HomeMy WebLinkAboutAECOM /Sediment THickness Verification . �,�0� AECOM 920.235.0270 tel
558 North Main Street 920.235.0321 fax
Oshkosh,Wisconsin 54901
RECEIVED
FEB 12 2015
February 12, 2015 DEPT OF PUI3LIC WORKS
OSNKOSH, WISCONSIN
Mr. James Rabe
City of Oshkosh
215 Church Avenue
PO Box 1130
Oshkosh, Wisconsin 54903-1130
Subject: Proposal for Sediment Thickness Verification of City of Oshkosh Storm Water
Basins, Oshkosh,Wisconsin—AECOM Proposal No OPP-351248
Dear Mr. Rabe,
AECOM Technical Services, Inc. (AECOM) is pleased to present this proposal for professional
environmental engineering services related to verifying sediment thickness at the following basins:
• Fair Acres, Murdock Avenue;
• Northwest Industrial Park Detention Basin ;
• Southwest Industrial Park, Global Parkway Extension Detention Basin; and
• Southwest Industrial Park, Phase I and Phase II, Wet Pond-2W and Wet Pond-2E.
This proposal presents our understanding of this project based upon our site knowledge, and
information provided to us by the City of Oshkosh, and outlines our recommended scope of work
and estimated fee for completing this project.
Proiect Understandinq
The City of Oshkosh (City) is currently considering evaluating the sediment collection quantities in
the various storm water detention basins referenced above. These basins have been in operation
for approximately 10 years and the information will be used to plan future monitoring and
maintenance of the basins. Long range planning includes probable dredging and disposal of
sediment accumulating in the basins. While we do not expect dredging to be required at this point,
this information will be used to prepare a maintenance schedule and a budget. We propose the
following scope of work tasks:
Task A: Prepare a GIS Based Information Data Collection System
Task B: Prepare a Health and Safety Plan for Working In and Around a Water Hazard Situation
Task C: Field Investigation to Measure Approximate Sediment Thickness
Task D: Prepare a Summary Report of Data Collection Methods and Results of Field Investigation
This document includes proprietary data that shall not be duplicated,used or disclosed outside City of Oshkosh for any purpose other than to
evaluate this document.This restriction does not limit City of Oshkosh's right to use information contained in this document if it is obtained from
another source without restriction.
OPP-351248_Stormwater Basin Sediment Thickness Verification Proposal.docx
AECOM 2
Scoae of Services
Task A: Prepare a GIS Based Information Data Collection System
The Yuma Data collector is proposed to be utilized for this project. This will allow field data to be
quickly recorded in a consistent format. The recorded information will include GPS location
information (horizontal datum in County Coordinate System, South Zone NADD83 and the Vertical
Datum will be NAVD88). The benefits for this system include:
• Completion of all inspections and documentation on site electronically;
• Quick data capture;
• Project team has access to all reports and records;
• Custom web portal that provides a variety of data management and report tools;
• Eliminates discrepancies with hard copy data forms;
• Reduced issues with lost data forms and photos;
• Encourages completion of field data forms prior to moving to the next location;
• Provides one consistent source of field data; and
• Provides a basis to prepare an electronic file that can be imported into the City GIS system.
Task B: Prepare a Health and Safety Plan for Working In and Around a Water Hazard
Situation
Prior to conducting any field activities, AECOM will prepare a Health and Safety Plan (HASP) to
meet the standards outlined in 29 CFR 1910.120 (Hazardous Waste Operations and Emergency
Response) and will review HASP requirements with all personnel involved with the fieldwork prior to
commencing the activities. A qualified AECOM employee will be designated to perform as the Site
Health and Safety Officer and will be present during all fieldwork. Specific attention will be made to
working in and around a water hazard environment.
