FEBRUARY 10, 2015 15-52 RESOLUTION
(CARRIED__7-0_____ LOST _______ LAID OVER _______ WITHDRAWN _______)
PURPOSE: APPROVAL OF CHANGE ORDER NO. 1 FOR PUBLIC WORKS
CONTRACT NO. 14-08 WITH DONALD HIETPAS & SONS, INC.
FOR VARIOUS WATER MAIN EXTENSIONS (+$33,719.60)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
DONALD HIETPAS & SONS, INC.
PO Box 166
Little Chute, WI 54140
Net Increase to contract: $33,719.60
PURPOSE: See attached Change Order.
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Acct. No. 317-0410-7480-03303 Special Assessments Fund – Water
541-1810-1799-00000 Water Utility – Construction in Progress
TO: Donald Hiefpas &Sons, Inc. CHANGE ORDER#1
PO Box 166 DATE: JANUARY 20, 2015
Litt(e Chute, WI 54140
Your present contract with the Cify of Oshkosh, Contract No. 14-08, awarded September 9, 2074, is hereby
,
amended and changed as follows:
NET INCREASE TO: SECTION I - PAVfNG $3,256.20
NET INCREASE TO: SECTfON li -STORM SEWER $14,112.40
NET INCREASE TO: SECTION IV-WATER MAIN $16,351.Q0
NET lNCREASE TO CONTRACT $33,719.60
Section I Section II Section IV
Paving Storm Sewer Water Main 7otals
Bid Total $91,728.65 $54,142.50 $639,055.00 $784,926.15
C.O, #1 $3,256.20 $'14,112.40 $16,351.00 $33,719.60
Confract 7otai $94,984.85 $68,254.9a $655,406.OQ $818,645.75
CiTY OF OSHKOSH
BY:
Recommended: City Manager
Director of Public Works City Clerk
Approved and accepte �
^�-r-�H��- rti t�p�s W���,,; E.,,f�-av—/S
�� ; � . ���o.. /S
C ractor
I certify that provision has been made to pay fhe liabifity that will accrue to the City of Oshkosh, Wisconsin,
under the within Change Order.
Comptroller
Approved as to form:
City Attorney
CONTRACT 14-08-CHANGE ORDER#1
SECTION I-PAVING
ADDITIONAL WORK REQUIRED: C.O.#1 -SECTION I
ITEM BID INSTALLED NET NET UNIT INCREASE 1N DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTR,4CT
PRICE PRICE
10000 Additionallabor,
equipment,and materials
to install hot mix asphalt as
temporary pavement, Square
complete as s ecified Feet 0.00 972.00 972.00 $3.35 $3,256.20
ADDITIONAL WORK: C.O.#1 -(ITEM 10000)-SUBTOTAL $3,256.20 $0.00
NET INCREASE TO: SECTION I $3,256.20
SECTION II-STORM SEWER
ADDITIONAL WORK REQUIRED: C.O.#1 -SECTION II
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTR,4CT
PRICE PRICE
20000 Furnish and install Pam
Covering,complete as Square
s ecified Yards 0.00 1,088.00 1,088.00 $0.80 $870.40
20001 Furnish and install 8"storm
sewer,complete as Linear
s ecified Feet 0.00 70.50 70.50 $58.00 $4,089.00
20002 Furnish and install Type 1
inlet,complete as specified
Each 0.00 3.00 3.00 $1,575.00 $4,725.00
20003 Connect to existing inlet,
complete as specified Each 0.00 1.00 1.00 $450.00 $450.00
20004 Additionallabor,
equipment, and materials
to install sediment logs
along the construction site
on 10/30/14 and 10/31/14,
complete as specified Lump
Sum 0.00 1.00 1.00 $3,978.00 $3,978.00
ADDITIONAL WORK: C.O.#1 -(ITEMS 20000-20004)-SUBTOTAL $14,112.40 $0.00
NET INCREASE TO: SECTION II $14,112.40
SECTION IV-WATER MAIN
ADDITIONAL WORK REQUIRED: C.O.#1 -SECTION IV
ITEM BID INSTALLED NET NET UNIT �NCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTR,4CT CONTR.4CT
PRICE PRICE
4036 Furnish and install 1"water
service(relay),complete as Linear
