HomeMy WebLinkAboutPW CNT 15-21/CHG OR 1 and 2llEPARTMENT OF PUBLIC WORKS
215 Church Avenue
P.O. Box 1130
Oshkosh, Wisconsin 54903-1130
Ph.(920)236-5065
Fax(920)236-5068
November 13, 2015
Mr. Justin Zylstra
Jos. Schmitt & Sons Construction Co., Inc.
PO Box 1084
Sheboygan, WI 53082-1084
Subject: Change Order No's. 1 and 2
Contract 15-21
Dear Mr. Zylstra:
�
OlHKOlH
ON THE WATER
Enclosed is executed copies of Change Order No's. 1 and 2 between the City of Oshkosh and Jos.
Schmitt & Sons Construction Co., Inc. regarding the abovementioned project.
If you have any questions, please call our office at (920)236-5065.
Sincerely,
��%�9���
� es Rabe, P.E., CPESC ' ' �
Director of Public Works
JER/tlt
Enclosures: Change Order No's. 1 and 2
cc; Pam Ubrig, City Clerk (w/original)
Tara Wendt, Assistant Finance Director (w/copy)
Jon Wallenkamp, Kueny Architects (w/copy)
Kevin Uhen, Public Works Field Operations Manager (w/copy)
File (w/original)
I:�Engineering�2015 CONTRACTS\IS-21 PW Field Ops Facility-Ph IIIU'roject_Information\Contract Info\Change Page 1 of 1
OrdersUS-21 Execured CO #1 & 2 Ltr 11-13-15.docx
��= � TM
�-�_ Document G701 — 2001
Change Order
PROJECT (Name and address): CHANGE ORDER NUMBER: 001
OWNER: ❑
Public Works Field Operations Facility - DATE: 9/17/2015 ARCHITECT: ❑
Phase II[
639 Witzel Avenue CONTRACTOR: ❑
Oshkosh, WI 54902
TO CONTRACTOR (N'ame and address): ARCHITECT'S PROJECT NUMBER: FIELD: ❑
Jos. Schmitt & Sons Construction CONTRACT DATE: 3/30/2015 OTHER: ❑
Company, Inc. CONTRACT FOR: General Construction
PO Box 1084
2014 Union Avenue
Sheboygan, WI53082-1084
THE CONTRACT IS CHANGED AS FOLLOWS:
(Include, where app[icable, any undisputed amount attributable to previously executed Construction Change Directives)
The original Contract Sum was
The net change by previously authorized Change Orders
The Contract Sum prior to this Change Order was
The Contract Sum will be decreased by this Change Order in the amount of
The new Contract Sum including this Change Order will be
The Contract Time will be increased by Zero (0) days.
The date of Substantial Completion as of the date of this Change Order therefore is
$ 2,889,000.00
$ 0.00
$ 2,889.000.00
$ 671,508.64
$ 2,217,491.36
NOTE: This Change Order dces not include changes in the Contract Sum, Contract Time or Guaranteed Maximum Price which have
been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and
Contracror, in which case a Change Order is executed to supersede the Construction Change Directive.
NOT V�tD �1NTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER.
LLC
!CT�Firm name)
�rporate Drive Suite 100
Prairie, WI 53158
IT�IZZ���
BY (Signature)
Jon P. Wallenkamp
(Tvped name)
September 17, 2015
DATE
Jos. Schmitt & Sons Construction City�Oshkos}y--�_� �
Company, Inc. ��°� ���G �
CONTRACTOR (Firm name) OWNER (Firm name)
2104 Union Avenue
PO Box 1084
Sheboygan, W153082-1084
R SS
BY ( gnature)
�uS�n J . Z.! \5n4
(Typed name)
9�Lg��.ot�
DATE
215 Church Avenue
Oshkosh. WI 54903-1103
ADDRESS
��'�l -
BY (Si ature)
(Typed am
� r�r�
DATE
AIA Document G701 T"" — 2001. Copyright � 1979, 1987, 2000 and 2001 by The American Institute of Architects. All rights reserved. WARNING: This AIA�
Document is protected by U.S. Copyright Law and Intemational Treaties. Unauthorized reproduction or distribution of this AIA� Document, or any
portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was
produced by AIA software at 10:09:31 on 09/17/2015 under Order No.3296704242_1 which expires on 06/11/2016, and is not for resale.
User Notes: (1160996207)
Signed for and in behalf of the City of Oshkosh
,,��-- �����
Mark A. Rohloff, City Manager
�
/ �'��-�� / ' /
Pamela R. Ubrig, City Clerk
L n orenson, 'ty A t ney
.,�►ro nc.,��M
Trena Larson, Director of Finance
I hereby certify that the necessary provisions
have been made to pay the liability which will
accrue under this contract.
lA