HomeMy WebLinkAbout07. 15-489NOVEMBER 24, 2015 15-489 RESOLUTION
(CARRIED__7-0_____ LOST _______ LAID OVER _______ WITHDRAWN _______)
PURPOSE: APPROVE CHANGE ORDER NO. 2 FOR PUBLIC WORKS
CONTRACT NO. 14-11 WITH WOOD SEWER & EXCAVATING, INC.
(+$66,650.40)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
WOOD SEWER & EXCAVATING, INC.
E9238 County Road X
New London, WI 54961
Net Increase to contract: $66,650.40
PURPOSE: See attached Change Order.
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Acct. No. 315-0410-7480-00000 Street Improvement Fund Expenditures
541-1810-1799-00000 Water Utility Construction in Progress
551-1910-1799-00000 Sewer Utility Construction in Progress
561-2010-1799-00000 Storm Water Utility Construction in Progress
�
HKO H
pN THE WATER
MEMORANDUM
TO: Honorable Mayor and Members of the Common Council
FROM: Pete Gulbronson, Civil Engineering Supervisor ��,��
DATE: November 19, 2015
RE: Change Order No. 2 for Public Works Contract No. 14-11
Sanitary Sewer Manhole Rehabilitation / Infiltration/Inflow Reduction Program
Wood Sewer & Excavating, Inc. ($+66,650.40)
BACKGROUIVD
Change Order No. 2 for Contract 14-11 is scheduled for consideration by the Common Council at the November
24, 2015 meeting. The contract was originally awarded to Wood Sewer & Excavating, Inc. in July of 2014 and
Change Order No. 1 was approved in June of 2015. This change order is for final quantities and additional
services provided.
ANALYSIS
Following is a summary of the significant changes to each section of the CIP:
• Sanitary Sewer:
o Addition of 25 critical manholes that needed to be rehabbed.
FISCAL IMPACT
Adequate funds are available in the relating sections of the 2Q14 Capital lmprovement Budget.
RECOMMENDATIONS
I recommend approval of Change Order No. 2 to Contact No. 14-11 in the amount of $66,650.40 to Wood
Sewer & Excavating, Inc.
Approved:
�i�C�J�-- � � -
l
Mark A. Rohloff
City Manager
PPG/tlt
I:\Engineering�2014 CONTRACTS\14-11 San MH Rehab-I&I Reduction Prog\Project_Information\Correspondence\Memo\14-11 CO #2 Memo_t t-19-15.docx
TO: WO00 SEWER & EXCAVATING, INC.
E923$ COUNTY ROAD X
NEW I.OND�N, WI 54961
CHANGE ORQER #2 (FINAL}
DATE: NOVEMBER 13, 2015
Your present contract with the City of Oshkosh, Contract No. 14-11, awardad Juiy 22, 2014, is hereby
amended and changed as foltows:
Recommended:
NET (NCREASE TO: SECT(ON I- SANITARY MANHO�� REHAB
NET INCREASE 70 CON7RACT
Director of Pubfic Works
$66,650,40
566,664A0
SECTION i
{SANITARY
MANHOLE
REHABILITATION) 70TAL
BID TOTAL $393,039,20 $393,038.2Q
CO #1 $39,825.02 $39 8Y5.02
PREVIOUS CONTRACT TOTAL $432,864.22 $432,864.2Z
CO #2 $&6,650.40 $68,650.40
GONTRACT TOTAL 489,514.82 499,594.82
CIl'Y OF OSHKOSH
BY:
City Manager
City Clerk
Ap "ved a� accepted: �
A J
!
�� ,
� Contractor
I certi(y that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wiscansin,
under ihe withfn Change Order.
Approved as to form:
City At�orney
Comptroller
CONTRACT 14-11 CHANGE ORDER #2 (FINAL)
SECTION I- SANITARY MANHOLE REHABILITATION
ITEM CONTRACT INSTALLED NET NET UNIT /NCREASEIN DECREASE/N
NUMBER DESCRIPT/ON UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
Replace sanitary manhole
casting (CITY to furnish
casting), complete as
100 specified Each 102.00 117.00 15.00 $200.00 $3,000.00
External manhole chimney
seal (9"), complete as
102 s ecified Each 58.00 75.00 17.00 $390.00 $6,630.00
External manhole chimney
seal (Infrashield), complete
103 as s ecified Each 25.00 36.00 11.00 $690.00 $7,590.00
8" external manhole
chimney seal extension,
104 com lete as s ecified Each 24.00 26.00 2.00 $280.00 $560.00
Internal manhole chimney
seal (10"), complete as
106 s ecified Each 5.00 3.00 -2.00 $280.00 $560.00
10" internal manhole
chimney seal extension,
108 com lete as s ecified Each 2.00 0.00 -2.00 $190.00 ($380.00)
7" internal manhole
chimney seai extension,
110 com lete as s ecified Each 3.00 0.00 -3.00 $180.00 $540.00
Re-form/re-shape manhole
bench, complete as
111 s ecified Each 10.00 0.00 -10.00 $500.00 $5,000.00
Concrete adjusting rings, Vertical
112 com lete as s ecified Feet 31.31 50.27 18.96 $260.00 $4,929.60
Rubber adjusting rings, Vertical
114 com lete as s ecified Feet 4.27 6.35 2.08 $580.00 $1,206.40
Reconstruct sanitary sewer
manhole (slurry), complete Vertical
116 as s ecified Feet 82.73 131.99 49.26 $550.00 $27,093.00
Furnish and install
standard sanitary manhole
(4' Diameter) (slurry), Vertical
118 complete as specified Feet 7.80 48.95 41.15 $800.00 $32,920.00
Saw cut concrete
