HomeMy WebLinkAboutPW CNT 13-11/CHG OR 1DEPARTMENT OF PUBLIC WORKS
215 Church Avenue
P.O. Box 1130
Oshkosh, Wisconsin 54903-1130
Ph.(920)236-5065
Fax(920)236-5068
July 31, 2015
Ms. Sue Wood
Wood Sewer & Excavating, Inc.
E9238 County Road X
New London, WI 54961
Subject: Change Order No. 1
Contract 13-11 �
Dear Ms. Wood:
�
OIHKOIH
ON iXE WAiER
Enclosed is an executed copy of Change Order No. 1 between the City of Oshkosh and Wood Sewer &
Excavating, Inc. regazding the abovementioned project.
If you have any questions, please call our office at (920)236-5065.
Sincerely,
C\�� / ` \/�-��-
Steven M. Gohde, P.E.
Interim Director of Public Works
SMG/tlt
Enclosure: Change Order No. 1
cc: Pam Ubrig, City Clerk (w/original)
Tara Wendt, Assistant Finance Directar (w/copy)
File (w/original)
i:��g���u;�g��3-u s.� r.m n�n.n-�anr�o}e«i�r ,m.�m��co��� mrmcna�ge obg.m-u e.e�rea co a� z3 �- Page 1 of 1
�s ao�.
TO: Wood Sewer & Excavating, Inc.
E9238 County Road X
New London, WI 54961
CHANGE ORDER #1
DATE: JULY 7. 2015
Your present contract with the City of Oshkosh, Contract No. 13-11, awarded August 13, 2013, is hereby
amended and changed as follows:
NET INCREASE TO: SECTION I- SANITARY MANHOLE REHAB
NET INCREASE TO CONTRACT
Section I
Sanitary Manhole
Rehabilitation Totals
Bid Total $740,768.82 $740,768.82
CO #1 $5,058.46 $5,058.46
Contract Total $745,827.28 $745,827.28
Recommended:
�., �-a�,/�
Interim Director of Public Works
CITY OF OSHKOSH
aY: /�a—� ��-r.�k�
�City Manager
,
ity CI k '
Appr d and accepted:
Contractor
$5, 058.46
$5,058.46
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin,
under the within Change Order.
� � \ _� )�
— - �
. . -
• .. . -. . . . I,
��u► �II •ir��l � 1 /
� . .�_
CONTRACT 13-11 - CHANGE ORDER #1
SECTION I- SANITARY MANHOLE REHABILITATION
ITEM BID INSTALLED NET NET UNIT �NCREASEIN DECREASEIN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTftACT
PRICE PRICE
100 Replace sanitary manhole
casting, complete as
specified
Each 157.00 139.00 -12.00 $160.00 $1,920.00
102 External manhole chimney
seal (Cretex), complete as
specified
Each 6a.00 47.00 -17.00 $230.00 $3,910.00
103 External manhole chimney
seal (Infi-Shield), complete
as specified
Each a7.00 82.00 -5.00 $520.00 $2,600.00
104 8" external manhole
chimney seal extension,
complete as specified
Each 39.00 7.00 -32.00 $170.00 $5,440.00
106 Internal manhole chimney
seal, complete as specified
Each 44.00 46.00 2.00 $230.00 $460.00
108 10"internal manhole
chimney seal extension,
complete as specified
Each 11.00 20.00 9.00 $130.00 $1,170.00
110 7" intemal manhole
chimney seal extension,
complete as specified
Each 26.00 12.00 -14.00 $120.00 $1,680.00
112 Concrete adjusting rings,
complete as specified Vertical
Feet 39.40 54.84 16.44 $280.00 $4,603.20
114 Rubber adjusting rings,
complete as specified Vertical
Feet 3.70 5.02 1.32 $590.00 $778.80
116 Reconstruct sanitary sewer
manhole, complete as
specified Vertical
Feet 119.77 7227 -47.50 $540.00 $25,650.00
118 Furnish and install
standard sanitary manhole
