
10/06/2016
16-03 Weekly 20161006
Weekly EC
10/06/2016
16-04 Weekly 20161006
Weekly EC
10/06/2016
16-05 Weekly 20161006
Weekly EC. Some tracking issues that needed to
addressed
10/06/2016
16-09 Weekly 20161006
Weekly EC. The site is prepped for asphalt paving.
Just needs a little clean up in the flowlines.
Contacted Jason from Bowers regarding this and he
said that he will have it addressed.
10/13/2016
16-01 Weekly 20161013
Weekly EC
10/13/2016
16-03 Weekly 20161013
Weekly EC
10/13/2016
16-04 Weekly 20161013
Weekly EC
10/13/2016
16-05 Weekly 20161013
Weekly EC
Page 18 of 20
10/13/2016
16-09 Weekly 20161013
Weekly EC inspection. The contractor (NEA) was on
site today paving the road. The restoration behind
the curb is growing so after today all BMP's can be
removed from the project area.
10/20/2016
16-01 Weekly 20161020
Weekly EC
10/20/2016
16-03 Weekly 20161020
Weekly EC
10/20/2016
16-04 Weekly 20161020
Weekly EC
10/20/2016
16-05 Weekly 20161030
Weekly EC
11/03/2016
16-01 Weekly 20161103
Weekly EC
11/03/2016
16-03 Weekly 20161103
Weekly EC
11/03/2016
16-05 Weekly 20161103
Weekly EC
11/03/2016
16-04 Weekly 20161103
Weekly EC
11/10/2016
16-04 Weekly 20161110
Weekly EC
11/10/2016
16-05 Weekly 20161110
Final EC Inspection
11/10/2016
16-03 Weekly 20161110
Weekly EC
11/10/2016
16-01 Weekly 20161110
Weekly EC
11/17/2016
16-01 Weekly 20161117
Weekly EC
11/17/2016
16-03 Weekly 20161117
Weekly EC
11/17/2016
16-04 Weekly 20161117
Weekly EC
11/23/2016
16-04 Weekly 20161123
Weekly EC
11/23/2016
16-03 Weekly 20161123
Weekly EC
11/23/2016
16-01 Weekly 20161123
Weekly EC
11/28/2016
16-01 Rain Event 20161128
Rain Event
11/28/2016
16-03 Rain Event 20161128
Rain Event
11/28/2016
16-04 Rain Event 20161128
Rain Event
12/07/2016
16-01 Weekly 20161207
Weekly EC
Page 19 of 20
12/07/2016 16-03 Weekly 20161207 Weekly EC
12/07/2016 16-04 Weekly 20161207
Weekly EC
12/14/2016 16-03 Weekly 20161214
Weekly EC
12/22/2016 16-03 Weekly 20161222
Weekly EC
12/26/2016 16-03 Weekly 20161226
Conducted by AECOM on site construction inspector
Page 20 of 20
ATTACHMENT E
City of Oshkosh
2016 Construction Erosion Control Site Inspections of Private Development
City of Oshkosh, WI
Best Management Practice Report
2016 (January 01, 2016 To December 31, 2016)
4 Construction Site Pollutant Control
Responsible Staff / Position: James Rabe
Director of Public Works
(920) 236-5065
4.2 Construction Site ESC Inspection and Enforcement Procedures
Responsible Staff / Position
Required: Yes
John Ferris
Civil Engineering Supervisor
(920) 236-5065
Description
Adopt and maintain procedures for construction site inspection and enforcement of erosion and sediment control
measures. At a minimum, the procedures shall establish:
1. Municipal departments or staff responsible for construction site inspections and enforcement.
2. Construction site inspection frequency.
3. Construction site inspection documentation.
4. Enforcement mechanisms that will be used to obtain compliance.
Goals
4.2.1 ESC Inspection and Enforcement Procedures
Responsible Staff / Position Kris Lyons
Engineer Tech
(920) 236-5065
Description
Develop and maintain procedures for construction site erosion and sediment control inspection and
enforcement procedures as described. Review the procedures annually and update as needed to maintain
effectiveness and permit compliance.
Provide a copy of or reference to the current procedures each reporting period.
Planned: 2015 2016 2017 2018 2019 2020 2021
Complete:
Activity Date Name Description
04/14/2016 2270 Bowen St. Sediment Discharge Sediment left within ROW and not cleaned up at the
DR Hanson end of the working day. Had a phone conversation
with DR Hanson on 4-14-2016 regarding the
Page 1 of 20
sediment discharge on site.
Follow up site visit on 4-15-2016 showed the
sediment had been cleaned up. The contractor may
have power washed the sediment down the storm
sewer inlet, but I am unable to prove it because no
sediment was found in the inlet. Just spray marks on
the casting.
04/15/2016 2460 Jackson St - Jackson Square Random site inspection checking for EC
Apartments compliance. Issues where discovered and
discussed on site with the general contractor.
04/15/2016 3420 Jackson St - Reilly Real Estate Random EC inspection found multiple issues on
site. Clearing and grubbing was not disposed of
properly, no silt fence was installed around topsoil
stock pile even though a trench was installed for it
and it appears to be adjacent to a wetland, and a
clay gravel spoil pile needs to be removed, and the
topsoil stock pile needs to temporarily seeded.
Follow up phone call with Bud Hoch at 8:45 am on 4-
22-2016 regarding the enforcement notice sent to
the permit holder. Bud Hoch is going to clean up the
site by grading and stabilizing the exposed soil.
Phone # (920) 579-1601
Drive-by on 4-26-2016 Kris & Laura observed silt
fence around the stock pile, contractor digging
material from stock pile and placing around the
building prepping for seeding.
04/15/2016
2920 N. Main St - Hoffmaster
Site inspection. No activity to date.
Driveway
04/15/2016
2920 N Main St - Hoffmaster ConcreteSite
inspection. No activity to date
Pad
04/15/2016
1600 Hazel - Emmeline Cook Parking Site inspection. No activity to date.
Lot Expansion
04/15/2016
1600 Hazel St - Emmeline Cook
Site inspection. All project work has been completed
Elementary Site Improvements
and fully restored.
04/15/2016
3500 N Main St - Bemis Perfecseal
Site Inspection. All exterior site improvements have
been completed and restore.
04/15/2016
2200-2208 Jackson St - DADL
Site inspection. The site construction is complete
and full restored.
04/15/2016
1951 Bowen St - Office Buildings NewSite inspection. The project area is complete and
Garage
looks good.
04/15/2016
1819 Evans St - Govani Dental
Site inspection. The building is constructed. All EC
Addition
BMP's are installed and functioning. Site looks
good.
04/21/2016
Site Inspection
Bad Guys Made Mud
04/27/2016
1870 Stillman Dr - Corrim Accessory
Building is constructed. It looks good. No disturbed
Building
area with this building. Site complete.
Page 2 of 20
04/27/2016
1159 Rockwell Ave - WPS Pearl Ave
Site is complete.
Substation
04/27/2016
512-520 Algoma Blvd - Indian trail
Site is complete and looks good.
Apartment parking lot
04/27/2016
1005 & 1015 N Washburn St - Dicks
Site looks really good. Veg is growing through the
Sporting Goods & Petsmart
mat. Landscaping is all planted. Site is complete.
04/27/2016
1870 Stillman Dr - Corrim Solar
Solar panels where installed over winter. Site plan
Panels
does not call for any perimeter control. Disturbed
area needs to be stabilized. Topsoil pile on site for
final stabilization it appears. Will conduct a follow up
check in a few weeks to verify that site restoration is
beginning.
04/27/2016
4372-4398 Jackson St - Soda Creek
Multiple issues on site. Talked to Eric Nelson from
Nicolet and also Lee Breitkreutz from Town &
County. Letter has also been sent out to Eric Nelson
and the developer.
04/28/2016
639 Witzel Ave - Central Garage
Site is now complete. E-mat with veg growing
through it. Everything looks great.
04/28/2016
748 Algoma Blvd - Reeve Union
No activity on site
Entrance Improvements
05/17/2016
3321 County RD A - AP Nonweiler
Random EC inspection of building expansion. The
site looked really good. The only issue was an inlet
protection with the wrong fabric. The contractor on
site was informed and said they would get it. The
contractor walked to get a new bag and I observed
them walking back carrying the right kind of inlet
protection. The rest of the site will be hard surface in
a few days based on what the contractor told me.
05/17/2016
455 Marion Rd - The Rivers Phase 11
Walked the site with the contractor to go over the
issues on site as they were discovered. The inlet
protection was missing 2x4's, there was some
damaged silt fence, and a very little bit of tracking
from construction vehicles coming and going. The
contractor started having his guys fix the issues as
we discussed them and was very receptive during
the walk through.
06/09/2016
1062 N. Koeller St - Father Carr's
Parking lot freshly completed. No activity on site
Place 2B Parking Lot
currently.
06/09/2016
450 N. Campbell Rd - Riverview
No activity on site
Condo Parking
06/09/2016
1300 Georgia St - South Park
Site has been stabilized with hay mulch, so the soil
Restroom Facility
and mulch has been washing out into the curbline in
the street. It also appears that no seed was placed.
The site shall be stabilized with hydromulch or
erosion mat and seeded.
Page 3 of 20
06/09/2016
1221 Knapp St - Winnebago County
No activity on site
Garage
06/09/2016
1560 & 1564 S. Koeller St - Market
No activity on site
Fair Outbuilding and Ross Dress for
Less
06/09/2016
1580 S. Koeller St - Culver's Raze
No activity on site
and Rebuild
06/09/2016
1900 S. Koeller St - Target Parking
No activity on site
Lot Reconstruction
06/09/2016
1414 W. 20th Ave - West End Pizza
No activity on site
Expansion
06/09/2016
1000 Cumberland Tr - Cumberland
No activity on site
Court Apartments Improvements
06/09/2016
Mockingbird Way - Casey's Meadow
Minimal construction onsite. Only on private
Phase 1C
residential lots. No erosion control issues.
06/28/2016
2541 W. 20th Ave - Pepsi Driveway
No activity on site
and Parking Reconstruction
06/28/2016
2559 Badger Ave - ECM Holding
No activity on site
Group Parking Expansion
06/28/2016
2301 Universal St - Multicircuits
No activity on site. Small section of silt fence
Expansion
remaining in their onsite swale. They were already
told they could remove it, but wanted further
protection until grass grows more sufficiently in that
swa I e.
06/28/2016
2200 Badger Ave - Curwood/Bemis
No activity on site
Factory Addition
06/28/2016
2240 Westowne Ave - McDonald's
Drive-thru currently under construction. No Erosion
Drive-Thru
Control Issues
06/28/2016
2240 Westowne Ave - Shell Car WashNo activity on site
06/28/2016
505 S. Washburn St - AMS of
No activity on site. Stabilization/vegetation is patchy,
Wisconsin
but no soil movement.
06/28/2016
2875 Atlas Ave - 4 Imprint
No activity on site. Silt fence remaining along STH
91 on the southern boundary of the site can be
removed since vegetation is well established.
06/28/2016 3211-3299 Elk Ridge Dr - Hunters
Ridge Phase II and IV
Terraces along Elk Ridge Dr. have been restored,
but were not sufficiently stabilized. Topsoil is
washing off into the curb lines in the road. These
areas shall be re -seeded and stabilized with
hydromulch or erosion mat.
Curb lines and around inlets on Elk Ridge Dr. contain
large amounts of sediment from soil washing offsite.
These areas shall be swept.
Tracking pads leading from Elk Ridge Dr. to the site
(there are two locations) have been filling in due to
construction traffic, and are causing tracking out into
the road. Tracking pads shall be freshened up by
scraping and/or bringing in new stone material.
Perimeter of Phase IV contains no erosion control
Page 4 of 20
measures, and drains to the public road. Silt fence
or sediment logs shall be installed around the
perimeter of the exposed topsoil to prevent soil
movement offsite.
06/28/2016
3735 S. Washburn St - Big Rig
Construction underway. All perimeter controls are in
Chrome Shop Expansion
place. No erosion control issues present.
06/28/2016
Knapp St (Parcel 91334440000) -
Construction underway. All perimeter controls are in
EAA Exhibitor Pads/Gateways Project place. No erosion control issues present.
06/28/2016
450 W. 33rd Ave - Lakeside Plastics
Final Site Walk Through. Site is completely
Expansion
stabilized.
06/28/2016
3042 Oregon St - Henke Landscaping No erosion control issues. Warehouse has been
constructed, but pond construction has not yet
begun.
06/28/2016
2505 Oregon St - Chester V's
No activity on site
06/28/2016
2225 Minnesota St - Oshkosh Corp.
No activity on site
Parking Lot
06/28/2016
2211 Oregon St -Lake Aire Center
No activity on site
Parking Lot
06/28/2016
424 Oregon St - Southside Riverwalk- Silt fence has been installed across the swales that
East of Oregon
drain to the two inlets placed on the south side of the
new walking path. Silt fence is not allowed in
channelized flow.
Only the areas adjacent to the walking path have
been erosion matted, everything else was placed
with hay mulch.
06/28/2016
421 Oregon St - Southside Riverwalk No activity on site
- West of Oregon St
06/28/2016
45 W. 6th Ave - Lang Development
No activity on site
LLC
06/28/2016
706 S. Main St - Luecks Parking Lot
No activity on site.