pavement, complete as Linear
122 s ecified Feet 2,880.00 3,262.40 382.40 $3.00 $1,147.20
Remove concrete
pavement, complete as Square
124 s ecified Yards 1,216.00 1,334.49 118.49 $4.00 $473.96
Pavement ties, complete
126 as s ecified Each 960.00 1,104.00 144.00 $6.00 $864.00
7" concrete pavement, Square
128 com lete as s ecified Yards 1,175.00 768.69 -406.31 $55.00 $22,347.05
7" concrete pavement
(HES), complete as Square
130 s ecified Yards 50.00 44.90 -5.10 $60.00 $306.00
8" concrete pavement, Square
132 com lete as s ecified Yards 25.00 204.50 179.50 $59.00 $10,590.50
8" concrete pavement
(HES), complete as Square �
134 s ecified Yards 25.00 360.50 335.50 $62.00 $20,801.00
Partial depth joints, Linear
136 com lete as s ecified Feet 150.00 0.00 -150.00 $3.00 $450.00
Page 1 of 3
CONTRACT 14-11 CHANGE ORDER #2 (FINAL)
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
12" radius curb with 6"
CABC and grading, Linear
138 com lete as s ecified Feet 30.00 0.00 -30.00 $20.00 $600.00
30" curb and gutter, 7", with
5" CABC and grading, Linear
140 com lete as s ecified Feet 10.00 49.95 39.95 $30.00 $1,198.50
4" concrete sidewalk, Square
142 com lete as s ecified Feet 50.00 0.00 -50.00 $6.00 $300.00
6" concrete sidewalk,
driveway, and ramp, Square
144 com lete as s ecified Feet 144.00 173.20 29.20 $7.00 $204.40
Drilled No. 4 sidewalk tie
146 bars, com lete as s ecified Each 24.00 6.00 -18.00 $5.00 $90.00
Curb ramp detectable
warning field, complete as Square
148 s ecified Feet 8.00 0.00 -8.00 $30.00 $240.00
Saw cut asphalt pavement, Linear
150 com lete as s ecified Feet 2,262.00 1,863.80 -398.20 $2.00 $796.40
Remove and replace HMA
pavement, complete as Square
152 s ecified Yards 1,392.00 915.20 -476.80 $40.00 $19,072.00
Lawn restoration, complete Square
154 as s ecified Yards 108.00 116.87 8.87 $9.00 $79.83
Manhole lid plug, complete
156 as s ecified Each 25.00 0.00 -25.00 $14.00 $350.00
Tuck point manhole,
158 com lete as s ecified Each 10.00 8.00 -2.00 $150.00 $300.00
Sanitary manhole grouting
setup, complete as
160 s ecified Each 61.00 60.00 -1.00 $500.00 $500.00
Sanitary manhole grout,
162 com lete as s ecified Gallons 4,575.00 3,435.00 -1,140.00 $7.50 $8,550.00
Cold mix patch, complete Square
168 as s ecified Yards 1,000.00 876.93 -123.07 $22.00 $2,707.54
Traffic control, complete as Lump
170 s ecified Sum 1.00 1.13 0.13 $13,600.00 $1,768.00
SECTION I-(BID ITEMS 100-170) - SUBTOTAL $121,056.39 ($63,088.99)
SECTION I- ADDITIONAL WORK REQUIRED: CO #1
ITEM CONTRACT INSTALLED NET NET UNIT �NCREASE /N DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
1 Additional equipment,
labor, and materials to
install hot mix asphalt for
temporary pavement at the
intersection of Sawyer
Street and Witzel Avenue
on 10/31/14; complete as Lump
specified Sum 1.00 1.00 $1,053.02
2 Additional equipment,
labor, and materials to
repair sanitary sewer on
Newport Avenue on
11/6/14; complete as Lump
specified Sum 1.00 1.00 $6,300.00
Page 2 of 3
CONTRACT 14-11 CHANGE ORDER #2 (FINAL)
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
3 Additional equipment,
labor, and materials to cut
and cap a 12" sanitary
sewer forcemain on Bowen
Street on 11/24/14; Lump
complete as specified Sum 1.00 1.00 $12,600.00
4 Additional equipment,
labor, and materials to
repair sanitary sewer on
Oak Street on 12/11/14; Lump
complete as specified Sum 1.00 1.00 $5,400.00
5 Additional equipment,
labor, and materials to
repair sanitary sewer on
20th Avenue on 1/23/15
and 1/26/15; complete as Lump
specified Sum 1.00 1.00 $14,472.00
SECTION I- ADDITIONAL WORK REQUIRED: CO #1 ITEMS 1-5) - SUBTOTAL $0.00 $0.00
SECTION I- ADDITIONAL WORK REQUIRED: CO #2
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT qUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PR/CE PRICE
6 Additional equipment,
labor, and materials to
abandon sanitary manhole
12-169 and install 8" sewer
on Oshkosh Avenue on
5/27/15; complete as Lump
specified Sum 0.00 1.00 1.00 $5,600.00 $5,600.00
7 Additional equipment,
labor, and materials to fix
sanitary main connection to
manhole 12-300 on 5/5/15; Lump
com lete as s ecified Sum 0.00 1.00 1.00 $1,200.00 $1,200.00
8 Additional cost for
manholes in lieu of a
restocking fee; complete as Lump
specified Sum 0.00 1.00 1.00 $1,883.00 $1,883.00
SECTION I- ADDITIONAL WORK REQUIRED: CO #2 ITEMS 6-8) - SUBTOTAL $8,683.00 $0.00
NET INCREASE TO: SECTION I $66,650.40
NET INCREASE TO SECTION i $129,739.39
NET DECREASE TO SECTION I ($63,088.99)
NET INCREASE TO CONTRACT: $66,650.40