January 6, 2015
Mr. Allen Davis
Mr. Jim Collins �
City of Oshkosh
215 Church Avenue
PO Box 1130
Oshkosh,Wisconsin 54903-1130
Subject: Proposal for Environmental Services, Construction Documents, Bidding, and
Construction Management for Proposed at Riverside Park Parking Lot Phase
II and Boatworks Riverwalk Parking Lot Improvements, Oshkosh,Wisconsin,
City Contract Number 15-23
AECOM Proposal No. OPP-330820
Dear Mr. Davis and Mr. Collins,
AECOM Technical Services, Inc. (AECOM) is pleased to present this proposal for the above-noted
projects. We have prepared this proposal based on our understanding of the projects and previous
involvement. This proposal presents our approach, scope of services, schedule, and fee estimate.
We recommend combining these projects into one bid package as this will reduce the effort to
prepare the bidding documents, and administer the bidding process, as well as providing a scope of
construction work of sufficient size to promote competitive bidding and therefore potentially reduce
project costs.
Project Understanding—Riverside Parking Lot Phase II
AECOM assisted the City of Oshkosh in with design and construction of Phase I in 2014. We
understand the City of Oshkosh (City)would like to implement the Phase II improvements with final
completion by October 31, 2015, (landscaping preferably completed by mid-September).
AECOM's approach—we will provide a Phase II improvements plan set based on the as-built
records for Phase I. A project manual with the bidding and contract requirements will be prepared
to combine Phase II with the proposed Boatworks Riverwalk Parking Lot referenced below. Bidding
assistance and construction management will also be provided by AECOM staff.
Project Understanding—Boatworks Rivewalk Parking Lot
AECOM assisted the City in obtaining a grant to help defray development costs of this parking lot in
2014. We anticipate our services outlined below will be eligible for grant reimbursement. This
parking lot is considered access and parking for the Riverwalk segments on the south shore of the
Fox River. In addition, this parking lot will provide parking and access to the Fishing Pier.
This document includes proprietary data that shall not be duplicated,used or disclosed outside City of Oshkosh for any purpose other than to
evaluate this document.This restriction does not limit City of Oshkosh's right to use information contained in this document if it is obtained from
another source without restriction.
OPP-330820_Boatworks and Riverside Parking Lot CM Proposal Revised.docx
AECOM 2
AECOM's approach —we will provide final design of the Boatworks Riverwalk Parking lot based on
Oshkosh Site Plan Review comments received in 2014. Bidding documents will be prepared and
combined with the proposed Riverside Parking Lot Phase II referenced above. Bidding assistance
and construction management will also be provided by AECOM staff.
This proposal includes:
• Kickoff Meeting with stakeholders of the respective Projects
• Final Design and Preparation of Construction Documents suitable for bidding
• Permit and Approval applications
o Riverside Parking Lot Phase II Permits already received
o Amend Existing Permits for Boafinrorks Riverwalk also including adding the Restroom
• Bidding Assistance and Contract Preparation
• Construction Monitoring/Management
AECOM Assumptions
This proposal assumes:
• The City will advertise for bids and place the bidding documents on Quest.
• The projects will be constructed in 15 weeks (May—September 2015).
• To expedite the processing of the landfill profile acceptance applications and soil removal
activities for this project, the City,will delegate authority to AECOM to sign the waste profile
application and transportation manifests on behalf of(acting as an agent for), the City.
AECOM understands the City will remain the responsible party for all final decisions
regarding management and disposal of contaminated materials encountered during this
project. By authorizing the proposal, the City will also be authorizing Paul F. Timm and his
designees of AECOM to act as the authorized agent for the City for completion of the waste
profile and transportation manifests, as needed, for the disposal of the contaminated soil
and/or sediment under this contract.
Scope of Services
AECOM will perform the following:
Task 1 Final Desiqn and Construction Documents
• Develop a plan set; anticipated to consist of the following drawings: Updated Riverside
Parking Lot Phase II drawings based on Phase I as-builts. Updated Boatworks Riverwalk
Parking Lot drawings based on Site Plan Review Comments. The scope of work outlined
below is for both projects bidding documents.
o Cover Sheet with project location and drawing index
o Existing Conditions—Sunrey control - Demolition Plan
o Erosion Control Plan
o Erosion Control Details Sheet
Use or disclosure of data contained on this sheet is subject to the restriction on the first page of this document.