Mill and Overlay
06/28/2016
1009 S. Main St - Fifth Ward Brewing
No activity on site
06/28/2016
243 Ohio St - U -Haul Loading Dock
Loading dock construction underway. No erosion
issues, site looks good.
06/28/2016
926 Dempsey Tr - DOT Building
No activity on site
Addition (WWTP Site)
06/28/2016
750 Witzel Ave - West Pointe Bank
No activity on site
Parking Lot
06/28/2016
300 N. Eagle St - Ahmadiyya Mosque No activity on site
Page 5 of 20
06/28/2016
375 N. Eagle St - Oshkosh West
No activity on site
Parking Lot Lighting
06/28/2016
600 N. Koeller St - River Valley One
No activity on site
Parking Lot Reconstruction
06/28/2016
530-540 N. Koeller St - N. Koeller
Sediment washing out onto public sidewalk where
Office Building
old driveway entrance was removed. Area needs to
be re-stabilized. Sidewalk was also not replaced as
it was supposed to. Right of way non-compliance
letter was issued regarding all outstanding items in
the right of way.
06/28/2016
1825 S. Washburn St - Tony's Auto
No activity on site
Body Addition
06/28/2016
2340 STH 44 - Taco John's
No activity on site
07/06/2016
2340 STH 44 - Taco John's
Final site inspection. No EC Issues, site is
stabilized.
07/06/2016
1580 S. Koeller St - Culver's Raze
Final site walk-through. No activity on site in some
and Rebuild
time, no erosion present.
Inlet protection is remaining in the existing drain
adjacent to the dumpster enclosure.
Representatives were told this could be removed
since site is fully stabilized.
07/14/2016
2200 Badger Ave - Curwood/Bemis
Final site inspection. No activity on site for some
Factory Addition
time.
Straw bale ditch checks remain in swales onsite.
Representatives told they could be removed as
vegetation is completely established and there are
no erosion control issues.
07/26/2016
Old post Office CTH A
DNR contacted the city regarding a brown water
discharge from a contractor.
It was determined the Northern Fiber was doing the
work.
Upon arrival it was noticed that they did discharge.
The contractor had a vac truck on site so they were
directed to suck up all of the discharge from the
catch basin and roadway along with material in the
terrace. They also power washed all of the sediment
from the area and sucked that up.
Photos where given to the DNR for their records.
08/03/2016
44 Frankfort St - Steven's Park
Site has been fully stabilized. Everything looked
Restroom Pavilion
good.
08/03/2016
425 Lake Shore Dr - City of Oshkosh
Site has grass growing through straw around new
Water Filtration Plant Expansion
building.
08/03/2016
1600 Hazel St - Emmeline Cook
Contractor has paved parking area. Contractor was
Elementary Parking Lot
installing E-mat while I was on site. I informed the
contractor that the mat installed backwards in
regards to the shingling. They immediately started
pulling up the overlapped areas and fixing.
Contractor was also informed that they need to get
Page 6 of 20
an inlet protection in 1 inlet where restoration won't
take place until after the new fence is installed. They
were going to install the next morning because they
didn't have one on their truck.
Site looked good.
08/03/2016
3321 County Road A - AP Nonweiler
Building is completed. Area around the building is all
hard surface. Site looks good.
08/03/2016
3321 County Road A - AP Nonweiler
No work has started yet.
Building Addition
08/03/2016
4372-4398 Jackson St - Soda Creek
Contractor is on site doing final site restoration.
Town & Country is installing top soil in swales and
around buildings.
Badger maintenance is fine grading topsoil areas.
Installing plants/ shrubs. Seeding and mating
finished areas.
08/03/2016
725 Butler Ave - Parkview Health
No activity on site yet
Care Center Parking Lot
08/03/2016
3420 Jackson St - Reilly Real Estate
Building is complete. Stock pile is removed. Silt
LLC Cold Storage Building
fence is still up because the site has a 2nd phase
that will be taking place.
08/03/2016
3420 Jackson St - Reilly Real Estate
No work has started for this project
LLC Second Cold Storage Bldg
08/03/2016
2460 Jackson St - Jackson Square
I, "Kris," have been in contact with the contractor in
regards to final stabilization. They are struggling to
get a contractor to complete the final stabilization. I
have given them a name of local contractors to talk
too. They have talked to them, but the financial side
has made changing contractors difficult
because they need to close 1 contract and then
open up another. Based on the last email with them
on 8/5/2016 from Bob Armstrong the contractor will
be back on site the week of 8/8/2016 completing the
work. I will continue to monitor the work on site and
see if the work is being completed during 8/8/2016 to
8/12/2016
08/04/2016 4372 - 4398 Jackson St - Soda Creek Badger maintenance is on site again stabilizing
swales on the north side of the property. E- mat was
shingled wrong. They were informed of the issue
and adjusted / fixed the area that was wrong. They
gave me their plan for what they wanted to do next.
08/05/2016 4372 - 4398 Jackson St - Soda Creek Contractor requested me to be on site to look at a
swale for them. The issue was building runoff and
losing their swales. I recommended they stabilize
the backside of the buildings and the swale at once
to minimize the exposed soil that can get damaged.
They agreed and will talk to their boss.
08/08/2016 4372 - 4398 Jackson St - Soda Creek Contractor requested me to be onsite to review what
was done. Work looked okay. They did inform me
that they are going to sod behind the buildings the
Page 7 of 20
rest of the week and restore the swale as they go
after installing the sod.
08/24/2016
2521 BOWEN ST - ANCHORAGE
Talked to Russ Williams on site regarding no
REALTY
perimeter control, no inlet protection, and tracking off
site. Told him that Type D modified IP was required
due to new WDNR rules. The entire area that the
building sat is exposed clay and construction debris.
He did say that he plans on filling the site and
stabilizing for winter. He is going to get a couple
pallets of sediment logs and ring the site tomorrow.
It was a very good discussion and he was
cooperative.
08/26/2016
2920 N. Main St - Hoffmaster
Everything is complete and looks good.
Concrete Pad & Fencing
08/26/2016
2920 N. Main St - Hoffmaster Parking It appears to be complete. It was a resurfacing of
Lot & Entrance
the turn around parking lot area.
08/26/2016
531 N. Main St - Dealer Fire Patio
Site is complete. Looks good.
08/26/2016
1100 W. Smith Ave - Oshkosh North
Was investigating around the northern 2 ball
Ball Biamond Bleacher Pad
diamonds. Was unable to locate any new work.
Laura informed me, Kris, that the ball diamond work
actually took place south of the ball diamonds across
the street.
08/26/2016
1010 W. Murdock Ave - The Wateford Paving is complete
Parking Lot
08/31/2016
3500 N. Main St - Bemis Perfect Seal
Site has been resurfaced in the their northern most
parking lot. Everything looks good.
09/16/2016
375 N. Eagle St - Oshkosh West
The lights and light bases are all installed.
Parking Lot Lighting
Everything has been restored
09/16/2016
Sunrise Estates
Utilities are installed. Contractor is cutting in road.
Site has silt fence installed and inlet protection
installed. The pond has not been installed. They
plan to install the pond after they finish cutting the
road.
09/16/2016
1600 Hazel - Emmeline Cook
Site has been restored. They finished landscaping
Elementary Parking Lot
along the northern fence
09/16/2016
505 Marion Rd - Mercury Marine
Site is complete. Everything appears paved.
Parking Lot
09/16/2016
1100 W. Smith - Oshkosh North
Site is complete. Looks good.
Bleacher Pad
09/16/2016
3420 Jackson - Reilly Real Estate
Building is installed. Site has been cleaned up.
Cold Storage 2nd building
09/16/2016
2460 Jackson - Jackson Square
Contractor is finally restoring the working area. Site
Apartments
looks good.
Page 8 of 20
09/16/2016 1870 Stillman - Corrim Company
Solar Panels
The disturbed area around the panels is vegetated
now. Everything else is stable.
09/16/2016 2510 W 9th - Marsh Eye Clinic
Site has perimeter control installed. IP was
the apartment to fix the issue. The contractor
installed. TP has been capped because parking lot
installed inlet protection and used a dewatering bag
is roughed in with stone
09/22/2016 1555 Algoma Blvd - Private House
Dewatering complaint regarding muddy water.
proceeded to clean up all the sediment in the
Talked with contractor on site regarding dewatering
roadway with snow shovels and heavy equipment.
technique. They had no practice in place. They
They will also sweep the road and install sediment
were also lacking inlet protection which they where
logs around the disturbed area. Stone bags will be
instructed to install. Perimeter control devices where
placed in the parking lot flowline that discharges into
also told to be installed around the site.
the disturbed area to slow the flow of water.
The contractor was very responsive and said that he
Egbert was demoing buildings for the new
would take care of everything.
10/06/2016 1335 Summit Ave - Water Main Break An 8" water main service to the apartment broke on
Private Side
Wednesday night. Walley Schmidt was contacted by
the apartment to fix the issue. The contractor
installed inlet protection and used a dewatering bag
while working on fixing the issue. They then
proceeded to clean up all the sediment in the
roadway with snow shovels and heavy equipment.
They will also sweep the road and install sediment
logs around the disturbed area. Stone bags will be
placed in the parking lot flowline that discharges into
the disturbed area to slow the flow of water.
10/06/2016 1130 N. Westfield St - Evergreen
Egbert was demoing buildings for the new
Manor Retirement Village
development. They were pulling sediment into the
ROW with their trucking operation. The contractor
was informed that they need to clean the road
surface. Soper Contractors was hired by Egbert to
clean the road surface with their sweeper.
12/01/2016 1000 CUMBERLAND TRL -
Complaint about mud on the road. Inspected (Kris)
CUMBERLAND TRAIL
site to see if the contractor was in compliance with
APARTMENTS
their EC plan. There was a little mud tracked on the
road because a sky lift had driven through a yard.
The contractor had a sweeper and went to clean the
road. There was no inlet protection on site. The
contractor contacted Egbert to have them install the
Type D modified inlet protection. There was also no
silt fence on site. The contractor indicated they
wanted to use a vegetative buffer. Looking at the
site the vegetative buffer was acceptable. I (Kris)
worked with them to amend their plan to keep them
in compliance. They were instructed that this plan
now must remain on site until the project is
complete. They were also informed that they must
keep a weekly and rain event inspection log to stay
with WDNR compliance.
Page 9 of 20
ATTACHMENT F
City of Oshkosh
2016 Pollution Prevention
State of Wisconsin
Department of Natural Resources
PO Box 7921, Madison WI 53707-7921
dnrmi.gov
No Exposure Certification
For Exclusion from WPDES Industrial Storm Water Permitting
Form 3400-188 (R 12/14) Page 1 of 4
Notice: This No Exposure Certification form is authorized by s. NR 216.21(3), Wis. Adm. Code. Submittal of this form is required for
industries listed within subchapter II of ch. NR 216, Wis. Adm. Code, where the facility has no exposure of materials or operations that
could contaminate storm water. This certification must be submitted to the Department every five years. Failure to properly submit a
completed No Exposure Certification to the Department every five years may result in forfeitures up to $10,000 per day, pursuant to s.
283.91(2), Wis. Stats. Personally identifiable information on this form may be used for other water quality program purposes.
Submission of this No Exposure Certification constitutes notice that the entity identified in Section I does not require permit
authorization for its storm water discharges associated with industrial activity under subch. II of ch. NR 216, Wis. Adm. Code, due to the
existence of a condition of "no exposure."
A condition of "no exposure" exists at an industrial facility when all industrial materials and activities are protected by a storm resistant
shelter to prevent exposure to rain, snow, snowmelt, and/or runoff. Industrial materials or activities include, but are not limited to,
material handling equipment or activities, industrial machinery, raw materials, intermediate products, by-products, final products, or
waste products. Material handling activities include the storage, loading and unloading, transportation, or conveyance of any raw
material, intermediate product, final product or waste product. A storm resistant shelter is not required for the following industrial
materials and activities:
• Drums, barrels, tanks, and similar containers that are tightly sealed, provided those containers are not deteriorated and do not leak.
"Sealed" means banded or otherwise secured and without operational taps or valves.
• Adequately maintained vehicles used in material handling.
• Final products, other than products that would be mobilized in storm water discharges (e.g., rock salt).
A No Exposure Certification must be provided for each facility applying for the no exposure exclusion. In addition, the exclusion from
WPDES permitting is available on a facility -wide basis only, not for individual outfalls. If any industrial activities or materials are or will
be exposed to precipitation, the facility is not eligible for the no exposure exclusion.
By signing and submitting this No Exposure Certification form, the entity in Section 1 is certifying that a condition of "no exposure" exists
at its facility or site, and is obligated to comply with the terms and conditions of s. NR 216.21(3), Wis. Adm. Code.
All information must be provided on this form. Detailed instructions for completing this form and obtaining the no exposure
exclusion are provided on pages 34. Please read the instructions prior to completely filling out this form.
Facility/Operator1.
Business Name
Operator Name
Contact Name
City of Oshkosh Water Filtration Plant
Brad Rokus
Brad Rokus
Mailing Address
City
State
ZIP Code
425 Lakeshore Drive
Oshkosh
I Wl
1 54901
E-mail Address
Phone Number
Alternate Phone Number
brokus@ci.oshkosh.wi.us
II. Facility/Site Location Information
(920) 232-5365
Facility Name
County
City 0 Town 0 Village
City of Oshkosh Water Filtration Plant
Winnebago
of Oshkosh
Location Address/Description
425 Lake Shore Drive
PLSS Information Township Range ® East Section Quarter Quarter -Quarter
18 N 17 E]west 19 1 NW SW
It site is not wholly containe in the quarter -quarter, more description Latitude Longitude
Q NW / QQ SW - SE portion 44.01873 -88.51841
Q NW / QQ SE - SW portion
Total acres of site associated with industrial activity 8.78 acres (entire property)
Yes No
0 0• Is the facility located on Indian Lands?
