Appleton, WI 54914
Subject: Change Order No. 1
Contract 14-06
Dear Mr. Fischer:
Enclosed is an executed copy of Change Order No. 1 between the City of Oshkosh and Jim Fischer, Inc.
regarding the abovementioned project.
If you have any questions,please call our office at(920)236-5065.
Sincerely,
- � p�����-
���
David C. Patek / v`
Director of Public Works
DCP/tlt
Enclosure: Change Order No. 1
cc: Pam Ubrig, City Clerk(w/original)
Lynn Lorenson, City Attorney (w/copy)
Tara Wendt, Assistant Finance Director (w/copy)
File (w/original)
I:�Engineering�2014 CONTRACTSU4-06 Conc Sidewalk(New&Rehab)�Pmject_Information\Contract Info\Change Page 1 Of 1
Orders\14-06 Executed CO#1 Ltr 3-11-1S.docz
TO: Jim Fischer, Inc. CHANGE ORDER#1
2635 South Casaloma Drive DATED: February 17, 2015
Appleton, WI 54914
Your present contract with the City of Oshkosh, Contract No.14-06, awarded March 11, 2014, is hereby
amended and changed as follows:
NET INCREASE TO: SECTION I - PAVING 186,602.59
NET INCREASE TO: SECTION II - STORM SEWER (35.11)
NET INCREASE TO CONTRACT $186,567.48
Section I Section II Section III Section IV
(Paving) (Storm) (Sanitary) (Water) Totals
Bid Total $643,274.70 $900.00 $0.00 $0.00 $644,174.70
C.O. #1 $186,602.59 ($35.11) $186,567.48
Contract Total $829,877.29 $864.89 $0.00 $0.00 $830,742.18
CITY OF OSHKOSH
BY:
Recommended: � � City Manager ^
�` � , ) � �,r
��d ��� �� �
Director of Public Works City Clerk �
rov and cept �
Co 'actor
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin,
under the within Change Order.
�l�.Q,• b�v
�.r.�,��, mptroller
Approved as t rm:
Cit
CONTRACT 14-06 CHANGE ORDER#1
SECTION I-PAVING
ITEM BID INSTALLED NET NET UNIT /NCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT qUANTITY QUANTITIES INCREASE DECREASE PRICE CONTR,4CT CONTRACT
PRICE PRICE
1110 Removing curb and gutter, Linear
complete as specified Feet 200 0.00 -200.00 $2.00 ($400.00)
1120 Removing concrete and
asphalt sidewalk and
driveway,complete as Square
s ecified Feet 80,250 83,203.95 2,953.95 $0.95 $2,806.25
1308 7"concrete pavement
removal and replacement,
including sawing,
pavement ties, integral
curb and grading,
excavating,6"CABC,
terracing,and traffic
control,complete as Square
s ecified Yards 600 1,230.22 630.22 $47.00 $29,620.34
1318 8"concrete pavement
removal and replacement,
including sawing,
pavement ties,integral
curb and grading,
excavating,6"CABC,
terracing,and traffic
control,complete as Square
s ecified Yards 1,750 1,427.72 -322.28 $50.00 ($16,114.00)
1319 8"concrete pavement
SHES removal and
replacement,including
sawing,pavement ties,
integral curb and grading,
excavating,6"CABC,
terracing,and traffic
control,complete as Square
s ecified Yards 350 642.09 292.09 $52.50 $15,334.73
1350 Pavement ties,complete
as s ecified Each 300 0.00 -300.00 $1.50 $450.00)
1360 Adjust manholes and
inlets,complete as
s ecified Each 5 4.00 -1.00 $200.00 ($200.00
1370 Terrace work,complete as Square
s ecified Yards 200 151.84 -48.16 $4.50 ($216.72)
1390 Concrete patches, Square
com lete as s ecified Yards 75 0.00 -75.00 $50.00 ($3,750.00
1410 12"radius curb with 6"
CABC and grading, Linear
com lete as s ecified Feet 250 58.10 -191.90 $2.00 $383.80)
1440 30"curb and gutter,7"with
5"CABC and grading,
complete as specified Linear
Feet 200 531.40 331.40 $19.00 $6,296.60
1460 Sidewalk curb,complete as Linear