(4' diameter), complete as
specified Vertical
Feet 251.30 204.16 -47.14 $699.00 $32,950.86
120 Furnish and install
standard sanitary manhole
(6' diameter), complete as
specified Vertical
Feet 72.50 0.00 -12.50 $2,400.00 $30,000.00
122 Saw cut concrete
pavement, complete as
specified Linear
Feet 4.88a.0a 5,080.83 196.83 $2.00 $393.66
Page 1 of 5
CONTRACT 13-11 - CHANGE ORDER #1
ITEM BID INSTALLED NET NET UNI7 INCREASE IN DECREASE IN
NUMBER DESCftIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
124 Remove concrete
pavement, complete as
specified Square
Yards 2,o2s.00 2,984.32 955.32 $6.00 $5,731.92
126 Pavementties,complete
as specified
Each 1,628.00 1,610.00 -18.00 $5.00 $90.00
128 7" concrete pavement,
complete as specified Square
Yards 1,725.00 1,377.35 347.65 $51.00 $17,730.15
130 7" concrete pavement
(HES), complete as
specified Square
Yards 50.00 55.80 5.80 $56.00 $324.80
132 8" concrete pavement,
complete as specified Square
Yards 320.00 77.60 -242.40 $57.00 $13,816.80
134 8" concrete pavement
(HES), complete as
specified Square
Yards 25.00 1,235.00 1,210.00 $60.00 $72,600.00
136 Partial depth joints,
complete as specified Linear
Feet 150.00 21420 64.20 $3.00 $192.60
138 12" radius wrb with 6" �
CABC and greding,
complete as specified Linear
Feet 30.00 0.00 -30.00 $24.00 $720.00
140 30" curb and gutter, 7", with
5" CABC and grading,
complete as specified
Linear
Feet 60.00 0.00 -60.00 $28.00 $1,680.00
142 4" concrete sidewalk,
complete as specifed Square
Feet 75.00 0.00 -75.00 $6.00 $450.00
144 6" concrete sidewalk,
driveway, and ramp, �
complete as specified Square
Feet zo.o0 19.70 -0.30 $7.00 $2.10
146 Drilled No. 4 sidewalk tie
bars, complete as specified
Each 24.00 10.00 -14.00 $5.00 $70.00
148 Curb ramp detectable
warning field, complete as
specifed Square
Feet 8.00 0.00 -8.00 $38.00 $304.00
150 Saw cut asphalt pavement,
complete as specified
Linear
Feet 2,756.00 2,576.10 -179.90 $1.00 $179.90
152 Remove and replace HMA
pavement, complete as
specified Square
Yards t,sss.00 1,726.78 30.78 $44.00 $1,354.32
Page 2 of 5
CONTRACT 73-71 - CHANGE ORDER #1
ITEM BID INSTALLED NET NET UNI7 INCREASEIN DECREASEIN
NUMBER DESCftIPT10N UNIT qUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
154 Lawn restoration, complete
as specified Square
Yards 192.00 95.66 -96.34 $9.00 $867.06
156 Manhole lid plug, complete
as specified
Each 185.00 173.00 -12.00 $14.00 $168.00
158 Tuck point manhole,
complete as specified
Each 58.00 61.00 3.00 $210.00 $630.00
160 Sanitary manhole grouting
setup, complete as
specified
Each 75.00 76.00 1.00 $500.00 $500.00
162 Sanitary manhole grout,
complete as specified
Gallons 4,466.00 5,390.00 924.00 $7.50 $6,930.00
164 Sanitary manhole
cementitious liner setup,
complete as specified
Each 5.00 5.00 $1.00
166 Structural cementitious
liner, complete as specified
Vertical
Feet 4Z52 50.58 3.06 $141.00 $431.46
168 Cold mix patch, complete
as specified Square
Yards 700.00 1,210.60 510.60 $28.00 $14,296.80
170 Traffic control, complete as