Task C: Field Investigation to Measure Approximate Sediment Thickness
AECOM proposes to mobilize a three person crew to each of the basins. Two of the staff will be
workers that go on the ice. One of the staff will stay on land and be the safety coordinator
responsible for accident reporting and/or safety actions. We intend to discuss with the City the
order of the basin investigations. Field results will be discussed daily with the City. One of the two
person crew will initially test the ice for safe thickness. We will require at least 4-inchs of good
quality ice to compete the work. Less than that will be deemed an unsafe condition and work will
not commence. Basin inlets will be avoided as these will be considered danger zones. Once the
ice is determined as meeting safe criteria, the two person crew will lay out the anticipated sampling
grid. In general, we anticipate collecting data from approximately 6 to 14 locations in each basin.
Sample locations and frequency will be modified based on the basin wet pool size, encountered
field conditions, and sediment thickness results.
Drilling of the holes, documenting top of sediment, verifying sediment thickness, and recording the
data will then commence. Anticipated equipment to be utilized is a transit and level to shoot an
accurate elevation of the top of Ice, a YUMA tablet and GPS antenna will be used to collect and
Use or disclosure of data contained on this sheet is subject to the restriction on the first page of this document.
K:\PROPOSAL\City of Oshkosh\OPP-351248_Stormwater Basin Sediment Thickness Verifcation\OPP-351248_Stormwater Basin Sediment
Thickness Verification Proposal.docx
AECOM 4
Terms and Conditions
Services described in this proposal will be performed on a time-and-expense/unit-cost basis. The
project services will be performed in accordance with the 2015 Negotiated Fee Schedule for various
elements of service we expect will be utilized providing the services outlined in this proposal. This
project will be complete per the negotiated April 2009 Negotiated Terms and Conditions.
Please indicate your acceptance of this proposal by having an authorized individual of the City
execute the attached Authorization Form and return it to our Oshkosh office. If you have any
questions regarding the proposed scope of services and corresponding costs, please contact us at
your convenience.
Of course, if you wish to discuss the terms, conditions, and provisions of our proposal, we would be
pleased to do so.
Sincerely,
`��
\ �� '
Albert Cole Paul F. Timm
Senior Program Manager Account Manager
Attachments:
Authorization Form
Use or disclosure of data contained on this sheet is subject to the restriction on the first page of this document.
K:\PROPOSAL\City of Oshkosh\OPP-351248_Stormwater Basin Sediment Thickness Verifcation\OPP-351248_Stormwater Basin Sediment
Thickness Verification Proposal.docx
' CO� AECOM 920.235.0270 tel
558 North Main Street 920.235.0321 fax
Oshkosh,Wisconsin 54901
February 12, 2015
I hereby certify that the necessary provisions have been made to pay the liability which will accrue
under this contract.
I hereby authorize AECOM to proceed with the scope of work for the Sediment Thickness
Verification of Several City of Oshkosh Storm Water Basins, Consulting Services, in Oshkosh,
Wisconsin as described in AECOM's proposal OPP-351248 dated February 11, 2015, with a budget
authorization of$21,565 under the general terms and conditions specified in the proposal.
ci.--� ����_.. <'��L - I`�j - 2 o r'�
Signatu Date
Mark A Rohloff
Print Name
City Manager
Title/Organization
<\� —
� _ � -
;�� � (�- �-C���
Signature Date
Pamela R. Ubrig;
Print Name
City Clerk
Title/Organization
�� ��'���
tur Date
Lynn A. Lorenson;
Print Name
City Attorney
Title/Organization
�Y'���A �i 1"��15
Signature Date
Trena Larson
Print Name
Director of Finance
Title/Organization
K:\PROPOSAL\City of Oshkosh\OPP-351248_Stormwater Basin Sediment Thickness Verifcation\OPP-351248_Stormwater Basin Sediment
Thickness Verification Proposal.docx
_ AECOM 6
I agree to accept invoices from AECOM via e-mail and not postal mail:
� Yes
Signature:
E-mail address:
Recipient Mr./Ms.:
Return to:
Name: Paul Timm
558 North Main Street
Address: Oshkosh, WI 54901
Fax: 920.235.0321
Phone: 920.236.6718
K:\PROPOSAL\City of Oshkosh\OPP-351248_Stormwater Basin Sediment Thickness Verifcation\OPP-351248_Stormwater Basin Sediment
Thickness Verification Proposal.docx