s ecified Feet 25 33.00 8.00 $15.00 $120.00
1500 4"concrete sidewalk with
3"CABC and grading, Square
com lete as s ecified Feet 58,110 63,862.50 5,752.50 $3.52 $20,248.80
Page 1 of 3
CONTRACT 14-06 CHANGE ORDER#1
ITEM BID INSTALLED NET NET UNIT �NCREASE IN DECREASE!N
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTR,4CT CONTRACT
PRICE PRICE
1502 4"concrete sidewalk with
3"CABC and grading,
water department
locations,complete as Square
s ecified Feet 2,500 4,785.84 2,285.84 $6.15 $14,057.92
1510 6"concrete sidewalk/
driveway/ramp with 3"
CABC and grading, Square
com lete as s ecified Feet 19,900 36,862.81 16,962.81 $3.95 $67,003.10
1512 6"concrete sidewalk/
driveway/ramp with 3"
CABC and grading,water
department locations, Square
com lete as s ecified Feet 2,500 2,355.34 -144.66 $7.00 ($1,012.62)
1520 8"concrete sidewalk/
driveway/ramp,with 3"
CABC and grading, Square
com lete as s ecified Feet 150 2,482.35 2,332.35 $7.40 $17,259.39
1540 Curb ramp detectable
warning field(natural/non-
painted),complete as Square
s ecified Feet 200 272.00 72.00 $26.00 $1,872.00
1550 No.4 reinforcing rods-
deformed,epoxy-coated, Linear
com lete as s ecified Feet 3,000 2,013.50 -986.50 $1.00 ($986.50)
1560 Drilled No.4 sidewalk tie
bars-deformed,epoxy-
coated,complete as
s ecified Each 4,500 7,127.00 2,627.00 $1.50 $3,940.50
1580 Cold weather covering
(sidewalk)-single
visquine,complete as Square
s ecified Feet 1,000 4,088.39 3,088.39 $0.01 $30.88
1582 Cold weather covering
(sidewalk)-double
visquine),complete as Square
s ecified Feet 1,000 0.00 -1,000.00 $0.01 $10.00)
1584 Cold weather covering
(sidewalk)-double
visquine with 6"hay, Square
com lete as s ecified Feet 500 0.00 -500.00 $0.01 ($5.00)
1590 Up-charge for late season
concrete sidewalk,
driveway,or ramps, Square
com lete as s ecified Feet 500 1,179.51 679.51 $0.75 $509.63
1591 Up-charge for late season
concrete pavement, Square
com lete as s ecified Yards 100 323.15 223.15 $4.50 $1,004.18
1700 Sawing existing pavement,
complete as specified Linear
Feet 6,000 11,348.10 5,348.10 $2.00 $10,696.20
1720 Profile saw cut concrete
curb,complete as specified Linear
Feet 25 15.00 -10.00 $30.00 ($300.00
1800 Base aggregate dense,'/.",
com lete as s ecified Tons 150 36.44 -113.56 $14.00 $1,589.84)
Page 2 of 3
CONTRACT 14-06 CHANGE ORDER#1
ITEM 8!D INSTALLED NET NET UNIT �NCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
1820 Re-grade existing gravel
driveways,complete as
s ecified Tons 75 7.10 -67.90 $20.00 $1,358.00)
1906 4"asphaltic pavement with
10"CABC and grading, Square
complete as specified Yards 2,000 2,716.53 716.53 $35.00 $25,078.55
1920 2"asphaltic pavement,
complete as specified Square
Yards 100 0.00 -100.00 $25.00 ($2,500.00
SECTION I-(BID ITEMS 1110-1920)-SUB-TOTAL $215,879.07 ($29,276.48)
NET INCREASE TO: SECTION I $186,602.59
SECTION II-STORM SEWER
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
2856 Furnish,install,maintain,
and remove Type D inlet
protection,complete as
s ecified Each 10 21.00 11.00 $40.00 $440.00
2932 Furnish and install Class I,
Urban,Type A erosion
control mat,complete as Square
s ecified Yards 1,000 49.77 -950.23 $0.50 ($475.11
SECTION II-(BID ITEMS 2856-2932)-SUB-TOTAL $440.00 ($475.11)
NET DECREASE TO: SECTION II ($35.11)
NET INCREASE TO SECTIONS I&il $216,319.07
NET DECREASE TO SECTIONS I&II ($29,751.59)
NET INCREASE TO CONTRACT: $186,567.48