BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
PTS CONTRACTORS INC.
4075 Eaton Road
Green Bay, WI 54311
Net Increase to contract: $51,637.81
PURPOSE: See attached Change Order.
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Acct. No. 541-1810-1799-00000 Water Utility – Construction in Progress
551-1910-1799-00000 Sewer Utility – Construction in Progress
317-0410-7480-03302 Special Assessments Fund – Sewer
561-2010-1799-00000 Storm Utility – Construction in Progress
541-1867-6401-08675 Water Utility – Maintenance of Services
TO: PTS Contractors, Inc. CHANGE ORDER#1
4O75 Eaton Road DATE� August J1. 2O15
Green Bay VV| 54311
Your present contract with the City of Oshkosh, Contract No, 15-07, awarded June 23, 2015, is hereby
amended and changed asfollows:
NET INCREASE TO: SECTION |-PAVING $4.750.80
NET|NCREASETO: SECTION ||'BT[>RK0SEWER 88.878.51
NET INCREASE TO: SECTION III-SANITARY SEWER $25'955.54
NET|NCREA8ETO� SECT|ON |V-VVATER MAIN $12.253.76
'
NET INCREASE TOCONTRACT ¢51'637.81
Section Section 11 Section III Section IV
(Paving) (Storm) (Sanitary) (Water) Totals
Bid Total $00001400 $16880252 $716881�50 $28107726 ` '
O{}#1
` nori+""ctTotal 7.04 ' �293'331.01 `' `$1,814,012,W {
CITY{)FOSHKOSH
BY:
Recommended: City Manager
Interim Director of Public Works City Clerk
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin,
under the within Change Order.
Comptroller
Approved eobJform:
City Attorney
CONTRACT 15-07 CHANGE ORDER#1
SECTION I-PAVING
ADDITIONAL WORK REQUIRED: CO#1-SECTION I
ITEM DESCRIPTION UNIT Rio INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACrPRICE CONTRACTPRICE
1010 Clearing,complete as
sp9cified Stations 0 5.00 5,00 $290,00 $1,460.00
loll Clearing,complete as Inch
_qn,-cffiPd Diameter 0 10.00 10.00 $186.00 $1,85D.o0
1020 Grubbing,complete as
specified Stations 0 5.00 6.00 $290.00 $1,450.00,1
ADDITIONAL WORK; CO#1-(ITEMS 1010-1024)-SUBTOTAL $4,780.00 $0.00
NET INCREASE TO: SECTION 1 $4,760,00
SECTION 11-STORM SEWER
ADDITIONAL WORK RE061RED: CO#1 -SECTION 11
ITEM OF-5rRIPTION UNIT BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
2612 Furnish and install Type 1
inlet(less casting),complete
ass cified Each 0.00 1.00 1.00 $1,4%00, $1,450.00
2514 Furnish and Install Type 3
Inlet(with 16"sump),
complete ass ecified Each 0.00 1.00 1,00 $1,800.00 $1.800.00
20000 Additional labor,equipment,
and materials to replace
storm sewer on Alaska Street
and West 17th Avenue for Lump
Wisconsin Public Service Sum 0.00 1.00 1.00 $640.00 $640.00
20001 Additional labor,equipment,
and materials to rebuild storm
manholes withln the concrete Lump
limits on West 6th Avenue Sum 0.00 1,00 1 1.00 $3.663.0 $3,653,43
20002 Additional labor,equipment,
and materials to repair
collapsed storm sower on
West 6th Avenue and Oregon Lump
IStreet Sum 0.00 - 1.00 1 $1.235.08 s1'235.08
ADDITIONAL WORK: CO#1-(ITEMS 2612-20002)•SUBTOTAL $8,678.51 $0.00
NET INCREASE TO: SECTION R $8,678.61
SECTION 111-SANITARY SEWER
ADDITIONAL WORK REQUIRED: CO#1-SECTION III
ITEM DESCRIPTION UNIT BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACTPRtC6 CONTRACYPRICE
30000 Furnish and Install trenchiess
1211 sanitary sewer casing Linear
PJR2 Feet 0,00 60.00 60.00 $266.00 $15 960.00
30001 Additional equipment,labor,
and materials to rebuild drop
manhole 04.322 at the
Intersection of Merritt Avenue Lump
and Monroe Street Sum 0.00 1.00 1 1.00 1$2,700,00 $2,700.00
10002 Additional equipment,labor,
and materials to rebuild the
chimney of manhole 03-212
at the Intersection of West
8th Avenue and Nebraska Lump