K:\PROPOSAL\City of Oshkosh\OPP-330820_Riverside Park&Boatworks Parking Lots CM\OPP-330820_Boatworks and Riverside Parking
Lot CM Proposal Revised.docx
AECOM 3
o Grading 8� Paving Plan—North Lot
o Grading & Paving Plan
o Bio-Retention Area Details Sheets
o Utility Plan
o Utility and General Details and Notes Sheet
o Landscaping Plan/Details
o Electrical Layout Plan (lighting 8�power)
o Electrical Details Sheet
• Assemble a project manual which will contain the bidding and contract requirements,
utilizing the City's Standard Specifications incorporated into 2010 version of EJCDC
documents.
• Prepare an opinion of construction cost at the Final Completion level of design for each
project.
• Hold a kickoff meeting and a review meeting at the 95%completion level for each project.
Deliverables: Three hard copies of the Draft plan set and project manual for City review at the 95%
completion level. One hard copy and electronic copy of the final plan set and project manual.
Task 2 Permit and Approval Aqplications
• Prepare an amendment request notification for the Boatworks Parking lot to Wisconsin
Department of Natural Resources(WDNR) and Army Corps of Engineers (COE). We
anticipate one amendment will be sufficient. If a new application is required, we will notify
the City for authorization to amend our budget accordingly.
• Permit applications were previously submitted and approved for Riverside Parking Lot.
WPDES Permit No WI-S067831.4 dated September 09, 2013 is active for three years.
Task 3 Bidding Administration and Contract Preparation
• Prepare/Coordinate a pre-bid conference.
• Answer bidder's questions and issue addenda (if needed).
• Attend the bid opening, and assist with recommending a contractor.
• Prepare a contract for signature by the City and contractor.
Deliverables: CD's containing the Plan Set and Project Manual in a PDF and Microsoft Word
format. Prepare a memorandum on contractor selection based on the bidding results. Three hard
copies of the project manual and associated plan set.
Use or disclosure of data contained on this sheet is subject to the restriction on the first page of this document.
K:\PROPOSAL\City of Oshkosh\OPP-330820_Riverside Park 8 Boatworks Parking Lots CM\OPP-330820_Boatworks and Riverside Parking
Lot CM Proposal Revised.docx
AECOM 4
Task 4 Construction Documentation
Provide a Resident Project Representative (RPR) to coordinate/monitor/document construction, and
work with the City and Contractor on administration issues. Provide part-time field and laboratory
testing to document compliance or noncompliance with project plans and specifications. Our budget
is based on a 15 week(10 weeks for Riverside Park Parking Lot Phase II and 5 weeks for
Boatworks Riverwalk Parking lot project)construction time frame.
A summary of tasks is provided below.
• Provide a full-time on-site RPR(or as project requirements dictate), during construction
events.
• Provide part time on-site testing staff, as needed during the project.
• Work as interface befinreen stake holders and contractor.
• Review contractor's progress schedule, schedule of submittals/submissions, and schedule of
values prepared by contractor, and consult with the City concerning their appropriateness.
• Serve as the liaison with the City and contractor, and assist them in understanding the intent
of the contract documents.
• Review contractor submittals and material samples for conformance with contract documents,
and notify the City of their availability for examination and non-conformance.
• Conduct site observations of the work in progress, determine if the work is generally
proceeding in accordance with the contract documents and that completed work conforms to
the contract documents.
• Transmit to contractor the City's clarifications and interpretations of the contract documents.
• Maintain correspondence files, reports of job conferences, shop drawings and sample
submissions, reproductions or original contract documents including all addenda, change
orders, field orders, and additional drawings issued subsequent to the execution of the ,
contract.
• Maintain reports for the construction contract recording hours on the job site; weather
conditions when on the job site; data relative to questions of extras or deductions; list of
visiting officials, representatives of manufacturers, fabricators, suppliers and distributors;
daily activities; decisions; observations in general; and specific observations in more detail
as in the case of observing test procedures.
