AECOM
1555 N RiverCenter Drive,Suite 214
Milwaukee,WI 53212
T 414-944-6080 F 414-944-6081 RECEIVED
JUL 2 2 2014
Amendment to Agreement Form DEPT. OF PUBLIC WORKS
OSHKOSH, WISCONSIN
Amendment No. 3
Campbell Creek Storm Water Modeling and Design
AECOM Project No. 60188754
City PO No. 114990
RETURN TO: AECOM Date: June 26, 2014
1555 N RiverCenter Drive, Suite 214
Milwaukee, WI 53212
Attention: Chuck Boehm
SUMMARY: Original Contract Amount: $381,320
Total Previous Amendment: $ 95,423
Amount of this Amendment: $ 62,698
Revised Contract Amount $539,441
Amendment# DESCRIPTION AMOUNT
3
$ 62,698
See Attached Amendment Memo.
All other project conditions remain
unchanged.
Total $ 62,698
AECOM City of Oshkosh
By:
ul F. Timm
Title: Account Manager Title:
Date: 6/26/2014 Date:
AECOM
By:
Patrick Clifford
Title: District Manager
Date: 6/26/2014
A=COM AECOM 920.235.0270 tel
558 North Main Street 920.235.0321 fax
Oshkosh,WI 54901
Authorization
June 26, 2014
I hereby certify that the necessary provisions have been made to pay the liability, which will accrue
under this contract.
I hereby authorize AECOM to proceed with the scope of work as outlined in Amendment 3, AECOM
project number 60188754, City PO number 114990, for the Campbell Creek Storm Water
Modeling and Design as described in AECOM's proposal, with a revised budget authorization of
$539,441.00 under the general terms and conditions specified in the proposal.
A it-tqu ST 151 zo `E-
Signature Date
Mark A Rohloff
Print Name
City Manager
• - e •anization --�
11' AllA PA 5-Q,C1
Signature Date
Pamela R. Ubrig
Print Name
City Clerk
Title/_• •anization
•I.t e Date
Lynn A. Lorenson
Print Name
City Attorney
Title/Organization
,i i J� WW1- 0(4
Signature Date
spina L arson Tatra, Y th/!
Print Name
Director of Finance/Vf'SPu<L
Title/Organization
AECOM Environment 2
I agree to accept invoices from AECOM via e-mail and not postal mail:
El Yes
Signature:
E-mail address:
Recipient Mr/Ms:
Return to:
Name: Paul Timm
Address: 558 N. Main Street, Oshkosh, WI 54901
Phone: 920-236-6718/920-236-6712
e-mail: Paul.Timm @aecom.com
ACOM AECOM 608 836 9800 tel
1350 Deming Way 608 836 9767 fax
Suite 100
Middleton,WI 53562
www.aecom.com
RECEIVED
Memorandum
JUL 222.014
DEPT. OF PUBLIC WORKS
OSHKOSH, WISCONSIN
To James Rabe, PE, CPESC Page 1
cc Paul Timm (AECOM)
Request for Project Budget Amendment#3: Campbell Creek Storm Water
Modeling and Design
AECOM Project#: 60188754
Subject City P.O.# 114990
Chuck Boehm, Project Manager
From Theran Jacobson, Project Engineer
Date June 26, 2014
This memo requests an amendment to the above referenced agreement. The amendment is necessary to cover
the costs of the additional/out of scope work conducted on the project under the City's direction. The items
described below are also described in more detail on a table at the end of this memo.
Below is a description of each out of scope item along with an amendment request budget.
Design of 9th and Washburn Area Detention Basin Permits(City Scope Task 12,AECOM Budget Task 10)
1. Additional modeling to evaluate impact of modified detention basin and local storm sewer extension to
expand the benefits of the available detention pond capacity and provide reduced flood stage, extent
and duration to assist in alternatives analysis.
2. Additional phone calls (including January 16th and April 8th 2014 teleconferences)and meetings with
City and Attorney during development of alternatives analysis and preparation for and following the third
Agency meeting.
3. Additional Agency(WDNR/USACOE) meeting (January 23,2014) regarding wetlands impacts
discussion and alternatives analysis.
4. Expanded alternatives analysis document based on updated modeling effort, expanded concepts and
material recommended by Attorney, and other updates to state a stronger case for the recommended
alternative.
5. Additional permitting support including responding to agency comments and assistance with obtaining
needed permit approvals.
Design of 9th and Washburn Area Detention Basin Design (City Scope Task 12,AECOM Budget Task 6)
1. Proposed structural design of three additional box manholes due to alternatives analysis modeling
proposing the use of 4'x8' box pipe.
2. Proposed structural design of apron and wing walls for 5'x8'discharge pipe
Campbell Creek Amendment 3 Memo April 2014-Final.docx
AECOM .