0 Di Is this a Federal facility?
0 Q Was the facility or site previously covered under a WPDES storm water permit?
If yes, provide the Facility Identification (FID) or FIN number (if known), and the SIC/activity codes
FID/FIN Number:I SIC/Activit Codes:
Primary: Secondary:
Q 0• Have you paved of roofed over a formerly exposed, pervious area in order to qualify for the no exposure exclusion?
If yes, indicate approximately how much area was paved or roofed over.
Acres paved or roofed over:
State of Wisconsin
DEPARTMENT OF NATURAL RESOURCES
Oshkosh Service Center
626 E. CTY RD Y, Suite 700
Oshkosh, Wl 54901
May 27, 2015
Steven Gohde
Oshkosh Wastewater Treatment Plant
215 Church Street
P O Box 1130
Oshkosh W1 54903-1130
Scott Walker, Governor
Cathy Stepp, Secretary
Jean Romback-Bartels, Regional bire,c to,
Telephone (920) 424-3050 1 WSCONSIN
FAX (920) 424-4404 DEPT. OF NATURAL RESOURCES
TDD () -
REC1;IVL-D
AJN - 12015
DP11t 0l` PUBLIC: OlRKS
OSHKOSH, WtSCONSIN
Subject: industrial Storm Water No Exposure Certification for
Facility: Oshkosh Wastewater Treatment Plant
Location: 233 Campbell Road, OSHKOSH, WI
FIN: 6096
Dear Facility Representative:
The Department of Natural Resources (Department) has evaluated the No Exposure Certification for Exclusion
from WPDES Storm Water Permitting (Form 3400-188) that you recently submitted, and has determined that
your facility does not require coverage under an Industrial Storm Water Discharge Permit as specified in
subchapter 11 of NR 216, Wis. Adm. Code. This determination is based upon the information provided by you for
your facility on Form 3400-188 stating your belief that the facility qualifies for a "conditional no exposure
exclusion" under s. NR 216.21(3), Wis. Adm. Code, and is contingent upon continued satisfaction of the
conditions under s. NR 216.21(3), Wis. Adm. Code.
Please be advised that under s. NR 216,21(3)(b)4,, Wis. Adm. Code, a No Exposure Certification must be
submitted for this facility every five years to maintain the no exposure status with the Department. The Effective
Date for the No Exposure Certification stahrs is May 27, 2015. If the industrial operations change at the facility
where industrial activities become exposed to storm water or if the Department determines facility discharges to
be significant contributors of pollutants to the waters of the state, the facility may be required to obtain coverage
under a General WPDES Industrial Storm Water Discharge Permit. If conditions change where industrial
activities become exposed to storm water, it will be your responsibility to notify the Department of the change in
the facility's status.
The Department appreciates your pollution prevention efforts to eliminate sources of storm water contamination
at the facility. If you have any questions concerning the contents of this letter,
please contact Susan Larson at Stisaii.Larsoii@Wiscoiisiii.gov or (920) 303-5449.
Sincerely,
Susan Larson
Storm Water Management Specialist
Northeast Region
dnr.W. ov PANTEO
wisconsin.gov Naturally WISCONSIN °APS `��`
No Exposure Certification
For Exclusion from WPDES Industrial Storm Water Permitting
Form 3400-188 (R 12/14) Page 2 of 4
(Completing this question does not disqualify you for the no exposure exclusion. However, your permitting authority may use
this information in considering whether storm water discharges from your site are likely to have an adverse impact on water
quality, in which case you could be required to obtain permit coverage.)
Required: Attach photos that are representative of the current outdoor conditions at the facility. Current photos may eliminate the need
for an inspection and facilitate a more timely acknowledgment by the Department.
Date Photos were taken: 01/12/2017
Exposure
• Are any of the following materials or activities exposed to precipitation, now or in the foreseeable future? If you answer
"Yes" to any of these questions, you are NOT eligible for the no exposure exclusion.
Yes
No
O
Using, storing or cleaning industrial machinery or equipment, and areas where residuals from using, storing or cleaning
industrial machinery or equipment remain and are exposed to storm water
O
Materials or residuals on the ground or in storm water inlets from spills/leaks
O
Materials or products from past industrial activity
O
Material handling equipment (except properly maintained vehicles)
O
Q
Materials or products during loading/unloading or transporting activities
Q
Materials or products stored outdoors (except final products intended for outside use [e.g., new cars] where exposure to
storm water does not result in the discharge of pollutants)
0
Q
Materials contained in open, deteriorated or leaking storage drums, barrels, tanks, and similar containers
0
Materials or products handled/stored on roads or railways owned or maintained by the discharger
0
Waste material (except waste in covered, non -leaking containers [e.g., dumpsters])
Q
Q
Application or disposal of process wastewater (unless otherwise permitted)
Q
IV. Certification
Q.
Particulate matter or visible deposits' of residuals from roof stacks and/or vents not otherwise regulated (i.e., under an air
quality control permit) and evident in the storm water outflow
& Signature
This form must be signed by an official representative of the permitted facility, in accordance with s. NR 216.22(7), Wis. Adm.
Code. See instructions on page 4. If this form is not signed, or is found to be incomplete, it will be returned.
No Exposure Certification for Exclusion from WPDES Industrial Storm Water Permitting:
I certify under penalty of law that I have read and understand the eligibility requirements for claiming a condition of "no exposure" and
obtaining an exclusion from WPDES storm water permitting.
I certify under penalty of law that there are no discharges of storm water contaminated by exposure to industrial activities or materials
from the industrial facility or site identified in this document (except as allowed under s. NR 216.21(3)(c), Wis. Adm. Code).
I understand that I am obligated to submit a No Exposure Certification form once every five years to the Department and, if requested,
to the operator of the local municipal separate storm sewer system (MS4) into which the facility discharges.
I understand that I must allow the Department, and MS4 operator where the discharge is into the local MS4, to perform inspections to
confirm the condition of "no exposure" and to make such inspection reports publicly available upon request.
I understand that I must obtain coverage under a WPDES permit prior to any point source discharge of storm water from the facility.
Additionally, I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in
accordance with a system designed to assure that qualified personnel properly gathered and evaluated the information submitted.
Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the
information, the information submitted is to the best of my knowledge and belief true, accurate and complete.
I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for
knowing violations.
Signature of Landowner/Authorized Representative Date Sig ed
Name of Landowner/Authorized Representative ITitle
Mail this completed form to the appropriate Wisconsin Department of Natural Resources office in the region where the facility
is located. See the instructions on the last page of this form for regional office addresses.
No Exposure Certification
For Exclusion from WPDES Industrial Storm Water Permitting
Form 3400-188 (R 12/14) Page 3 of 4
Instructions
Who May File a No Exposure Certification
Wisconsin law under subch. II of ch. NR 216, Wis. Adm. Code, prohibits point source discharges of storm water associated with
industrial activity to waters of the State without a Wisconsin Pollutant Discharge Elimination System (WPDES) permit. However,
WPDES permit coverage is not required for discharges of storm water associated with industrial activities if the discharger can certify
that a condition of "no exposure" exists at the industrial facility or site. Storm water discharges from construction activities identified in
subch. III of NR ch. 216, Wis. Adm. Code, are not eligible for the no exposure exclusion.
Obtaining and Maintaining the No Exposure Exclusion
This form is used to certify that a condition of "no exposure" exists at the industrial facility or site described herein. This certification
must be re -submitted once every five years. The industrial facility operator must maintain a condition of "no exposure" at the facility or
site in order for the no exposure exclusion to remain applicable. A facility that has submitted a No Exposure Certification form should
routinely inspect the facility to verify that it continues to operate in a condition of "no exposure."
If conditions change resulting in the exposure of materials and activities to storm water, the facility operator must obtain coverage
under a WPDES storm water permit immediately. Any conditionally exempt discharger who anticipates changes in circumstances shall
submit a Notice of Intent form to the Department 14 or more working days prior to the change of circumstances and in accordance with
s. NR 216.22, Wis. Adm. Code.
Completing the Form
You must type or clearly print your answers to all questions. One No Exposure Certification form must be completed for each facility or
site for which you are seeking to certify a condition of "no exposure". Please make sure you have addressed all applicable questions
and have made a photocopy for your records before sending the completed form to the Department.
Additional guidance on no exposure certification can be accessed at US EPA's website:
http://cfpub.epa.aov/npdes/stormwater/exposure.cfm or contact the Department Storm Water Program at: 608-267-7694.
Provide the legal name of the business that operates the facility or site described in this certification.
The operator is the legal entity that controls the facility's operation, rather than the plant or site manager. Provide the name of the
person who will be the contact for the operator.
Provide the contact information for the operator contact.
Provide the mailing address for the operator contact. All correspondence will be sent to this address.
1. Enter the official or legal name of the facility or site, the county, and municipality name.
2. Enter the location address, if no address exists, provide a geographic description.
3. Enter the geographical description of the approximate center of the facility or site in Public Land Survey System (PLSS) format
with township, range, section, quarter, and quarter -quarter information.
Note: This information can be found on property tax statements, plat maps, Wisconsin Atlas and Gazetteer, and online with
Wisconsin DNR Surface Water Data Viewer at: http://dnrmaps.wi.gov/sl/?Viewer=SWDV
4. Enter the Latitude and Longitude in decimal degrees.
5. Enter the total acres of the site associated with industrial activity.
6. Indicate whether the facility is located on Indian Lands.
7. Indicate whether the industrial facility is operated by a department or agency of the Federal Government (see also Section 313 of
the Clean Water Act).
8. Indicate whether the facility was previously covered under a WPDES storm water permit.
If yes, include the Facility ID Number (FID) and/or FIN.
Enter the 4 -digit SIC code which identifies the facility's primary activity and second 4 -digit SIC code identifying the facility's
secondary activity, if applicable. SIC codes can be obtained from: https://www.osha.gov/pis/imis/sic_manual.html
9. Indicate whether a formerly exposed, pervious area (i.e., lawn, meadow, dirt or gravel road/parking lot) has been paved or roofed
over in order to qualify for no exposure.
If yes, indicate approximately how much area was paved or roofed over.
10. Required: attaching photos that are representative of the current outdoor conditions may eliminate the need for an inspection
and facilitate a more timely acknowledgment by the Department. Provide the date the photos were taken.
No Exposure Certification
For Exclusion from WPDES Industrial Storm Water Permitting
Form 3400-188 (R 12/14) Page 4 of 4
ExposureSection Ill.
Check "Yes" or "No" as appropriate to describe the exposure conditions at your facility. If you answer "Yes" to ANY of the questions in
this section, a potential for exposure exists at your site and you cannot certify to a condition of "no exposure". You must obtain
coverage under a WPDES storm water permit if you have not already done so. After obtaining permit coverage, you can institute
modifications to eliminate the potential for a discharge of storm water exposed to industrial activity, and then certify to a condition of
"no exposure."
Section IV. Certification & Signature
Wisconsin statutes provide severe penalties for submitting false information on this application form. State regulations require this
application to be signed in accordance with the signatory requirements of s. NR 216.22 (7), Wis. Adm. Code:
1. For a corporation: a responsible corporate officer including president, secretary, treasurer, vice president, manager, or a duly
authorized representative having overall responsibility for the operation covered by this permit
2. For a unit of government: a ranking elected official, or other duly authorized representative
3. For a partnership: a general partner; and for a sole proprietorship: the proprietor
4. For a limited liability company: a manager
Address
Unless otherwise directed, mail the completed NOI form to the Wisconsin DNR (WDNR) office associated with the county of the facility
site location as follows:
SOUTH•
Columbia Grant Jefferson
Dane Green LaFayette
Dodge Iowa Richland
Rock WDNR South Central Regional
Sauk Headquarters
3911 Fish Hatchery Road
Fitchburg, WI 53711
608-275-3266
I SOUTHEAST REGION (SER)
Kenosha Ozaukee Sheboygan
Milwaukee Racine Walworth
Washington WDNR Waukesha Service Center
Waukesha 141 N.W. Barstow Street, Room 180
Waukesha, WI 53188
262-574-2100
NORTHERN•
(NOR)
Ashland
Douglas
Langlade
Rusk
WDNR Baldwin Service Center
Barron
Florence
Lincoln
Sawyer
890 Spruce Street
Bayfield
Forest
Oneida
Taylor
Baldwin, WI 54002
Burnett
Iron
Polk
Vilas
715-684-2914 ext. 109
Price
Washburn
NORTHEAST•
Brown
Green Lake
Marquette
Outagamie
WDNR Northeast Regional Headquarters
Calumet
Kewaunee
Menominee
Shawano
2984 Shawano Avenue
Door
Manitowoc
Oconto
Waupaca
Green Bay, WI 54313-6727
Fond du Lac
Marinette
Oneida Reservation
Waushara
920-662-5100
Winnebago
CENTRAL
REGIOWEST
Adams
Crawford
La Crosse
Portage
WDNR Baldwin Service Center
Buffalo
Dunn
Marathon
St. Croix
890 Spruce Street
Chippewa
Eau Claire
Monroe
Trempealeau
Baldwin, WI 54002
Clark
Jackson
Pepin
Vernon
715-684-2914 ext. 109
Juneau
Pierce
Wood
SOUTH•
Columbia Grant Jefferson
Dane Green LaFayette
Dodge Iowa Richland
Rock WDNR South Central Regional
Sauk Headquarters
3911 Fish Hatchery Road
Fitchburg, WI 53711
608-275-3266
I SOUTHEAST REGION (SER)
Kenosha Ozaukee Sheboygan
Milwaukee Racine Walworth
Washington WDNR Waukesha Service Center
Waukesha 141 N.W. Barstow Street, Room 180
Waukesha, WI 53188
262-574-2100
m
W
D
J
~ Materials
—Receiving
f Area
a;
ater
Filtration Pump
!ant ` Station
Backwash Chlorine
Water Contact
Holding Basin
Tank
Washington Avenue
(2009 air photo)
Brown- . Site Map N o so too
1 �
Caldwell ' City Of Oshkosh Feet
Water Filtration Plant °a�° grz°
— In' SS-If^SS
11tAE BTflE£T
mm".