IStreet Sum I 0.00---L 1,00 1.00 1 $260.00 1 $260.00,
30002 Additional equipment,labor,
and materials to Install now
laterals for 45 West 6th Lump
Avenue Sum 0,00 1.00 1 1,00 [$1,318,27 $1,318.27
page 1 oft
CONTRACT 16-07 CHANGE ORDER#11
ITEM DESCRIPTION UjV17 BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
$0003 Additional equipment,labor,
and materials to abandon 27"
sanitary sewer and bulkhead Lump
the main in Manhole 09-28 Sum 0,00 1.00 1,00 $6727.27 $6,727.27
ADDITIONAL WORK; CO#1•(ITEMS 30000-300037-SUBTOTAL $26,965,64 WOO
NET INCREASE TO; SECTION 111 $26,956.64
SECTION IV-WATER MAIN
ADDITIONAL WORK REQUIRED: CO#1-SECTION IV
ITEM DESCRIPTION UNIT BID INSTALLED NET NET UNIT INCREASE IN DECREASEIN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACTPRICE CONTRACTPRICE
4352 Cut and cap existing 6"water
main,com2lete ass ecifiied Each 0.00 4.00 .4.00 $1,400.00 $6,600.00
40001 Additional labor,equipment,
and materials to abandon Lump
water main off of Eagle Street Sum 0.00 1.00 1,00 $2,559,74 $2,559,74
40002 Additional labor,equipment,
and materiels to repair a
water main break at West 6th
Avenue and South Sawyer Lump
Street Sum 0,00 IXO 1.00 $7$6.15 $736.16
40003 Additional labor,equipment,
and materials to lower$"
water main on West South
Park Avenue and Georgia Lump
IStreet sum I uo__J_ 1.00 1.00 1 $3,35T87 $3,357-87
ADDITIONAL WORK: CO#1(ITEMS 4352.40003)-SUBTOTAL $12,253.76 $0.00
NET INCREASE TO: SECTION IV $12,263.76
NET INCREASE TO SECTIONS 1,11,111,&W
NET DECREASE TO SECTIONS 1,11,111,&IV $0.00
NET INCREASE TO CONTRACT:
P89e 2 of 2
copme-)
OJHKOJH
ON THE WATER
MEMORANDUM
TO: Honorable Mayor and Members of the Common Council
FROM: Steven M. Gohde, Interim Director of Public Works
DATE: September 3, 2015
RE: Change Order No. 1 for Public Works Contract No. 15-07
Utility Repairs and Installation/Various Locations
PTS Contractors, Inc. (+$51,637.81)
BACKGROUND
Change Order No. 1 for Contract 15-07 is scheduled for consideration by the Common Council at the
September 8, 2015 meeting. The contract was originally awarded to Vinton Construction Company in June of
2015. This change order is for additional services provided.
ANALYSIS
Following is a summary of the significant changes to each section of the CIP:
• Storm Sewer—Additional work for storm sewer repairs and manhole rebuilds.
• Sanitary Sewer—Additional work to accommodate plan changes because of field conditions, as well as
a bore across Oregon Street because field conditions didn't allow for open cutting.
• Water Main —Additional work to accommodate field conditions and repair water mains that failed during
construction.
FISCAL IMPACT
Contract Section Change Order Amount New Contract Total CIP Budget Amount
Storm Sewer $7,228.51 $219,506.03 $206,000.00
Sanitary Sewer $27,405.54 $1,279,615.24 $1,402,475.00
Water Main $17,003.76 $291,819.11 $279,200.00
Water Utility Operating $0.00 $23,072.50 $25,842.00
Total $51,637.81 $1,814,012.88 $1,913,517.00
Adequate funds are available in the relating sections of the 2015 Capital Improvement Budget from other
projects being under budget. Specifically, $13,506.03 of storm sewer funding and the $12,619.11 of water main
funding will be transferred from the available CIP budgets of the first paving contract of 2015.
RECOMMENDATIONS
I recommend approval of Change Order No. 1 to Contact No. 15-07 in the amount of +$51,637.81 to PTS
Contractors, Inc.
Approved:
Mark A. Rohloff
City Manager
I:\Engineering\2015 CONTRACTS\15-07 Misc Sewer Relays\Project_Information\Correspondence\Memo\15-07 Memo for CO#1_9-3-15.docx