• Record names, addresses, and telephone numbers of the general contractor,
subcontractors, and major suppliers of materials and equipment.
• Prepare necessary field modifications and change orders in accordance with instructions of
the City. Field modifications are conditions that require no adjustment on the contract cost
or time of completion. Change orders require modification of cost and/or time of
completion.
• Furnish the City with monthly reports of progress of the work and the Contractor's
compliance with the approved progress schedule. Attend monthly progress meetings at the
jobsite with the City to discuss progress of work. Keep the City informed of any expected
delays in progress schedule.
Use or disclosure of data contained on this sheet is subject to the restriction on the first page of this document.
K:\PROPOSAL\City of Oshkosh\OPP-330820_Riverside Park&Boatworks Parking Lots CM\OPP-330820_Boatworks and Riverside Parking
Lot CM Proposal Revised.docx
AECOM 5
• Report to the City whenever RPR believes any work is unsatisfactory, faulty or defective, or
does not conform to the Contract Documents, and advise if work should be corrected or
rejected.
• Where applicable, witness field testing of the facilities furnished under the contract to assist
in determining conformance with the contract documents.
• Notwithstanding that it is the contractor's sole responsibility for job site safety, AECOM will
report immediately to the City the occurrence of any accident.
• Review applications for payment from the contractor for compliance with the established
procedure for their submission, and forward with recommendations to the City noting
relation to the schedule of values, work completed, materials and equipment delivered at
the site, but not incorporated in the work.
• Before AECOM issues the"Certificate of Substantial Completion,"submit to the contractor
a list of observed items requiring completion or correction.
• Conduct a final inspection in the company of the City and contractor, and prepare a final list
of items to be completed or corrected.
• Provide Field and Laboratory material testing to document conformance with plans and
specifications. At this time we anticipate gradation testing of gravel/rip rap fill, compaction
control testing, cast-in-place concrete placement monitoring.
• Provide photo documentation throughout the construction period.
• Provide vehicles, necessary equipment, and material for inspection.
• Provide four site visits by Engineering design team during construction to verify design
criteria.
Construction Layout: Survey layout associated with earthwork grading, alignments, approaches,
storm sewer grades, and lighting. Eight(8)-10 hour trips to the site, (for each project) along with
associated mileage and equipment rental, are included in the fee estimate.
As-Record Plans: Pertinent information recorded by the RPR, along with surveyed elevations of key
features (such as pipe inverts, curb and surface grades, etc)will be drafted onto the plan set and
noted as"As-Record" information. This information can be placed in City files.
Deliverables: Correspondence and submittal information as described in this task scope. As-
Record plan set in AutoCAD format.
AECOM proposes a design and construction management team comprised of:
Paul Timm - Project Manager
Mark Magee- RPR
Terry Peterson P.E. - Design Lead and Civil Engineer
Jeremy Thomas P.E. -Geotechnical Engineer
Use or disclosure of data contained on this sheet is subject to the restriction on the first page of this document.
K:\PROPOSAL\City of Oshkosh\OPP-330820_Riverside Park&Boatworks Parking Lots CM\OPP-330820 Boatworks and Riverside Parking �
Lot CM Proposal Revised.docx
AECOM 6
Project Schedule
The following schedule has been prepared assuming a construction start of May 2015 and ending
September 2015.
Project Kickoff Meeting with Stakeholders: January 2015
95% Review Plan Set and Project Manual: End February 2015
Final Construction Documents for bidding: Mid-March 2015
Bid Opening: Early April 2015
City Council Approval & Contracts signed: Mid-April 2015
Preconstruction Meeting and Contractor Mobilization: Early May 2015
Construction (20 weeks): May to September 2015
Project Closeout: November 2013
Project Fees
We propose to perform the above-noted scope of services for the following estimated fees:
Task Descriqtion Estimated Fee
Task 1 Final Design and Construction Documents
Riverside Park Phase 2 (100 hours, $1,000 Expenses) $12,000
Boatworks Riverwalk Parking Lot(135 hours, $1,000 Expenses) $17,000
Task 2 Permit and Approval Applications
Riverside Park Phase 2 $0
Boafinrorks Riverwalk Parking Lot(35 hours) $4,000
Task 3 Bidding Administration and Contract Preparation
Riverside Park Phase 2 (25 hours) $4,000
Boafinrorks Riverwalk Parking Lot(25 hours) $4,000
Task 4 Construction Documentation and Project Management
Riverside Park Phase 2 (450 Hours, Expenses$3,100,
Survey$10,000) $66,850
Boatworks Riverwalk Parking Lot(225 Hours, Expenses$2,100
Survey$10,000) 33 980
Subtotal Riverside Parking Lot Phase 2 $82,850
Subtotal Boafinrorks Riverwalk Parking Lot �$Q
Total Estimated Fee: $141,830
Task 4 budget reflects a schedule of completing both projects independently. As with all City
projects, AECOM will only bill for actual time and expenses incurred. Project budgets for each
parking lot will be tracked separately. If the projects overlap there could be savings realized in
completing task 4
Use or disclosure of data contained on this sheet is subject to the restriction on the first page of this document.