AC AS
L
RI E
S
PPL BA IN
ON
A
o
LIFT PUMP
STATION
B
IN
42'FW
S
BWR- BACKWASH RECYCLE
— In' SS-If^SS
11tAE BTflE£T
mm".
LOW LIFT
PUMP
STATION
O
—30'RW
36^FW— —24" SID �2q,
aLL —24'WM2p I z `24"WM-
76>
av II �'WM I Ni �.Cjy m3 I %—12'WM—
HIGH
LIFT O v v
PUMP
TATION
CENTER 30'FW—
SOUTH ClEARWELL CLEARWELL NORTH CLEARWELL
(0.7 MG) (0.66MG) (1.1 MG)
LOW LIFT
SO
2T SD
II_
AND HIGH
LEGEND
o
LIFT PUMP
STATION
,,,
--30-RW
BWR- BACKWASH RECYCLE
O2piE CONTACTOR N0.2
—30"RW
6'TD, TYP
30^ RW
BWS- BACKWASH SUPPLY
BW W - BACKWASH WASTEWATER
MEOM
FiLTFn No.�
ZED
sEo1MENrATroN fiALNTRAM z9 -
c
�.
CCP- CHEM FEED FFLUENCARRIER PIPE
FE- FILTER EFFLUENT
OOPL MEON
11 ��
EEMNENTATION BAfiM TRAINU q
II
.I 6
FLOW
METER
VAULT
>
k
FTN- FILTER TO WASTE
FW- FINISHED WATER
■��
ET�
Ti
III
a
.
PDO - PUt
RW- RAWWATER
ozplE coNrAcroR No.l
uuu n�oln
10 6 2
❑❑❑
SEOIMEMATN]N RASH TRAM iB
•11
RM DRA"1'..�
SD- STORMDRAN
FILTER N0.2
3
�
1i11
$D- TANKAIN
TD • TA
WATER
SEOIMEMATgN BASH TRAM IA `
•III
CH2IVIHILL.
N
TER I
WM- WATER MAIN
FILTRATION
PLANT
ONAI L�dA
fIITER NO. 1
fLoccunau
6A6
.,�, .- M,y
�
�
DOR O CATCH BASIN
Q HYDRANT®
OO......
e"IIJM
o MANHOLE
STORM OUTLET
® VALVE
LOW LIFT
PUMP
STATION
O
—30'RW
36^FW— —24" SID �2q,
aLL —24'WM2p I z `24"WM-
76>
av II �'WM I Ni �.Cjy m3 I %—12'WM—
HIGH
LIFT O v v
PUMP
TATION
CENTER 30'FW—
SOUTH ClEARWELL CLEARWELL NORTH CLEARWELL
(0.7 MG) (0.66MG) (1.1 MG)
LOW LIFT
SO
2T SD
AND HIGH
o
LIFT PUMP
STATION
,,,
--30-RW
—30"RW
30^ RW
m
I o 14'BWR 24 WM—
I
�.
N PLANT
FLOW
METER
VAULT
I I
w
�.�......�.,��Ir
■��
tt
WATER FILTRATION PLANT
LOW LIFT
PUMP
STATION
O
—30'RW
36^FW— —24" SID �2q,
aLL —24'WM2p I z `24"WM-
76>
av II �'WM I Ni �.Cjy m3 I %—12'WM—
HIGH
LIFT O v v
PUMP
TATION
CENTER 30'FW—
SOUTH ClEARWELL CLEARWELL NORTH CLEARWELL
(0.7 MG) (0.66MG) (1.1 MG)
LOW LIFT
SO
2T SD
AND HIGH
o
LIFT PUMP
STATION
,,,
--30-RW
—30"RW
30^ RW
m
I o 14'BWR 24 WM—
I
N PLANT
I I
SCHEMATIC
tt
WATER FILTRATION PLANT
unNE
CRY OF OSHKOSH, WISCONSIN
oos�E
I O
3
�
`v
' ""E�µE��
CH2IVIHILL.
City of Oshkosh Water Filtration Plant.
WPDES Stormwater No Exposure Documentation
Water Filtration Plant: Administrative Wing.
M 16/2 MTV
Water Filtration Plant: Material Receiving Area (all dry material delivered within confines of building)
Site Photos Page 1
City of Oshkosh Water Filtration Plant.
WPDES Stormwater No Exposure Documentation
i
4
Water Filtration Plant: liquid material receiving (Secondary
containment sump. Potential spills are contained in
sump and disposed to sanitary system)
Site Photos Page 2
Water Filtration Plant: Low/ High Pump Station
Department of Public Works'
Field Operations Facility
Stormwater Pollution Prevention Plan
Prepared for
City of Oshkosh
Oshkosh, WI
April, 2017
Public Works' Field Operations Facility
Stormwater Pollution Prevention Plan
Prepared for
City of Oshkosh, Oshkosh, WI
April, 2017
Brown-,, Caldwell
SWPPP Final Version 04 18 17
City of Oshkosh: Field Operations Facility SWPPP
Table of Contents
Table of Contents
Listof Tables............................................................................................................................................... iv
1. Introduction
.......................................................................................................................................1-1
1.1
General Site Description........................................................................................................1-1
1.2
Regulatory Background..........................................................................................................1-1
1.3
Objectives and Scope of Stormwater Pollution Prevention Plan.........................................1-2
1.4
Stormwater Pollution Prevention Responsibility...................................................................1-2
1.5
Plan Availability.......................................................................................................................1-2
1.6
Plan Compliance and Modifications......................................................................................1-2
1.7
Other Plans Incorporated by Reference................................................................................1-2
2. Stormwater
Pollution Prevention Team...........................................................................................2-1
2.1
Team Coordinator...................................................................................................................2-1
2.2
Team Members.......................................................................................................................2-2
3. Potential
Contamination Sources and Risk Identification..............................................................3-1
3.1
Initial Site Evaluation Summary.............................................................................................3-1
3.2
Stormwater Drainage and Outfalls........................................................................................3-2
3.3
Areas of Potential Stormwater Contamination.....................................................................3-3
3.4
Materials Inventory.................................................................................................................3-3
3.5
Vehicle Inventory .....................................................................................................................3-4
3.6
Historical Leaks and Spills.....................................................................................................3-5
3.7
Non-Stormwater Runoff Discharges......................................................................................3-5
4. Best
Management Practices............................................................................................................4-1
4.1
Objective..................................................................................................................................4-1
4.2
Management Measures and Controls...................................................................................4-1
4.2.1 Existing Management Practices..............................................................................4-1
4.2.2 Proposed Management Practices...........................................................................4-2
4.3
Management Practices Implementation...............................................................................4-2
4.4
Prohibited Activities................................................................................................................4-3
4.5
Residual Pollutants Expected to Remain in Stormwater......................................................4-3
5. Inspections and Record Keeping.....................................................................................................5-1
5.1
Quarterly Visual Stormwater Outfall Inspections..................................................................5-1
5.2
Semi -Annual Structural BMP Inspection...............................................................................5-1
5.3
Annual Site Review and Inspection.......................................................................................5-2
5.4
Spill Response and Documentation......................................................................................5-2
5.5
Annual Stormwater Sampling and Testing............................................................................5-3
5.6
SWPPP Updates or Revisions.................................................................................................5-3
5.7
Employee Training Requirements..........................................................................................5-3
Brown,,-- Caldwell
iii
SWPPP Final Version 04 18 17
City of Oshkosh: Field Operations Facility SWPPP
Table of Contents
5.8 Preventive Maintenance........................................................................................................5-3
5.9 Implementation Schedule......................................................................................................5-3
Appendix A: Field Operations Facility Emergency Contact 2017 Rotation List.....................................A-1
Appendix B: Blank Checklists and Forms............................................................................................... B-1
Appendix C: Completed Checklists and Forms........................................................................................0-1
Appendix D: WDNR Fact Sheet Defining Reportable Spills................................................................... D-1
AppendixE: Figures...................................................................................................................................E-1
List of Tables
Table 1. Stormwater Pollution Prevention Team....................................................................................2-1
Table 2. Field Operations Facility Area Descriptions..............................................................................3-1
Table 3. Stormwater Outfall Drainage Basins........................................................................................3-2
Table 4. Stormwater Drainage Basins.....................................................................................................3-3
Table 5. Areas of Potential Stormwater Contamination.........................................................................3-3
Table6. Materials Inventory .....................................................................................................................3-4
Table7. Vehicle Inventory ........................................................................................................................3-5
Brown,,-- Caldwell
iv
SWPPP Final Version 04 18 17
Section 1
Introduction
1.1 General Site Description
The City of Oshkosh Field Operations Facility (Facility) is located at 639 Witzel Avenue, Oshkosh, WI
54902. A location map of the facility is found in Figure 1. The main entrance to the site is via Ohio
Street, and there are secondary access drives from 3rd Avenue, Idaho Street, and Witzel Avenue. The
entire site encompasses approximately 15.6 acres. The Facility is the headquarters for the field
operations of the Public Works Department for the City of Oshkosh. The site houses offices and
facilities for some public works department staff, vehicle storage, maintenance operations for most
municipal vehicles, and materials storage for the public works department and other City
departments. Also on the site is a fueling station, road salt storage building, a public yard waste
drop off location and a public used oil drop off location.
It should be noted that this facility was completely re -built and completion of the final phase was in
February, 2016. During the design and re -building process, proper stormwater management was a
major consideration. Special attention was given to operations such as materials delivery, vehicle
maintenance, fueling area, and stormwater management measures. The re -built site fully complied
with the City's and state's stormwater management requirements and guidance.
1.2 Regulatory Background
The United States Environmental Protection Agency (USEPA) developed the stormwater regulatory
program through the authority of the Clean Water Act amendments of 1987 to reduce discharges of
contaminated stormwater associated with urban areas. The National Pollutant Discharge Elimination
System (NPDES) program is the USEPA program to regulate discharges of wastewater and
stormwater into waters of the United States through the issuance of discharge permits. The rules
adopted by the USEPA require permits for stormwater discharges where stormwater runoff may
contact contaminants through industrial activity, at construction sites, and from/or in municipalities
with separate storm sewer system (MS4) permits.
In Wisconsin, the Department of Natural Resources (WDNR) is the permitting authority for the
stormwater NPDES program. The primary goal of the stormwater program is to improve the quality of
surface waters by reducing stormwater pollution. State stormwater regulations are primarily found in
Wisconsin Administrative Code Chapters NR 216 and NR 151. All code references cited in this
document refer to the current NR 216 Code, and NR 151 Code.
The City of Oshkosh received a Municipal Separate Storm Sewer System Permit (MS4) under NR
216.02(4) in 2007, and the permit was re -issued in 2014. Section 2.6.7 of the MS4 Permit requires
"Storm water pollution prevention planning for municipal garages, storage areas and other sources
of storm water pollution from municipal facilities." This information must be submitted to the WDNR
with the annual report prepared by the City. This document contains the information required for
submittal under the MS4 Permit. The document follows the basic format of an industrial facility
Stormwater Pollution Prevention Plan (SWPPP) and will be referred to as a "SWPPP" for the Field
Operations Facility.
Brown— Caldwell
1-1
SWPPP Final Version 04 18 17
City of Oshkosh: Field Operations Facility SWPPP
Section 1
1.3 Objectives and Scope of Stormwater Pollution Prevention Plan
This SWPPP identifies potential sources of stormwater contamination, and preventive measures that
are in place to reduce stormwater pollution. The SWPPP focuses on two major objectives:
1. The identification of site conditions and activities that are potential sources of
stormwater pollution.
2. The identification of practices that minimize and control pollutants in stormwater runoff.
The scope of this plan includes:
1. Identification of a Facility stormwater contact person,
2. Descriptions and maps showing relevant site features,
3. An inventory of equipment used or stored at the facility,
4. A description of materials exposed to stormwater that may contribute to pollution,
5. A description of current and proposed Best Management Practices (BMPs),
6. Implementation schedule for BMPs,
7. A list of spills and leaks over the last 3 years,
8. Employee training requirements,
9. A description of site compliance and monitoring, and
10. Recordkeeping and internal reporting requirements.
1.4 Stormwater Pollution Prevention Responsibility
The persons listed on Table 1 are responsible for the stormwater management at the Field
Operations Facility (Facility), including future revisions to the SWPPP.