s ecified Feet 0.00 17.00 17.00 $45.00 $765.00
Page 1 of 2
CONTRACT 14-08-CHANGE ORDER#1
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
4048 Furnish and install 1"
corporation and stop box,
com lete as s ecified Each 0.00 1.00 1.00 $340.00 $340.00
4237 Furnish and install 8"45°
bend,complete as
s ecified Each 0.00 2.00 2.00 $350.00 $700.00
4457 Furnish and install 16"x
10"tapping valve and
sleeve,complete as
specified Each 0.00 1.00 1.00 $5,900.00 $5,900.00
40001 Furnish and install 6"MJ
anchoring coupling,
com lete as s ecified Each 0.00 8.00 8.00 $195.00 $1,560.00
40002 Abandonment of 16"x 10" Lump
tee,complete as specified Sum 0.00 1.00 1.00 $500.00 $500.00
40003 Additionallabor,
equipment,and materials
to cover stockpiled
contaminated soils on
10/1/14,complete as Lump
specified Sum 0.00 1.00 1.00 $950.42 $950.42
40004 Additionallabor,
equipment,and materials
to remove the casing pipe
from the existing main at
the tie-in on River Mill Road
on 10/2/14,compiete as Lump
specified Sum 0.00 1.00 1.00 $1,427.15 $1,427.15
40005 Additionallabor,
equipment,and materials
to investigate the location
of the water service on the
WIOUWASH Trail on
10/10/14,complete as Lump
specified Sum 0.00 1.00 1.00 $2,912.38 $2,912.38
40006 Additionallabor,
equipment,and materials to
continue investigating the
location of the water
service on the
WIOUWASH Trail on
10/13/14,complete as Lump
specified Sum 0.00 1.00 1.00 $1,296.05 $1,296.05
ADDITIONAL WORK: C.O.#1 -(ITEMS 4036-40006)-SUBTOTAL $16,351.00 $0.00
NET INCREASE TO: SECTION IV $16,351.00
NET INCREASE TO SECTIONS I,II,&IV $33,719.60
NET DECREASE TO SECTIONS I,Ii,8�IV $0.00
NET INCREASE TO CONTRACT: $33,719.60
Page 2 of 2
�
O HKO H
ON THE WATER
MEMORANDUM
TO: Honorable Mayor and Members of the Common Council
FROM: Steven M. Gohde, Assistant�irector of Public Works SM9
DATE: February 5, 2015
RE: Change Order No. 1 for Public Works Contract No. 14-08
Various Water Main Extensions
Donald Hietpas & Sons, Inc. (+$33,719.60)
BACKGROUND
Change Order No. 1 for Contract 14-08 is scheduled for consideration by the Common Council at the February
10, 2014 meeting. The contract was originally awarded to Donald Hietpas & Sons, Inc. in September of 2014.
This change order is for additional services provided.
ANALYSIS
Following is a summary of the significant changes to the Water Main section of the CIP:
• Water Main — Additional time and materials were needed to install temporary pavement and soil
stabilizing material for late season construction due to the delay in obtaining the necessary permits; to
install storm sewer at Water Distribution; to install sediment logs instead of silt fence because the
WDNR permit required that the construction fence be installed prior to the silt fence installation; and to
locate the water service at the end of the WIOUWASH trail.
FISCAL IMPACT
Contract Section Chan e Order Amount New Contract Total CIP Bud et Amount
Water Main $33,719.60 $818,645.80 $890,000.00
Total $33,719.60 $818,645.80 $890,000.00
Adequate funds are available in the Water Main section of the 2014 Capital Improvement Budget.
RECOMMENDATIONS
I recommend approval of Change Order No. 1 to Contact No. 14-08 in the amount of +$33,719.60 to Donald