Design of Armory Detention Basin(City Scope Task 13,AECOM Budget Task 7)
1. Effort associated with modifying plans to design and incorporate new stockpile locations for spoil
material from the Armory excavation.
2. Effort associated with modification of specifications to adjust availability of disposal locations
3. Additional structural design efforts to detail out 3 box manhole structures as directed by City staff at
November,2013 update meeting
Summary
The total amendment request is provided below:
Amendment 3
Task Task Name Requested Original Current Budget Following
# Budget Budget • Amendment 3
Change
1 Survey $73,070 $86,797 $0 $86,797
2 Watershed H&H Model $31,480 $32,430 $0 $32,430
3 Design H&H Modeling $35,530 $37,840 $0 $37,840
4 Clubhouse Design $50,570 $63,170 $0 $63,170
5 West Park Design $37,180 $0 $0 $0
6 9th&Wash. Design $65,270 $65,270 $11,213 $76,483
7 Armory Design $52,810 $72,685 $8,940 $81,625
8 Meetings&PM $35,410 $37,860 $0 $37,860
9 Armory Wetland Permit $0 $62,043 $0 $62,043
10 9&Wash Wetland Permit $0 $18,648 $42,545 $61,193
Total: $381,320 $476,743 $62,698 $539,441
A more detailed breakdown of the amendment items and costs is attached to this memo.
Campbell Creek Amendment 3 Memo April 2014-Final.docx 2
A=COM
Additional Amendment Details:
Summary of Out of Scope Work Charged Hours Through June 13,2014 and additional future permitting support
Project Task# Item Hours Budget
Impacts
Budget Task 10: 9th & Additional Modeling/Analysis Boehm: 7 hrs $ 11,718
Washburn Permitting for additional pipe capacity Jacobson: 70.75 hrs
options, outlet structure pipe Bartlein: 26.5 hrs
modifications Hurlebaus: 5 hrs
Modahl:4.50 hrs
Budget Task 10: 9th & Additional Phone Calls/Meeting Boehm:4 hr $ 1,880
Washburn Permitting Time Jacobson:4 hrs
January 7, 2014;January 16, Majerus: 3 hrs
2014;April 8, 2014 Rubsam:4 hrs
Budget Task 10: 9th & Detailed Alternatives Analysis Boehm:4.25 hrs $ 5,309
Washburn Permitting memorandum; including Crotteau: 5 hrs
memo, H&H results tables, Gundlach: 0.50 hrs
figures, and updated cost Jacobson: 26.0 hrs
estimate Modahl: 4.50 hrs
Timm: 7.0 hrs
Budget Task 10: 9th & Preparation for January 23, Boehm: 6.5 hr $ 4,298
Washburn Permitting 2014 Agency Meeting. Jacobson: 19 hrs
Additional Agency Meeting Timm: 6 hrs
(January 23, 2014). Rubsam: 2 hrs
Budget Task 10: 9th & Alternatives Analysis Updates Boehm: 6 hr $ 4,170
Washburn Permitting Jacobson: 28 hrs
Engels: 2.5 hrs
Budget Task 10: 9th & Additional permitting support Boehm: 6 hr $ 15,170
Washburn Permitting including review comments Jacobson: 80 hrs
and permit related document Timm:40 hrs
development updates.
Task Total $ 42,545
Campbell Creek Amendment 3 Memo April 2014-Final.docx 3
Ai COM
Summary of Out of Scope Charged Hours Through June 13,2014
Budget Task 7:Armory Additional design effort $ 1,100
Design associated with stockpile Jacobson: 5 hrs
relocation Timm:4 hrs
Budget Task 7: Armory Additional specifications $ 1,250
Design changes associated with Jacobson: 8 hrs
disposal location adjustments Timm: 3 hrs
Budget Task 7:Armory Additional structural design $ 6,590
Design efforts to detail 3 box Jacobson: 5 hrs
structures Gahagan: 8 hrs
Schuenemann: 28
hrs
Everson: 3 hrs
Rhimes: 19 hrs
Timm: 1 hr
Task Total $ 8,940
Proposed Out of Scope Future Hours for additional tasks
Budget Task 6: 9th and Additional structural design for $ 6,555
Washburn Design 3 proposed box manholes Boehm: 1 hr
Jacobson: 6 hrs
Rhimes: 60 hrs
Everson: 8 hours
Budget Task 6: 9th and Additional structural design for $ 4,658
Washburn Design apron and wingwalls for 5'x8' Boehm: 0.5 hr
discharge pipe Jacobson:4 hrs
Rhimes: 52 hrs
Task Total $ 11,213
Amendment Total: $62,698
Campbell Creek Amendment 3 Memo April 2014-Final.docx 4