1.5 Plan Availability
A copy of this SWPPP will be maintained at the Facility at all times and a second copy of this plan will
be on file at the Oshkosh Engineering Division office at 215 Church Avenue, Oshkosh, WI. Copies will
be made available to WDNR representatives at their request.
1.6 Plan Compliance and Modifications
This SWPPP will be updated and amended whenever there is a change in design, construction,
operation, or maintenance of the Facility that may impact the potential for pollutants to be
discharged through stormwater. This SWPPP also should be revised in accordance with the findings
and recommendations from the annual site review and inspection. In addition, if this SWPPP is
found to be ineffective in controlling the discharge of pollutants, the SWPPP should be amended to
correct the identified deficiencies.
1.7 Other Plans Incorporated by Reference
Certain other environmental management plans may contain provisions for managing stormwater. In
some cases, it may be possible to build on elements of these plans that are relevant to stormwater
pollution prevention. In this case, the Facility does not currently have any other environmental
management plans specific to the site. The City does have a city-wide stormwater management plan
(updated in 2014) which provides stormwater pollution control guidance on a larger scale for the
City.
Brown— Caldwell
1-2
SWPPP Final Version 04 18 17
Section 2
Stormwater Pollution Prevention
Team
The stormwater pollution prevention team consists of a team coordinator and team members who
are assigned various responsibilities for implementing the SWPPP. Implementation of this SWPPP
includes:
1. Ongoing assessment of potential sources of contamination and associated BMPs,
2. Response to spill events, if any,
3. Employee training, and
4. The annual plan evaluation.
The current team roster is provided in Table 1. Each member has specific responsibilities in
maintaining and implementing the SWPPP. Individuals may have more than one responsibility.
Table 1.
Stormwater Pollution Prevention Team
Responsibility
Name
Phone Number
Team Coordinator
Kevin Uhen; Field Operations Manager
920-232-5380
Primary Emergency Contact (M -F 7:OOam -
Kevin Uhen; Field Operations Manager
920-232-5380
3:OOpm)
Secondary Emergency Contact (M -F 7:OOam -
Travis Hildebrandt; Mechanics Manager
Office: 920-232-5380
3:OOpm)
Cell: 920-379-3506
On-call Supervisor- Rotating Schedule
Emergency Calls - after hours (24 hours)
920-379-3508
(SeeAppendixA)
Coordination with Engineering Division and
John Ferris; Civil Engineering Supervisor
920-236-5065
City-wide stormwater program
2.1 Team Coordinator
The stormwater pollution prevention coordinator has the ongoing responsibility for implementation of
this SWPPP. Specifically, this includes:
1. Implementation of inspection schedules,
2. Records preservation,
3. Coordinating responses to spill emergencies,
4. Employee training, and
5. Annual updates to the SWPPP, if required.
The team coordinator serves as a point of contact for facility personnel and for those outside the
facility (such as regulatory officials) who may wish to discuss aspects of the SWPPP or to obtain other
information. The coordinator oversees the re-evaluation and modification of this document annually
and following a major spill event. These modifications may include:
Brown— Caldwetl
2-1
SWPPP Final Version 04 18 17
City of Oshkosh: Field Operations Facility SWPPP Section 2
1. Relocation or alteration of material storage or handling areas,
2. Best management practice revisions (structural or non-structural),
3. Altering drainage patterns,
4. Addition of structural control measures, or
5. Documentation of significant leaks or spill events.
The coordinator must be familiar with all phases of facility operation to evaluate potential sources of
pollution during implementation and periodic reevaluation of this document.
2.2 Team Members
At the direction of the Team Coordinator, members of the team have the responsibility for:
• Conducting inspections,
• Implementing and maintaining BMPs,
• Conducting annual employee training and new employee training, and
• Responding to spill events, if any.
Team members will meet with the coordinator annually and following spill events to re-evaluate and
modify the SWPPP as needed. If individual team members must be replaced, equally qualified
personnel will be assigned by the team coordinator to assume the previous members'
responsibilities. If this cannot be accomplished immediately, the current team members will be
assigned to those responsibilities during the interim.
Brawn— Caldwell
2-2
SWPPP Final Version 04 18 17
Section 3
Potential Contamination Sources
and Risk Identification
3.1 Initial Site Evaluation Summary
The site evaluation includes an assessment of potential pollutant sources to determine areas,
activities, and materials that may contribute pollutants to stormwater runoff. The evaluation
determines the necessity for BMPs and helps guide the selection of the most appropriate BMPs to
prevent or control pollutants from these areas, activities, and materials.
Brown and Caldwell conducted site evaluations on August 9, 2016 and January 12, 2017. The
Facility site contains the following buildings:
• Main Building (also called "Building 1" in this plan
• Cold Storage,
• Salt Storage Shed,
• Covered Bin Storage #1
• Covered Bin Storage #2
Also on the site are outdoor material storage areas, parking areas, public yard waste dropoff, public
oil recycling, and a municipal vehicle fueling area. These features are shown on Figure 2 and
described more fully in Table 2. For purposes of this plan the Main Building has been divided into
several functional areas to more accurately represent the activities occurring, the locations of these
activities within the building, and the roof drainage discharge points. The activities conducted at
each of these areas are listed below in Table 2. The locations of buildings and areas listed on Table
2 is shown on Figure 2.
Brown— Caldwetl
3-1
SWPPP Final Version 04 18 17
Table 2. Field Operations Facility Area Descriptions
Map ID #
(Figure 2)
Area Name
Description
Area
(sq. ft.)
Floor
Drains
1
Administrative Offices
Administrative Offices, Lockers, Training for staff
8,200
Yes
2
Maintenance Facilities
Repair Bays & Weld Shop used to perform maintenance of municipal
vehicles (major & minor repairs)
11,625
Yes
3
Garage
Parking for Streets and Sanitation Department Vehicles
97,700
Yes
4
Department Shops
Storage and work areas forvarious tasks
11,500
Yes
5
Oil Room
Oil & Paint Storage
288
Yes
6
Vehicle Wash Area
Wash station for streets and sanitation department vehicles
4,633
Yes
7
Saltshed
Storage for road salt and liquid de-icer (salt brine)
5,700
No
8
Cold Storage Building
Miscellaneous equipment. Paver, rollers, compressors, pumps, flat-bed
trailer, construction materials.
20,980
Yes
9
Covered Bin Storage #1
Storage of plow blades
5,000
N/A
10
Fueling Station
Vehicle fueling for all City vehicles except buses, covered by awning
1,860
N/A
11
Water Utility Storage
Storage of drinking water distribution materials (ductile iron pipe,
valves, fire hydrants, cold patch, bedding stone)
16,655
N/A
Brown— Caldwetl
3-1
SWPPP Final Version 04 18 17
City of Oshkosh: Field Operations Facility SWPPP
Table 2 Continued
Q + i— '�!
*All floor drains within buildings are connected to the sanitary sewer system.
3.2 Stormwater Drainage and Outfalls
The Facility covers approximately 15.6 acres. The site has six storm sewer outfalls. The outfalls, and
the watershed to each outfall, are identified on Figure 3. Table 3 summarizes the drainage area
characteristics of each of outfall.
Outfall ID.
Watershed Area
(acres)
0.60
Table 2. Field Operations Facility Area Descriptions
Contributory Drainage
Areas
BLDG 1F, Area 3
Outfall A
Map ID #
Area Name
Description
Area
Floor
(Figure 2)
2.14
69%
(sq. ft.)
Drains
12
Storm & Sanitary
Storage of materials for storm and sanitary sewer manholes and inlets
12,425
N/A
98%
Structure Storage
(castings, grates, concrete riser sections)
13
Miscellaneous Storage
Storage for miscellaneous materials, seasonally dependent (examples
27,030
N/A
Area
include Christmas trees, dumpsters, chippers)
14
Covered Bin Storage #2
Bins covered by roof for storage of miscellaneous materials such as;
3,350
N/A
rocks, gravel, topsoil, cold mix
15
Public Yard Waste Drop-
Public drop-off area for yard waste (grass clippings, brush, etc.)
31,130
N/A
Off
16
Public Waste Oil Drop-
Two 175 gallon waste oil tanks. Each within concrete secondary
385
N/A
off
containment. Both tanks under roof.
17
Scrap Metal Dumpsters
Dumpsters for disposal for scrap metal waste generated by Public Works
1,860
N/A
Department (no public access)
18
Employee & Visitor
Employee & visitor vehicle parking
33,450
N/A
Parking
*All floor drains within buildings are connected to the sanitary sewer system.
3.2 Stormwater Drainage and Outfalls
The Facility covers approximately 15.6 acres. The site has six storm sewer outfalls. The outfalls, and
the watershed to each outfall, are identified on Figure 3. Table 3 summarizes the drainage area
characteristics of each of outfall.
Outfall ID.
Watershed Area
(acres)
0.60
Percent Impervious
Contributory Drainage
Areas
BLDG 1F, Area 3
Outfall A
48%
Outfall B
3.00
70%
Area 1-2
Outfall C
2.14
69%
BLDG 1D, 1E, Area 4
Outfall D
Outfall E
2.43
2.19
4.20
100%
BLDG 1A, 1B, 1C, 1G
Area 5, 10, 11
100%
Outfall F
98%
BLDG 2, Area 5, 6, 7, 8, 9,
12
Direct Offsite 1.04 7% Offsite Areas 1, 2, 3
Total Site 15.60 81%
The site has been further sub -divided into 16 drainage areas. The drainage areas, along with
general flow direction and discharge points are shown on Figure 3. Attributes of each drainage area
and the structural stormwater treatment provided are summarized in Table 4. All runoff leavingthe
site enters City of Oshkosh storm sewers, and ultimately discharges to the Fox River via two storm
sewers with outfalls near the Ohio Street bridge.
Brown— Caldwell
3-2
SWPPP Final Version 04 18 17
City of Oshkosh: Field Operations Facility SWPPP
Section 3
3.3 Areas of Potential Stormwater Contamination
Based on conversations with City staff and site inspections of the facility, the highest potential
sources of stormwater pollution are listed in Table 5. The location of each area can be seen on
Figure 2. Recommendations for each of these identified areas are provided in Section 4 of this
document.
Table 4. Stormwater Drainage Basins
Percent Impervious Structural BMP Conveyance Type
Basin ID.
Area (acres)
AREA 1-2
3.00
70%
Grass Swale & Biofilter
Storm Sewer
AREA
0.49
38%
Biofilter
Storm Sewer
AREA 4
1.44
54%
Biofilter
Storm Sewer
AREA 5
2.85
100%
Underground Detention
Storm Sewer
AREA 6
0.30
100%
Inlet with Sump
Storm Sewer
AREA 7
0.13
100%
Inletwith Sump
Storm Sewer
AREA 8
0.12
100%
Inletwith Sump
Storm Sewer
AREA 9
0.20
100%
Inletwith Sump
Storm Sewer
AREA 10
0.85
100%
None
Storm Sewer
AREA 11
1.34
100%
None
Storm Sewer
AREA 12
0.12
42%
Inlet with Sump
Storm Sewer
BLDG 1A, 113, 1C,
1D, 1E, 1F, 1G
3.24
100%
None
Storm Sewer
BLDG 2
0.48
100%
None
Storm Sewer
OFFSITE AREAS
1.04
7%
None
Overland Flow
Total Site
15.60
81%
3.3 Areas of Potential Stormwater Contamination
Based on conversations with City staff and site inspections of the facility, the highest potential
sources of stormwater pollution are listed in Table 5. The location of each area can be seen on
Figure 2. Recommendations for each of these identified areas are provided in Section 4 of this
document.
3.4 Materials Inventory
Materials that are present at this facility with potential to contribute to stormwater pollution are
itemized in Table 6. The table includes a material description, use, location, approximate quantity of
material stored, containment methods, and likelihood of exposure to stormwater. Figure 2 shows
the location of the material on the site.
Brown— Caldwetl
3-3
SWPPP Final Version 04 18 17
Table 5. Areas of Potential Stormwater Contamination
Map ID
Potential
Outfall
Area
Problem Description
#
Pollutants
Locations
7
Saltshed
Salt & brine are enclosed in building - potential for
Salt/ Liquid de-icer
Outfall F
contamination duringtruck loading
10
Fueling area
Outdoor fuel pumps covered by awning; limited potential for spills
Diesel fuel and
Outfall F
to be exposed to runoff and carried into storm sewer
gasoline
11, 12,
Outdoor
Equipment and materials stored outdoors are exposed to rain -
Various
Outfall E
13
storage areas
any pollutants attached to materials may be carried by runoff
3.4 Materials Inventory
Materials that are present at this facility with potential to contribute to stormwater pollution are
itemized in Table 6. The table includes a material description, use, location, approximate quantity of
material stored, containment methods, and likelihood of exposure to stormwater. Figure 2 shows
the location of the material on the site.
Brown— Caldwetl
3-3
SWPPP Final Version 04 18 17
City of Oshkosh: Field Operations Facility SWPPP
Section 3
3.5 Vehicle Inventory
Vehicles and equipment stored and serviced at this facility with potential to contribute to stormwater
pollution are itemized in Table 7. All vehicles are stored inside the main building (Building 1 on
Figure 3).