' K:\PROPOSAL\City of Oshkosh\OPP-330820_Riverside Park&Boatworks Parking Lots CM\OPP-330820_Boahvorks and Riverside Parking
Lot CM Proposal Revised.docx
AECOM 7
Terms and Conditions
Services described in this proposal will be performed on a time-and-expense/unit-cost basis. The
on file 2015 Negotiated Fee Schedule and 2009 Negotiated Terms and Conditions of Service
indicate the unit prices and terms for various elements of service we expect will be utilized to
provide the services outlined in this proposal.
Please indicate your acceptance of this proposal by having an authorized individual of your firm
execute the attached Authorization Form and return it to our Oshkosh office. If you have any
questions regarding the proposed scope of services and corresponding costs, please contact us at
your convenience.
Of course, if you wish to discuss the terms, conditions, and provisions of our proposal, we would be
pleased to do so.
Sincerely,
.
' � � �—
. �
Terrance A. Peterson, P.E. Paul F. Timm
Principal Engineer Senior Project Manager
��������
Albert Cole
Senior Program Manager
Attachments:
Authorization Form
Use or disclosure of data contained on this sheet is subject to the restriction on the first page of this document.
K:\PROPOSAL\City of Oshkosh\OPP-330820_Riverside Park&Boatworks Parking Lots CM\OPP-330820_BOatworks and Riverside Parking
Lot CM Proposal Revised.docx
.� • �
��0� AECOM 920.235.0270 tel
558 North Main Street 920.235.0321 fax
Oshkosh,Wisconsin 54901
Authorization
January 6, 2015
I hereby certify that the necessary provisions have been made to pay the liability which will
accrue under this contract.
I hereby authorize AECOM to proceed with the scope of work outlined in the proposal for
Construction Documents, Bidding, and Construction Management for Riverside Park Parking Lot
Phase II and Boafinrorks Riverwalk Parking Lot Improvements, Oshkosh, Wisconsin City Contract
Number 15-23 as outlined in AECOM's Proposal No. OPP-330820 dated January 6, 2015 with a
budget authorization of$141,830 under the general terms and conditions specified in the
proposal.
- �7�c�—%�����/����!/i-�
Signa ure Date
Mark A Rohloff .
Print Name
City Manager
Titl anization
/- z� --� �
Si t r Date
� . ; �nti�l� S ���cK��
Print Name �
��`�` �t����-v C'_I� r I�_
Title/Organization
/ —�.b--�l�'
' at e Date
Lynn A. Lorenson;
Print Name
City Attorney
Title/Organization
�!"��nG ���Im I I�-�o(15
Signature Date
Trena Larson
Print Name
Director of Finance
Title/Organization
K:\PROPOSAL\City of Oshkosh\OPP-330820_Riverside Park 8 Boatworks Parking Lots CM\OPP-330820_Boatworks and Riverside
Parking Lot CM Proposal Revised.docx
. AECOM
9
I agree to accept invoices from AECOM via e-mail and not postal mail:
� Yes
Signature: �� ��� ; �
E-mail address: � ��r�, �f �� G� • cs�l (LC'.�� � ��� . �t�
Recipient Mr./Ms:
Return to:
Name: Paul Timm
Address: 558 North Main Street
Oshkosh, WI 54901
Fax: 920.235.0321
Phone: 920.236.6718