PURPOSE: APPROVE CHANGE ORDER NO. 2 FOR PUBLIC WORKS
CONTRACT 13-24 WITH AUGUST WINTER & SONS, INC. FOR
THE WASTEWATER TREATMENT PLANT CONTROL SYSTEM,
INFLUENT PUMPING, AND AERATION BLOWERS UPGRADE
(+$90,275.00)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
AUGUST WINTER AND SONS, INC.
2323 North Roemer Road
Appleton, WI 54911
Net Increase to contract: $90,275.00
PURPOSE: See attached Change Order.
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Acct. No. 551-1910-1799-00000 Sewer Utility – Construction in Progress
j CONTRACT MODIFICATION uccuivED
CITY OF OSHKOSH— CONTRACT NO. 13-24 vi
CH2MHILL MAY 1 4 21315
u
I CHANGE ORDER WRITTEN AMENDMENT MODIFICATION NO: 002 DEPT HKDSIUl IV'.'Il SL.W NSIN
TO August Winter&Sons, Inc.
PROJECT: Wastewater Treatment Plant Control System, Influent PROJECT NO: 482461
Pumping &Aeration Blowers Upgrade
OWNER: City of Oshkosh
ENGINEER: CH2MHILL
The following modification(s)to the Contract are hereby ordered (use additional pages if required):
Refer to Items 2a.through 2k. described on attached page 2 with supporting documentation following page 3.
Reason for Modification(s):
Actions taken to modify design or construction methods to adjust for site conditions.
Attachments(List Supporting Documents):
Contract Amount or Price Contract Times (Calculate Days)
Original $4,210,500 Original Duration 760 Days
Previous Contract Previous Contract
Modification(s) Modification(s)
(Add/Deduct) $50,000 (deduct) (Add/Deduct) 0 Days
This Contract Modification This Contract
(Add/Deduct) $90,275(add) Modification 0 Days
Revised Contract Amount $4,250,775 Revised Contract Time 760 Days
The Revised Contract Completion Date is: March 4, 2016
Owner(City of Oshkosh) Contractor(August Winter&Sons, Engineer(CH2M HILL)
Inc)
By: By: :✓/( 7 By: Lv/-eQA- 7)t
Date Date j7/�3„ /24,7 Date: 'x/30 0 /S
(see page 3)
Change Order No. 2 April 20,2015
City of Oshkosh Contract No. 13-24
Wastewater Treatment Plant Control System, Influent Pumping&Aeration Blower Upgrade
Contractor: August Winter& Sons, Inc.
This document shall become a supplement to City of Oshkosh Contract No. 13-24 and all provisions will
apply hereto.
TABLE 1
Description of Requested Changes
Item COR No. Description Action Amount
2a. 002 Extend centrifuge starter panel pads Add $2,741
2b. 003 Change 18 LED light fixtures Add $15,902
28. 004 ___Enlarge transformer pad, removed previously abandoned conduit, Add $20,737
remove unsuitable soils
2d. 005 Change valve electrical feeders Add $5,062
2e. 006 Label wires in new SCCs with existing numbers in addition to new Add $23,102
numbers in the field and on over 500 SCC drawings
2f. 007 Install 4 additional LED light fixtures Add $6,478
2g. - Modify influent pump vent piping to include additional valves Add $8800
2h. 010 Modify RIO 2B UPS and DO probe junction boxes Add $2,304
2i. 012 Modify 2"conduit for VFD installation Add $1,275
2j. 013 Modify feeders SWGR/Rockwell Drive/Pump P-11-2-1 Motor to adjust Add $13,604
for site conditions and current electrical code requirements
2k. - Credit—not witness blowers factory test Deduct -$7,730
TOTAL VALUE OF THIS CHANGE ORDER Add $90,275
•
2
Signed for and in behalf of the City of Oshkosh
Mark A. Rohloff, City Manager
Pamela It Ubrig,City Clerk
Lynn Lorenson,City Attorney
Trena Larson, Director of Finance
I hereby certify that the necessary provisions
have been made to pay the liability which will
accrue under this contract.
3
MEMORANDUM
TO: Honorable Mayor and Members of the Common Council ((ll,,��--),�����
FROM: Stephan M. Brand, Public Works Utility Bureau Manager�V
DATE: May 21, 2015
RE: Change Order No. 2 for Public Works Contract No. 13-24
WWTP Control System, Influent Pumping, &Aeration System Blower Upgrades
August Winter and Sons, Inc./$90,275
BACKGROUND
Change Order No. 2 for Contract 13-24 is scheduled for consideration by the Common Council at the May 26,
2015 meeting. The contract was originally awarded to August Winter and Sons in January 2014 to replace
aging influent pumping equipment, control systems, and aeration system blowers. When replacing and retro
fitting equipment in a production facility setting, we occasionally encounter conditions that were unanticipated
and require modifications to the plans. We also encounter situations where improvements can be made to add
long-term value to the project. The project is approximately 40%complete.
ANALYSIS
The four major items in this change order include: upgrading to LED light fixtures in the influent wastewater
screening area, which will reduce lighting operation and maintenance cost in a hazardous area; enlarging the
concrete pad and removing unsuitable soils in the area of the new transformer; adding labeling to the wiring in
the supervisory control centers to show existing wire numbers and new wire numbers for trouble shooting
purposes; and modifying electrical wire feeders to adjust for site conditions and electrical code requirements in
the pump room. All items related to this change order was reviewed by CH2M HILL, our consultant on the
project, and were found to be reasonable and within expected costs for the work performed.
FISCAL IMPACT
The original contract amount was for $4,210,500. Change Order No. 1 decreased the budget by $50,000.
Change Order No. 2 is for $90,275. The revised contract price with this change order is $4,250,775. This
project is included in the 2014 Capital Improvements Program under the Major Equipment(Sewer Utility Fund).
RECOMMENDATIONS
I recommend approval of Change Order No. 2 to Contact No. 13-24 in the amount of$90,275 to August Winter
and Sons, Inc.
Approved:
Mark A. Rohloff
City Manager
SMB/tit
BEngir erin0\13-24 WWrP Ctrl Snl Infuent Pump,flAeration Blower Upgrade\Correspondenc IMemol3-24 CO#2 Memo_5-21-15 LLacx