Brown— Caldwell
3-4
SWPPP Final Version 04 18 17
Table 6. Materials Inventory
Material
Map ID# (Fig. 2) and
Approximate
Containment
Likelihood of Exposure to
Material Use
Description
Location
Quantity
Methods
Stormwater
Salt
De-icing roads
7 Salt Shed
4,000 Tons
Stored inside
Most likely in winter months,
dome
when loadingtrucks
Liquid De-icers
De-icing roads
7 Salt Shed
10,000 Gal.
Closed storage
Most likely in winter months,
containers
when loadingtrucks
Underground
Minimal - During fueling and
Diesel Fuel
Fuel for city vehicles
10 Fueling Area
20,000 Gal.
storage tank
tank emptying, Area covered by
awning
Unleaded
Underground
Minimal - During fueling and
Gasoline
Fuel for city vehicles
10 Fueling Area
20,000 Gal.
storage tank
tank emptying, Area covered by
Awning
Municipal Vehicle /
5 Oil Room
Waste Oil
Equipment
(within Main Building)
600 Gal.
Storage tank
Minimal - Duringtank emptying
maintenance
16 Shed
Minimal - 2 tanks under roof
Waste Oil
Public Drop-off
350 Gal.
Storagetank
and within secondary
(east of 3rd Ave. entrance)
containment.
Vehicle/ Equipment
5 Oil Room
Bulk Oil
825 Gal.
Stored inside
Minimal -stored inside
maintenance
(within Main Building)
Transmission
Vehicle/ Equipment
5 Oil Room
Fluid
maintenance
(within Main Building)
275 Gal.
Stored inside
Minimal -stored inside
Vehicle/ Equipment
5 Oil Room
Anti -freeze
275 Gal.
Stored inside
Minimal -stored inside
maintenance
(within Main Building)
Vehicle/ Equipment
5 Oil Room
Hydraulic Oil
550 Gal.
Stored inside
Minimal -stored inside
maintenance
(within Main Building)
Auto Wash
6 Vehicle Wash
1-3 55 Gal
Soap
Vehicle Washing
(within Main Building)
55 -165 Gal
Drums
Minimal -stored inside
Cold Mix
Pavement Patching
11 Water Utility Storage
155 tons
3 -sided bin
Potential- stored in bins, no
Asphalt
roof
Stone
Pipe Bedding
11 Water Utility Storage
90 tons
3 -sided bin
Potential - stored in bins, no
roof
Cold Mix
Pavement Patching
14 Covered Bin Storage
5 10 cu . yds.
Bin/Roof
Minimal - stored in bin under
Asphalt
#2
roof
Topsoil
Restoration of Grass
14 Covered Bin Storage
5 -10 cu. yds.
Bin/Roof
Minimal - stored in bin under
Areas
#2
roof
Stone
Pipe Bedding
14 Covered Bin Storage
5 - 20 cu. yds.
Bin/Roof
Minimal - stored in bin under
#2
roof
Asphalt
Road Shoulder
14 Covered Bin Storage
5 10 cu. yds.
Bin/Roof
Minimal - stored in bin under
Millings
Repair
#2
roof
3.5 Vehicle Inventory
Vehicles and equipment stored and serviced at this facility with potential to contribute to stormwater
pollution are itemized in Table 7. All vehicles are stored inside the main building (Building 1 on
Figure 3).
Brown— Caldwell
3-4
SWPPP Final Version 04 18 17
City of Oshkosh: Field Operations Facility SWPPP
* 1 Elgin Pelican mechanical; 4 Elgin Whirlwind vacuum
3.6 Historical Leaks and Spills
Section 3
Based on information provided by City of Oshkosh, no reportable leaks or spills have occurred at the
facility within the last three years. From inspection during the site visit, no evidence was found of
any leaks or spills discharging off-site.
3.7 Non-Stormwater Runoff Discharges
There are no known non-stormwater runoff discharges at the site.
Brown— Caldwell
3-5
SWPPP Final Version 04 18 17
Table 7. Vehicle
Inventory
Vehicle/Equipment Type
Number of
Pieces
Vehicle/Equipment Type
Number of
Pieces
Brush Cutter
4
Pickup truck
15
Rotary Mower
3
Platform truck
4
Backhoe - wheeled
1
Pressure washer
2
Backhoe - tracked
2
Pump
7
Vacuum truck
3
Rear boom mower
1
Cement mixer
1
Recycling truck
4
Compressor
5
Refuse truck
9
Concrete hand saw
4
Roller
3
Concrete saw - walk behind
2
Rotary snowblower
2
Crack sealer
1
Semi -tractor
2
Dump truck - single axle
3
Snowthrower
1
Dump truck - tandem axle
14
Street Sweepers *
5
Forklift
1
Tamper
2
Generator
3
Tractor
2
Grader
3
Trailer
17
Loader - skidsteer
2
Wood Chipper
2
Loader - wheeled
6
Area Truck Salters
7
Mower
5
Multi-purpose Tractor
2
* 1 Elgin Pelican mechanical; 4 Elgin Whirlwind vacuum
3.6 Historical Leaks and Spills
Section 3
Based on information provided by City of Oshkosh, no reportable leaks or spills have occurred at the
facility within the last three years. From inspection during the site visit, no evidence was found of
any leaks or spills discharging off-site.
3.7 Non-Stormwater Runoff Discharges
There are no known non-stormwater runoff discharges at the site.
Brown— Caldwell
3-5
SWPPP Final Version 04 18 17
Section 4
Best Management Practices
4.1 Objective
This section describes structural and non-structural Best Management Practices (BMPs) at the
Facility. The primary objective of the BMPs is to prevent stormwater from coming into contact with
source materials and/or to treat stormwater pollution before discharging from the site. Wherever
possible, sources will be removed or covered to eliminate stormwater contamination.
This section includes measures and controls taken to promote good housekeeping, runoff
management, and preventive maintenance. Spill prevention techniques, inspections, employee
training, and record keeping are addressed in Section 5 of this SWPPP.
4.2 Management Measures and Controls
Activities and materials present at the Facility that may impact stormwater quality are discussed in
Section 3.3.
Source control is the most effective way to reduce pollutants in stormwater. Measures such as
removing unnecessary materials, storing materials inside, and establishing a delivery schedule that
minimizes on site storage have been implemented wherever possible. A summary of existing and
proposed control measures follows.
4.2.1 Existing Management Practices
Existing Stormwater Management Practices that exist at the Facility and will be maintained to
perform their intended function include:
Structural Measures:
E1. There are three biofilters on the site. The three biofilters treat runoff from approximately 4.93
acres. The biofilters will be maintained and inspected for proper function as described in
Section 5.2 of this document.
E2. There is an underground detention basin that treats approximately 2.85 acres of the site. The
basins will be maintained and inspected for proper function as described in Section 5.2 of this
document
E3. There are four inlets with 18" sumps located along Idaho Street that receive direct runoff from
Drainage Basins 6,7,8,9, and 12. These inlets also receive indirect runoff (via a storm sewer)
from Building 2 (Cold Storage) and portions of Drainage Basin 5. The inlets will be maintained
and inspected for proper function as described in Section 5.2 of this document
Non Structural Measures:
E4. General Site Housekeeping: Keep the outdoor storage areas in an orderly condition.
Continually practice good housekeeping measures such as; removing un -used equipment,
disposing of empty barrels, regularly emptying dumpsters, covering outdoor bulk storage areas,
prompt clean-up of spills, and cleaning of equipment and materials prior to outdoor storage.
E5. Salt Shed Area: During truck loading operations, spilled salt is removed daily and either placed
back inside the dome (if dry) or used elsewhere on the facility when needed. Salt is picked up
with brooms, shovels and/or front-end loader. Spilled salt is not washed away.
Brawn -o Caldwell
4-1
SWPPP Final Version 04 18 17
City of Oshkosh: Field Operations Facility SWPPP
Section 4
E6. Nearly all material delivered to the facility is unloaded inside Building 1 or Building 2. Outside
loading docks are not utilized at the site.
E7. Oil and other maintenance fluids are delivered to the site via a pump system. The couplings
for the delivery system are within a covered box. Sorbent pads are kept within the box to
collect minor drips or spills that occur during delivery.
E8. All city -owned vehicles on the site are stored inside, eliminating the risk that leaks or
contaminants will be exposed to rainfall. All floor drains in vehicle storage areas are
connected to the sanitary system.
E9. Cleaning solvents, oils, lubricants, paint, gas cans, and similar fluids are stored inside Building
1. All floor drains are connected to a sanitary system.
E10. The amount of hazardous liquids and materials kept on -hand are minimized. Products are
ordered on an "as needed" basis.
E11. Hazardous liquids and materials that are ready for disposal are kept in sealed containers
inside Building 1, which contains the materials, and eliminates contact with stormwater.
E12. The diesel fuel and gasoline tanks are located underground within containment structures,
eliminating leaks and exposure to storm water.
E13. The vehicle fueling station is covered by an awning reducing the likelihood of leaks or spills
being exposed to storm water. There is also an emergency shut off located at the fence along
Idaho Street.
E14. There is a spill containment kit located at the vehicle fueling area.
E15. Vehicles and equipment are kept in good working order to minimize leaks. All vehicle
maintenance, including washing, occurs within Building 1
E16. All floor drains in the Main Building and Cold Storage are connected to sanitary sewers. There
are no floor drains in any other building.
E17. Oil dry absorbent material is supplied inside at repair areas, and vehicle parking areas where
leaks and spills might occur. Used oil dry material is swept up and disposed of in dumpster.
4.2.2 Proposed Management Practices
Implementation of the following additional BMPs is recommended to further prevent stormwater
contamination:
P1. Continue maintaining existing structural and non-structural management practices listed
above.
P2. Fueling Area: The existing spill control station only contains oil -dry material. The station will
have a rubber mat and oil booms included to prevent spilled fuel from entering adjacent storm
inlets.
P3. Training: Implement an employee training program (Refer to Section 5.7).
P4. Inspections: Conduct routine inspections and record findings as described in Section 5.
4.3 Management Practices Implementation
The existing and proposed structural and non-structural BMPs will continue to be followed and
maintained. If future changes in site activities require the implementation of additional BMPs, this
Plan will be modified accordingly and the BMPs will be implemented in a timely manner. The
Brown— Caldwell
4-2
SWPPP Final Version 04 18 17
City of Oshkosh: Field Operations Facility SWPPP
Section 4
proposed management practices identified above will be implemented based on the schedule
presented in Section 5.9.
4.4 Prohibited Activities
The following are activities that are currently prohibited at the site:
• Cleaning spills using techniques such as flushing with water is prohibited. Instead, spills
should be cleaned up by using absorbent material or sweeping.
• Fueling area is restricted for use by authorized governmental employees only.
• Washing of vehicles or equipment outside of designated wash bays.
• Storing unused equipment, barrels, product containers, batteries, fuel cans, etc. in
uncovered, outside locations.
4.5 Residual Pollutants Expected to Remain in Stormwater
Based on current operations at the subject site and the anticipated implementation of the BMPs, low
concentrations of residual pollutants that are expected to remain in stormwater include:
• Oil and grease from employee/visitor parking areas and vehicle fueling area,
• Total suspended solids (TSS) and salt from the salt shed area, and
• TSS from outdoor material storage
Implementation of this SWPPP and the BMPs is believed to be adequate to minimize the residual
pollutants in the facility's stormwater runoff.
Brown— Caldwetl
4-3
SWPPP Final Version 04 18 17
Section 5
Inspections and Record Keeping
Inspections, as described in this section, should be conducted and documented to ensure that the
provisions of this SWPPP are being followed and to identify areas needing improvement. Deficiencies
revealed during inspection procedures that require further action, such as purchasing or replacing
equipment, should be communicated to the SWPPP team coordinator. Blank forms are in Appendix B
and completed forms may be placed in Appendix C. Inspection records should be retained for a
period of at least 5 years.
5.1 Quarterly Visual Stormwater Outfall Inspections
The storm sewer outfalls at the site should be inspected at least once every three months.
Whenever possible, the inspections should be conducted at the beginning of a rainfall event. The
storm sewer outfalls should be inspected at the manhole nearest the property boundary. All
observations should be made from the surface. NO MANHOLE ENTRY SHOULD BE ATTEMPTED.
The stormwater surface flow paths over the impervious surfaces should also be inspected during
quarterly visual stormwater inspections.
Each inspection must be documented (see Appendix B for forms) and include observations of color,
odor, clarity, floating solids, trash, foam, oil sheen, or other obvious indicators of stormwater
pollution. Staining of surface flow paths should also be noted and source control management
measures implemented.
If the quarterly inspections are conducted during a non -runoff period, there should be no flow
observed at the inspection point. (NOTE: All site outfalls are at an elevation lower than the Lake
Winnebago summer target maximum water level. This means that standing backwater from the lake
may be observed at the outfalls, however there should be no movement of water from the Field
Operations site into the manholes). If flow is observed, the source of the water should be
determined and removed if necessary. An example of acceptable dry -weather flow would be
groundwater discharge.
During the quarterly inspections, the drainage areas should also be checked for material exposed to
stormwater that should be removed, or stored under shelter.
5.2 Semi -Annual Structural BMP Inspection
At a minimum the structural BMPs should be visually inspected in May and September of each year
as follows:
Biofilters and Grass Swale: Visually inspect for:
• Ponded water after end of rain events for more than 24 hours
• Rills, gullies, or other signs of erosion around the sloped perimeter of the practice.