specifed Lump
Sum 1.00 1.00 $16,440.00
SECTION I-(BID ITEMS 100 - 170) - SUBTOTAL E110,397.56 (5140,228.87)
ADDITIONAL WORK REQUIRED: CO #1 • SECTION I
ITEM BID INSTALLED NET NET UNR �NCREASEIN DECREASEIN
NUMBER DESCRIPTION UNIT qUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
1 Infreshield purchase
Each 0.00 -51.00 -51.00 $121.33 $6,187.83
2 Additional equipment,
labor, and materials to
repair storm sewer on
Hazel Street on 5/8/2014 Lump
Sum 0.00 1.00 1.00 $7,056.10 $7,056.10
3 Additional equipment,
labor, and materials to
reinstall Hardee's lateral on
High Avenue on 5/16/2014
Lump
Sum 0.00 1.00 1.00 $2,475.00 $2,475.00
Page 3 of 5
CONTRACT 13-11 • CHANGE ORDER #1
ITEM BID INSTALLED NET NET UNIT �NCREASEIN DECREASEIN
NUMBER DESCR/PTION UNIT qUANT17Y QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
4 Additional equipment,
labor, and materials to
reinstall the lateral for 1230
Ontario Street on
5/27/2014 Lump
Sum 0.00 1.00 1.00 $2.332.50 $2,332.50
5 Additional equipment,
labor, and materials to
abandon sanitary Manhole
07-180 on 6/11/2014 Lump
Sum 0.00 1.00 1.00 $7,136.00 $7,136.00
6 Additional equipment,
labor, and materials to
repair storm sewer at the
intersection of Wright
Street and Scott Avenue
on 7/16/2014 Lump
Sum 0.00 1.00 1.00 $5,370.00 $5,370.00
7 Additional equipment,
labor, and materials to
invistigate a possible
abandonment of a santiary
manhole not on the City's
records (sanitary Manhole
01-05). Lump
Sum 0.00 1.00 1.00 $3,024.00 $3,024.00
8 Additional equipment,
labor, and materials to
invistigate a set of sanitary
and water laterals that were
abandoned (sanitary
Manhole Ot-23). Lump
Sum 0.00 1.00 1.00 $1,600.00 $1,600.00
9 Additional equipment,
labor, and materials to
properly abandon a
santiary lateral (sanitary
Manhole 01-214). Lump
Sum 0.00 1.00 1.00 $1,600.00 $1,600.00
10 Additional equipment,
labor, and materials to
install a new sanitary wye
that was in close proximity
to sanitary Manhole OS-57.
Lump
Sum 0.00 1.00 1.00 $1,600.00 $1,600.00
11 Additional equipment,
labor, and materials to
remove a sanitary manhole
not in the City's records
and install PVC main
(sanitary manhole
approximately 19' south of
05-79). Lump
Sum 0.00 1.00 1.00 $4,084.00 $4,084.00
Page 4 of 5
CONTRACT 13-11 - CHANGE ORDER #1
ITEM BID INSTALLED NET NET UNIT INCREASEIN DECREASEIN
NUMBER DESCftIPT10N UNIT qUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
12 Additional equipment,
labor, and materials to
install a new sanitary wye
that was in close proximity
to sanitary Manhole 07-
110. Lump
Sum 0.00 1.00 1.00 $2,400.00 $2,400.00
13 Additional equipment,
labor, and materials to
install a new sanitary wye
that was in close proximiry
to sanitary Manhole 12-79.
Lump
Sum 0.00 1.00 1.00 $2,400.00 $2,400.00
ADDITIONAL WORK: CO #1 -(ITEMS 1- 13) • SUBTOTAL E41,077.60 (E6,187.83)
NET INCREASE TO: SECTION I 55,058.46
NET INCREASE TO SECTION I: $151,475.16
NET DECREASE TO SECTION I: (E146,416.70)
NET INCREASE TO CONTRACT: E5,058.46
Page 5 of 5