HomeMy WebLinkAbout13. 15-251 MAY 26, 2015 15-251 RESOLUTION (CARRIED___6-0____ LOST _______ LAID OVER _______ WITHDRAWN _______) PURPOSE: APPROVE CHANGE ORDER NO. 2 FOR PUBLIC WORKS CONTRACT 13-24 WITH AUGUST WINTER & SONS, INC. FOR THE WASTEWATER TREATMENT PLANT CONTROL SYSTEM, INFLUENT PUMPING, AND AERATION BLOWERS UPGRADE (+$90,275.00) INITIATED BY: DEPARTMENT OF PUBLIC WORKS BE IT RESOLVED by the Common Council of the City of Oshkosh that the following Change Order, a copy of which is attached, is hereby approved: AUGUST WINTER AND SONS, INC. 2323 North Roemer Road Appleton, WI 54911 Net Increase to contract: $90,275.00 PURPOSE: See attached Change Order. BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated from: Acct. No. 551-1910-1799-00000 Sewer Utility – Construction in Progress j CONTRACT MODIFICATION uccuivED CITY OF OSHKOSH— CONTRACT NO. 13-24 vi CH2MHILL MAY 1 4 21315 u I CHANGE ORDER WRITTEN AMENDMENT MODIFICATION NO: 002 DEPT HKDSIUl IV'.'Il SL.W NSIN TO August Winter&Sons, Inc. PROJECT: Wastewater Treatment Plant Control System, Influent PROJECT NO: 482461 Pumping &Aeration Blowers Upgrade OWNER: City of Oshkosh ENGINEER: CH2MHILL The following modification(s)to the Contract are hereby ordered (use additional pages if required): Refer to Items 2a.through 2k. described on attached page 2 with supporting documentation following page 3. Reason for Modification(s): Actions taken to modify design or construction methods to adjust for site conditions. Attachments(List Supporting Documents): Contract Amount or Price Contract Times (Calculate Days) Original $4,210,500 Original Duration 760 Days Previous Contract Previous Contract Modification(s) Modification(s) (Add/Deduct) $50,000 (deduct) (Add/Deduct) 0 Days This Contract Modification This Contract (Add/Deduct) $90,275(add) Modification 0 Days Revised Contract Amount $4,250,775 Revised Contract Time 760 Days The Revised Contract Completion Date is: March 4, 2016 Owner(City of Oshkosh) Contractor(August Winter&Sons, Engineer(CH2M HILL) Inc) By: By: :✓/( 7 By: Lv/-eQA- 7)t Date Date j7/�3„ /24,7 Date: 'x/30 0 /S (see page 3) Change Order No. 2 April 20,2015 City of Oshkosh Contract No. 13-24 Wastewater Treatment Plant Control System, Influent Pumping&Aeration Blower Upgrade Contractor: August Winter& Sons, Inc. This document shall become a supplement to City of Oshkosh Contract No. 13-24 and all provisions will apply hereto. TABLE 1 Description of Requested Changes Item COR No. Description Action Amount 2a. 002 Extend centrifuge starter panel pads Add $2,741 2b. 003 Change 18 LED light fixtures Add $15,902 28. 004 ___Enlarge transformer pad, removed previously abandoned conduit, Add $20,737 remove unsuitable soils 2d. 005 Change valve electrical feeders Add $5,062 2e. 006 Label wires in new SCCs with existing numbers in addition to new Add $23,102 numbers in the field and on over 500 SCC drawings 2f. 007 Install 4 additional LED light fixtures Add $6,478 2g. - Modify influent pump vent piping to include additional valves Add $8800 2h. 010 Modify RIO 2B UPS and DO probe junction boxes Add $2,304 2i. 012 Modify 2"conduit for VFD installation Add $1,275 2j. 013 Modify feeders SWGR/Rockwell Drive/Pump P-11-2-1 Motor to adjust Add $13,604 for site conditions and current electrical code requirements 2k. - Credit—not witness blowers factory test Deduct -$7,730 TOTAL VALUE OF THIS CHANGE ORDER Add $90,275 • 2 Signed for and in behalf of the City of Oshkosh Mark A. Rohloff, City Manager Pamela It Ubrig,City Clerk Lynn Lorenson,City Attorney Trena Larson, Director of Finance I hereby certify that the necessary provisions have been made to pay the liability which will accrue under this contract. 3 MEMORANDUM TO: Honorable Mayor and Members of the Common Council ((ll,,��--),����� FROM: Stephan M. Brand, Public Works Utility Bureau Manager�V DATE: May 21, 2015 RE: Change Order No. 2 for Public Works Contract No. 13-24 WWTP Control System, Influent Pumping, &Aeration System Blower Upgrades August Winter and Sons, Inc./$90,275 BACKGROUND Change Order No. 2 for Contract 13-24 is scheduled for consideration by the Common Council at the May 26, 2015 meeting. The contract was originally awarded to August Winter and Sons in January 2014 to replace aging influent pumping equipment, control systems, and aeration system blowers. When replacing and retro fitting equipment in a production facility setting, we occasionally encounter conditions that were unanticipated and require modifications to the plans. We also encounter situations where improvements can be made to add long-term value to the project. The project is approximately 40%complete. ANALYSIS The four major items in this change order include: upgrading to LED light fixtures in the influent wastewater screening area, which will reduce lighting operation and maintenance cost in a hazardous area; enlarging the concrete pad and removing unsuitable soils in the area of the new transformer; adding labeling to the wiring in the supervisory control centers to show existing wire numbers and new wire numbers for trouble shooting purposes; and modifying electrical wire feeders to adjust for site conditions and electrical code requirements in the pump room. All items related to this change order was reviewed by CH2M HILL, our consultant on the project, and were found to be reasonable and within expected costs for the work performed. FISCAL IMPACT The original contract amount was for $4,210,500. Change Order No. 1 decreased the budget by $50,000. Change Order No. 2 is for $90,275. The revised contract price with this change order is $4,250,775. This project is included in the 2014 Capital Improvements Program under the Major Equipment(Sewer Utility Fund). RECOMMENDATIONS I recommend approval of Change Order No. 2 to Contact No. 13-24 in the amount of$90,275 to August Winter and Sons, Inc. Approved: Mark A. Rohloff City Manager SMB/tit BEngir erin0\13-24 WWrP Ctrl Snl Infuent Pump,flAeration Blower Upgrade\Correspondenc IMemol3-24 CO#2 Memo_5-21-15 LLacx