• Weeds/ invasive vegetation within the Biofilters.
• Shifting, cracked or displaced structures (outlets, cleanouts, etc.)
• Debris / trash collected in the biofilters or blocking the overflow outlet(s)
Brown— Caldwell
5-1
SWPPP Final Version 04 18 17
City of Oshkosh: Field Operations Facility SWPPP
Under round Detention: Document and visually inspect (through surface manholes) for:
• Buildup of sediment in the sumps (sediment depth may be estimated with a metal or wooden
rod).
• From the surface access points inspect odor, floating solids, trash, foam, oil sheen.
• If sediment depth exceeds 50% of the standing water depth (standing water depth from CMP
bottom is 3.0') the sediment should be removed.
• At a minimum floating trash should be removed on an annual basis.
• NO MANHOLE ENTRY SHOULD BE ATTEMPTED.
Storm Inlets (along Idaho Street): Document and visually inspect (through surface manholes) for:
• Buildup of sediment in the sumps (sediment depth may be estimated with a metal or wooden
rod).
• If sediment depth exceeds 50% of the standing water depth (standing water depth from CMP
bottom is 15) the sediment should be removed. (Note: The City annually cleans all inlet
sumps. Sediment buildup exceeding 50% of standing water depth is not anticipated,
however extreme rain patterns could result in the need for more frequent sediment removal
on occasion.)
• From the surface inspect odor, floating solids, trash, foam, oil sheen.
• NO ENTRY SHOULD BE ATTEMPTED.
5.3 Annual Site Review and Inspection
A comprehensive annual site compliance review and inspection of the facility and property should be
performed. The Annual Review should be conducted by the team identified in Table 1 plus the
Director of Public Works. This inspection will be used to verify that the site drainage conditions and
potential pollutant sources identified in the SWPPP remain accurate and that the BMPs prescribed in
the SWPPP are being implemented and functional. The findings from the annual inspection should
be documented. An annual inspection checklist is included in Appendix B. Based on the findings
from these inspections, this document may be revised.
5.4 Spill Response and Documentation
Should a spill occur on the property that could be exposed to stormwater, the spill must be cleaned
up immediately. If the spill is reportable, it must be reported to the City of Oshkosh illicit discharge
coordinator (John Ferris, Civil Engineering Supervisor, 920-236-5065), the WDNR (1-800-943-0003),
and the Oshkosh Fire Department (920-236-5240). A record should be kept of all spills and should
include the following:
• Date and time of the incident
• Substance spilled
• Volume spilled
• Weather conditions
• Duration of the incident
• Cause of the incident
• Response procedures
• Parties notified
• Amount of spilled material recovered and recovery method
Brown— Caldwell
5-2
SWPPP Final Version 04 18 17
City of Oshkosh: Field Operations Facility SWPPP
A spill documentation form is included in Appendix B and can be used to record the pertinent data if
a spill occurs. A brief WDNR fact sheet providing definition for a reportable spill is included in
Appendix D.
5.5 Annual Stormwater Sampling and Testing
The City of Oshkosh is not required to perform physical, chemical, or biological analysis of
stormwater at this facility.
5.6 SWPPP Updates or Revisions
The City of Oshkosh must amend this SWPPP whenever there is a change in the pollution prevention
team personnel, design, construction, or operation that may impact the potential for pollutants to
come into contact with stormwater; or if the SWPPP proves to be ineffective in controlling the
discharge of pollutants.
5.7 Employee Training Requirements
To effectively implement this document, employees must be adequately trained. The goal of training
programs is to teach personnel the components and goals of the Pollution Prevention Plan. Properly
trained personnel can recognize situations that could contaminate stormwater and can respond
safely and effectively to an accident. The employee -training program should cover topics such as:
• Spill prevention and response
• Good housekeeping
• Material management practices
All new employees will be trained upon hiring. All employees will receive refresher training once
every two years. Training effectiveness should be evaluated to ensure information has been
effectively communicated. Arrangements for the employee training should be made by the Field
Operations Manager. An employee training record is included in Appendix B.
5.8 Preventive Maintenance
Any regularly scheduled maintenance required of elements of the stormwater management system
should be performed as is recommended by operation and maintenance plans for those stormwater
management aspects.
5.9 Implementation Schedule
The aspects of this SWPPP will be implemented using the following schedule.
1. Completion of SWPPP: April, 2017
2. Implementation of Site Inspections: Spring 2017
3. Implementation of Proposed Best Management Practices: Spring/Summer 2017
P1. Continue maintaining existing structural and non-structural practices - Ongoing
P2. Fueling Area - add recommended equipment by Summer 2017
P3. Training - Ongoing
P4. Inspections - Initiate inspection schedule Spring, 2017
Brown— Caldwetl
5-3
SWPPP Final Version 04 18 17
City of Oshkosh: Field Operations Facility SWPPP
Appendix A: Field Operations Facility Emergency
Contact 2017 Rotation List
Brawn— Caldwell
A-1
SWPPP Final Version 04 18 17
Jan 9_Thru Jan 15. 2017
Tr�) i l, --
Jan 16 Thru Jan 22
i'Y Frei!
Jan 23 Thru Jan 29
Kevin
Jan 30 Thru Feb 5
Bob
Feb 6 Thru Feb 12
Todd
Feb 13 Thru Feb 19
Feb 20 Thru Feb 26
Andy
Feb 27 Thru Mar 5
Kevin
Mar 6 Thru Mar 12
Bob
Mar 13 Thru Mar 19
Todd
Mar 20 Thru Mai' 26
Mar 27 Thru April 2
April 3 thru IA rp it 9
Devin
f3pjji 10 _..T,.h_it1...AqEd__' 2
Bob
April 17 Thru April 23
Todd
Rotation List
Phone 4 379-350£
April 24 Thru April 30
May 1 Thru May 7
May 8 Thru May 14
Kevin
Ma 15 Thru Ma 21
Todd
1. V
May 30 Thru June 4
Bob
June 5 Thru June 11
Andy
June 12 Thru June 18
Kevin
June 19 Thru June 25
Todd
June 26 °Th[U ,duly 2
,M 3TVatJolvs)
Bob
July 10 Thru July 16
Ftp-�r1gt
July '17 Thru July 23
Devin
July 24 Thru July 30
Todd
July 31 Thru August 6
Aug_ 7_Thru _August 13
Bob
Aug14 Thru Au 20
f�i'kr$ti
Aug 21 Thru Aug 27
Kevin
t.it R�3 'If-I)f i � ti 4
Todd
Sept_5 Thru Sept 10
Sob
Sept 1.1_Thru Sept 17
Sept 18 Thru _Sept 24
Andy
Sept _25_Thru Oct 1
Kevin
Oct 2 Thru Oct 8
o(I(A
Oct -9 Thru Oct 16
chi
Oct 16 Thru Oct 22
,ED'S
Oct 23 Thru Oct 29
Li. q tl y
Oct 30 Thru Nov 5
Kevin
Nov 6 thru Nov 12
Todd
Nov 13 Thru Nov 19
8ol:)
Revised
'11/22/2016
M v.,90 .'I"hru Nov 26
Nov 27ThruDec 3
Dec 4 Thru Dec 10
Kevin
Dec 10 Thru Dec 17
To,d<1
i `i TIt s 0 e,(..2 6
Rob
A,{10y
Jan 2 Thru Jan 7 20,18
Jan 8 Thru Jan 14
Kevin
City of Oshkosh: Field Operations Facility SWPPP
Appendix B: Blank Checklists and Forms
Brawn— Caldwell
B-1
SWPPP Final Version 04 18 17
City of Oshkosh: Field Operations Facility SW PPP
QUARTERLY VISUAL STORMWATER INSPECTION
Instructions: Quarterly inspections are conducted to document SWPPP is followed, and to identify areas of improvement. Follow the schedule
and procedure described in Section 5.1. Completed forms should be placed in Appendix B, and kept for at least 5 years.
Date/Time:
Inspector(s):
Weather: (current and date/time end of last rain)
INSPECTION TASKS
Outfall A
Outfall B
Outfall C
Outfall D
Outfall E
Outfall F
& OBSERVATIONS
(BLDG 1F, Area 3)
(Area 1-2)
(BLDG 1D, 1E, Area 4
(BLDG 1A, 1139 1C9
(Area 5, 10, 11)
(BLDG 2, Area 5, 69
1G)
79 89 99 12)
At Outfall: Signs of oil
sheen, foam, sludge,
odor, trash, etc.?
Is there flow? (Y/N):
Drainage Area: Signs of
contaminants at
storage locations, litter
or trash on ground?
Presence of equipment,
containers, etc.
Drainage Area surface
flow paths: Any
staining, waste or bulk
storage in flow path?
Other observations?
Brown Aho Caldwell
P:AOshkosh City of\160204 Oshkosh Field OpsSWPPP\SWPPP\Final DeliverableV01 Qtrly Visual Insp Field Ops Final.doe
City of Oshkosh: Field Operations Facility SWPPP
SEMI-ANNUAL STRUCTURAL BMP INSPECTION
Instructions: Semi-annual inspections are conducted to document that structural BMPs are
functional property and providing the stormwater quality treatment as designed.
Completed forms should be placed in Appendix C, and kept for at least 5 years.
These forms shall be reviewed at the annual Site Inspection and Review Meeting.
Date/Time:
Inspector(s):
Weather: (current and date/time end of last rain)
Biofilter 1-2
(note and comment on any of the following observations)
Condition
Notes / Comments
1. Side slope vegetated
cover
2.Side slopes gullies/rills
3.Infiltration bed
vegetation condition
4.Trash / debris
5.Outlet structure
condition (1)
6.Clean-outs condition (1)
7.Water ponding > 24 hrs.
8.Other Comments
(1) Look for structural cracks, shifting or soil sunk around base. Also look inside structures for standing water, oil
sheen, debris, odors.
Biofilter 3
(note and comment on any of the following observations)
Condition
Notes / Comments
1. Side slope vegetated
cover
2.Side slopes gullies/rills
3.Infiltration bed
vegetation condition
4.Trash / debris
5.Outlet structure
condition (1)
6.Clean-outs condition (1)
7.Water ponding > 24 hrs.
8.Other Comments
(1) Look for structural cracks, shifting or soil sunk around base. Also look inside structures for standing water, oil
sheen, debris, odors.
Brown -D Caldwell
P:\Oshkosh City of\150204 Oshkosh Field Ops SWPPP\SWPPP\Final Deliverable\02 Sturctural BMP Inspection Form.doc Page 1
City of Oshkosh: Field Operations Facility SWPPP
SEMI-ANNUAL STRUCTURAL BMP INSPECTION
Biofilter 4
(note and comment on any of the following observations)
Condition
Notes / Comments
1. Side slope vegetated
cover
2.Side slopes gullies/rills
3.Infiltration bed
vegetation condition
4.Trash / debris
5.Outlet structure
condition (1)
6.Clean-outs condition (1)
7.Water ponding > 24 hrs.
8.Other Comments
(1) Look for structural cracks, shifting or soil sunk around base. Also look inside structures for standing water, oil sheen, debris,
odors.
Grass Swale
(note and comment on any of the following observations)
Condition
Notes / Comments
1.Vegetated cover
2. Gullies/rills
3.Trash / debris
4.Outlet structure
condition (1)
5.Water ponding > 24 hrs.
6.Other Comments
(1) Look for structural cracks, shifting or soil sunk around base. Also look for standing water, oil sheen, debris, odors.
Underground Treatment Structure
(note and comment on any of the following observations)
Condition
Notes / Comments
1.Surface slumping in
pavement at location
2.Observe at each riser
and outlet manholes
• Odor, oil sheen,
floating trash
• Measure standing
water depth
• Measure sediment
depth
3. Record date of sediment
removal.
4.Other Comments
* NOTE: DO NOT ENTER MANHOLES — OBSERVE FROM SURFACE
Brown Caldwell
P:\Oshkosh City of\150204 Oshkosh Field Ops SWPPP\SWPPP\Final Deliverable\02 Sturctural BMP Inspection Form.doc Page 2
City of Oshkosh: Field Operations Facility SWPPP
SEMI-ANNUAL STRUCTURAL BMP INSPECTION
Storm Inlets (along Idaho Street)
(note and comment on any of the following observations)
Condition
Notes / Comments
1. Observe at each inlet
• Odor, oil sheen,
floating trash
• Measure standing
water depth
• Measure sediment
depth
2. Record date of sediment
removal.
3.Other Comments
* NOTE: DO NOT ENTER INLETS— OBSERVE FROM SURFACE
Brown -D Caldwell
P:\Oshkosh City of\150204 Oshkosh Field Ops SWPPP\SWPPP\Final Deliverable\02 Sturctural BMP Inspection Form.doc Page 3
City of Oshkosh: Field Operations Facility SWPPP
ANNUAL SITE REVIEW AND INSPECTION CHECKLIST
An annual inspection is performed to evaluate the effectiveness of controlling stormwater
contamination and to identify any additional measures that can be feasibly implemented. The
Stormwater Pollution Prevention Plan should be amended to reflect any changes. It is recommended
the Annual Inspection be conducted with at least the following City staff:
• Director of Public Works • Stormwater Team Listed on Table 1
Date of Review:
Staff Present at Review:
CHECKLIST FOR ANNUAL INSPECTION:
1. Review Past Year's Quarterly Inspection Reports and BMP Inspection Reports
• Verify that all inspections were conducted and documented.
• Verify that identified stormwater concerns were addressed and/or corrected.
• Schedule or confirm staff training needs.
• Confirm team assignments and responsibilities.
2. Inspect site drainage conditions. Things to look for include:
• Inspect the site for possible bare soil / erosion problems.
• Determine if drainage off the property has changed. Are there any new areas of ponding or
flow?
• Are there any unusual stains around storage areas or along overland stormwater flow paths?
Notes:
3. Check for potential pollution sources. Sources may include the following:
• Inspect the outdoor storage areas. Is there any indication of exposed materials causing
pollution in stormwater runoff?
• Inspect the area near the dumpsters for material not covered.
• If there is any standing water at the time of inspection, are there sheens, sludge, foam, or
rust precipitations?
• Inspect all areas of the site for signs of spills (oil, grease, etc.) or other contaminants.
Notes:
4. Perform the following preventive maintenance activities:
• Inspect the drain opening located in the bottom of the dumpster to verify that it is plugged.
• Check the spill control stations contents.
Brown... Caldwell
Page 1
P:\Oshkosh City of\150204 Oshkosh Field Ops SWPPP\SWPPP\Final Deliverable\03 Ann Site Insp Chklst Field Ops Final.doc
City of Oshkosh: Field Operations Facility SWPPP
Notes:
5. Review the Structural and Non -Structural Best Management Practices that are in place.
• Are the Best Management Practices being followed?
• Are the Best Management Practices effective?
• Are there any additional management practices that should be implemented?
Notes:
6. Other observations - take note of anything else at the Property that may be of significance to
the SWPPP.
Notes:
7. Outline the revisions and amendments that need to be made to the SWPPP.
This annual inspection certification is to indicate the City's commitment and continual support for
this Stormwater Pollution Prevention Plan. An annual site inspection has been conducted and based
on the findings from the inspection; the SWPPP for this facility will be amended accordingly.
Signed:
Printed Name:
Title: Date:
Facility: City of Oshkosh
Public Works Field Operations Facility
639 Witzel Avenue
Oshkosh, WI 54902
Brown... Caldwell
Page 2
P:\Oshkosh City of\150204 Oshkosh Field Ops SWPPP\SWPPP\Final Deliverable\03 Ann Site Insp Chklst Field Ops Final.doc
City of Oshkosh: Field Operations Facility SWPPP
SPILL DOCUMENTATION FORM
Instructions: Facilities in the City of Oshkosh with a SWPPP must document all significant spills or
leaks that occur at the site. The following format can be followed to document the necessary
information.
Record below all significant spills and / or leaks of pollutants that may be exposed to stormwater.
Date:
Time:
Substance and Volume spilled:
Weather conditions:
Duration of the incident:
Cause of the incident:
Response procedures:
Parties notified:
Location of spill (attach map or drawing):
Brown ago Caldwell
P:\Oshkosh City of\150204 Oshkosh Field Ops SWPPP\SWPPP\Final Deliverable\04 Spill Document Form Field Ops Final.doc
City of Oshkosh: Field Operations Facility SWPPP
Methods used to contain spill:
Amount of spilled material recovered:
Disposition of recovered spilled material. Attach disposal receipts if appropriate.
Potential for environmental impact:
Brown ago Caldwell
P:\Oshkosh City of\150204 Oshkosh Field Ops SWPPP\SWPPP\Final Deliverable\04 Spill Document Form Field Ops Final.doc
City of Oshkosh: Field Operations Facility SW PPP
Training Topic(s):
Description of Training Materials:
EMPLOYEE TRAINING RECORD
Date of Training:
Attendee Name
Signature
Attendee Name
Signature
1
13
2
14
3
15
4
16
5
17
6
18
7
19
8
20
9
21
10
22
11
23
12
24
Trainer Name (Printed) Trainer Signature Trainer Company Date
Attach Training Materials With This Sheet
Brown—Caldwell
P:AOshkosh Cityof\160204 Oshkosh Field OpsSWPPP\SWPPP\Final DeliverableV06 Empl Training Record Field Ops Final.doc
City of Oshkosh: Field Operations Facility SWPPP
Appendix C: Completed Checklists and Forms
Brawn— Caldwell
C-1
SWPPP Final Version 04 18 17
City of Oshkosh: Field Operations Facility SWPPP
Appendix D: WDNR Fact Sheet Defining Reportable
Spills
Brawn— Caldwell
D-1
SWPPP Final Version 04 18 17
Wisconsin DNR - Hazardous Substance Spills
Immediate Reporting Required for Hazardous Substance Spills
If you are aware of a hazardous substance spill notify the Department
of Natural Resources (DNR). State law requires the IMMEDIATE reporti
of hazardous substance spills and other discharges to the environment.
CALL 500-943-0003
TO REPORT SPILLS
Use DNR Form 4400-225 to report other
hazardous substance discharges
Other hazardous substance discharges, including historical contamination and contamination caused by an
ongoing long-term release, discovered during an environmental assessment or laboratory analysis of soil,
sediment, groundwater or vapor samples, should be reported to DNR by filling out and submitting DNR
Form 4400-225, "Notification for Hazardous Substance Discharge (Non -Emergency Only)," which is is
available at http://dnr.wi.gov/files/pdf/forms/4400/4400-225.pdf.
✓ Report hazardous substance discharges as soon as visual or olfactory evidence confirms a
discharge or laboratory data is available to document a discharge. Do not wait to complete
a Phase II environmental assessment, or other similar report, to notify DNR.
Reporting is everyone's responsibility
Individuals and entities that cause a hazardous substance spill or discharge to the environment are required
by state law to notify DNR immediately - as soon as the spill or discharge is identified. Individuals and
entities that own or control property where the spill or discharge occurred must report the discharge
immediately if it is not reported by the person or entity that caused the discharge.
For public health and safety, DNR encourages everyone to report known hazardous substance discharges.
Reporting a spill or other discharge, in itself, does not make a person or entity liable for the contamination.
Proper spill containment, cleanup, and disposal is always required
Every person/entity (including lenders and local governments) that causes a hazardous substance discharge, or
owns or controls property at which a discharge occurred, must comply with the response action requirements in
Wis. Admin. Chs. NR 700 to 754. No spill or discharge is exempt from the duty to properly contain, clean up and
dispose of the substance and associated contaminated media, such as soil, water and other affected materials.
Publication Number: DNR -RR -560 dnr.wi.gov, search "spills"
Spill reporting exemptions
All spills must be cleaned up, but it is generally not necessary to report recent spills that are:
• less than 1 gallon of gasoline
• less than 5 gallons of any petroleum product other than gasoline
• any amount of gasoline or other petroleum product that is completely contained on an impervious surface
• individual discharges authorized by a permit or program approved under Wis. Stats. Chs. 289 - 299
• less than 25 gallons of liquid fertilizer
• less than 250 pounds of dry fertilizer
• pesticides that would cover less than 1 acre of land if applied according to label instructions
* NOTE: Reporting is required if the ongoing, long-term release or application of a permitted pesticide, fertilizer or other substance
accumulates to levels that exceed current health or safety standards.
• less than the federal reportable quantities listed in 40 C.F.R. §§ 117 or 302
* NOTE: U.S. EPA (federal) spill reporting requirements are outlined on the internet at https://www.epa.gov/emergency-response/when-
are-you-required-report-oil-spill-and-hazardous-substance-release.
Spill reporting exemptions do not apply (and reporting is required) when:
• the spilled substance has not evaporated or been cleaned up in accordance with Wis. Admin. chs. NR 700 - 754
• the spilled substance is a potential fire, explosion or safety hazard
• the spilled substance causes, or threatens to cause, chronic or acute human health concerns
* NOTE: If you are unsure about potential human health effects, consult with local or state health officials.
• the spilled substance adversely impacts, or threatens to impact, the air, lands or waters of the state (as either a
single discharge or when accumulated with past discharges) - even if the degree of the impact has not yet been
thoroughly evaluated
* NOTE: If the substance causes sheen on surface water, has entered or is on the verge of entering the waters of the state, DNR will
consider the spilled substance a threat to impact, or to have adversely impacted, waters of the state and reporting is required.
Terms, definitions, statutes and rules
Hazardous substance —Any substance that can cause harm to human health and safety, or the environment,
because of where it is spilled, the amount spilled, its toxicity or its concentration. Even common products such as
milk, butter, pickle juice, corn, beer, etc., may be considered a hazardous substance if discharged to a sensitive area.
Discharge — Spilling, leaking, pumping, pouring, emitting, emptying, dumping, etc., to land, air or water.
Spill — A discharge that is typically a one-time event or occurrence, and usually inadvertent.
Wis. Stat. § 292.11(2) and Wis. Admin. § NR 706.05 — Require individuals and entities that possess or control
a hazardous substance, or that cause the discharge of a hazardous substance to the environment, to notify DNR
immediately about the discharge.
Wis. Stat. § 292.99 — Authorizes penalties up to $5,000 for each violation of the notification requirement.
Consult Wis. Stat. Ch. 292 and Wis. Admin. §§ 700 - 754, and http://dnr.wi.gov/topic/Spills/ for further information on
hazardous substance spill and discharge reporting, investigation and cleanup.
Regional Spill Coordinators - DNR contacts
Northeast: Ted Amman (608) 275-3332 South Central: Mike Schmoller (608) 275-3303
Northern: John Sager (715) 392-7822 West Central: Tom Kendzierski (715) 839-1604
Southeast: Scott Ferguson (414) 263-8685 Spill Team Leader: John Sager (715) 392-7822
This document is intended solely as guidance and does not contain any mandatory requirements except where requirements found in statute or administrative rule are referenced. This guidance does not establish or affect
legal rights or obligations and is not finally determinative of any of the issues addressed. This guidance does not create any rights enforceable by any party in litigation with the State of Wisconsin or the Department of Natural
Resources. Any regulatory decisions made by the Department of Natural Resources in any matter addressed by this guidance will be made by applying the governing statutes and administrative rules to the relevant facts.
City of Oshkosh: Field Operations Facility SWPPP
Appendix E: Figures
Brawn— Caldwell
E-1
SWPPP Final Version 04 18 17
LAKE BUTTE DES MORTS
Legend
SWPPP Site Location
Streets 2015 Inventory
Municipal Boundary
I _ -
LAKE WINNEBAGO
a
Figure 1
Site Location Map
Field Operations Facility
City of Oshkosh,Wl
N 0 3,000 6,000
A Feet
Brown AND •
Caldwell ' Oshkosh
7
•
Legend
ndary
AfeaS
9 C - SYorege#t
- BnOergmund Detentron
Lan —pcV / Open Space
—.—B—
10 Fueling S.—
FieltlOperaliotuSt.-m —System
Dn—'
11 water u Mry Storage
■ °aa ^
1 Aaministraave OBKes
12 Storm B Santry St—t—Storage
• Storm Manhole
2 aintenance FacA�es
13 isce nexus Storage Ama
o�m exer
City MM Storm Sewer system
3 Garage
4 cep --Steps
14 C.— Bin Storage N2
15 ram waste Dmp—
Cm'�nkt
5 Oil Room
16 —k waste 011[)op
• Cm'Mannole
B e ice a h—
17 Scrap Metal Dampsters
�Slo�m Sexer
7 Salt—
8 Com Storage -1-g
18 Empmyee& V.- Pmking
C C F
WITZEL AVE
LL
3
Building 1
2
4
1
15
1
W 3RD AYES
DISCHARGE TO
`rte ■ • FOX RIVER
1
is
s �1
5 X9'9
A�
F�
Q �
l Figure 2. Site Plan
Field Operations Facility SWPPP
City of Oshkosh, WI
N 0 50 100
Aeet
Brown AND o,
Caldwell ' LOshkosh
®® ® • • ® ® BIOFILTER 4
OUTFALL C
WITZEL AVE
OFFSITEAREA2 _ BIOFILTER 3
AREA4 f� •
FSITE AREA ® •
p BLDG 2 `
BLDG 1D BLDG 1E OUTFALLA
AREA61 •
A
�\`" OUTFALL B
OUTFALL F *_--ARFA7 UBLDG 1C NDERGROUND BLDG IF i
—� DETENTION •
•AREA 5
8 �► BLDG 1A
BLDG 1G •
11
AREA9 ��JJ
• ® BLDG 1B 9%A
ARA 12 `
• • i �AREA 1-2 • , 1 � M
AREA OUTFACED —�
• 1 BIOFILTER 1-2 €
AREA 11
GRASS S -LE
Legend
Site Bountlary Drainage Area to OutfallA
OFFSI
QDrainage Areas DminageArea to OutfallB
City M S4 Storm Sewer System D.—g. Area m Outfall C - W3RDAVE - Figure 3. Drainage Basins
• Gaylnlet OUTFALL E c Field Operations Facility
DamageArea to owran° City Of Oshkosh, WI
• City Manhole Drainage Area to Outfall E G
N 0 50 100
— storm Sewer Drainage Area to Outfall F /�`\ 0
Field Operations Storm Sewer System Storm Water BM Ps / V Feet
■ storm Inlet Untlergmuntl Detention w
• SlonnManhole erorner • BrowIIAND I •�Nr
Caldwell ' LOShkOSh
Storm Sewer Grass Swale