HomeMy WebLinkAboutPW CNT 11-06/CHG OR No 2/Fischer-Ulman DEPARTMENT OF PUBLIC WORKS
215 Church Avenue
P.O.Box 1130
Oshkosh,Wisconsin 54903-1130
Ph.(920)236-5065 OJHKOJH
Fax(920)236-5068
ON THE WATER
June 24, 2014
Bill Ulman
Fischer-Ulman Construction Inc.
1115 South Theodore Street
Appleton, WI 54915
Re: Change Order No. 2 (Final)
Contract 11-06
Dear Mr. Ulman:
Enclosed is an executed copy of Change Order No. 2 (Final) between the City of Oshkosh and Fischer-
Ulman Construction Inc. regarding the abovementioned project.
If you have any questions, please call our office at(920)236-5065.
Sincerely,
David C. Patek
Director of Public Works
DCP/tlt
Enclosure: Change Order No. 2 (Final)
cc: Pam Ubrig, City Clerk(w/original)
Lynn Lorenson, City Attorney(w/copy)
Tara Wendt, Assistant Finance director(w/copy)
File (w/original)
I:\Engineering\201 I CONTRACTS\I1-06 Concrete Sidewalk-Rehab&New\Project_Information\Contract Page 1 of 1
Info\CHANGE ORDERS\11-06 Executed CO#2 Ltr 6-24-14.docx
CHANGE ORDER# 2 (FINAL)
DATED: June 3, 2014
TO: Fischer-Ulman Construction Inc.
1115 S Theodore St
Appleton WI 54915
Your present contract with the City of Oshkosh, Contract No. 11-06 , is hereby amended
and changed as follows:
NET DECREASE TO: SECTION I -CONCRETE SIDEWALK ($434.76)
NET INCREASE TO: SECTION II -STORM SEWER $0.00
NET DECREASE TO CONTRACT: ($434.76)
CITY OF OSHKOSH
BY: /!/1,.
Recommended: City Mai lager '
Director of Public Works City Clerk
Approved and accepted:
Ci ntractory /
YL61/l�-�
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
3fD !VA c7CCe ,`,OM
Comptroller
A•• oved as to •rm:
r
1AI?►.
Cit A •,ney
CONTRACT 11-06 CHANGE ORDER#2
SECTION I-CONCRETE SIDEWALK
ITEM BID CO#1 INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
100 Mobilization&construction
of temporary access for W.
9th Avenue sidewalk
construction,complete as Lump
specified Sum 1 -1.00 0.00 $1,500.00
101 Sidewalk removal&
driveway removal,
complete as specified Square
Feet 90,500 27,504.88 117,812.56 -192.32 $0.43 ($82.70)
102 Concrete/asphalt sawing,
complete as specified Linear
Feet 5,500 -165.90 5,334.10 $2.00
103 Construct 4"thick concrete
sidewalk in various
locations in the City of
Oshkosh,complete as Square
specified Feet 97,100 -2,932.37 94,045.81 -121.82 $2.89 ($352.06)
104 Construct 6"thick concrete
sidewalk in various
locations in the City of
Oshkosh,complete as Square
specified Feet 14,500 3,546.81 18,046.81 $3.17
105 Construct 7"thick
crosswalk areas,complete Square
as specified Feet 3,000 240.78 3,240.78 $3.30
106 Provide and install metal
detectable warning plates, Square
complete as specified Feet 216 72.00 288.00 $25.00
107 Three(3")inch asphalt
replacement,complete as Square
specified Feet 1,500 -453.00 1,047.00 $3.70
108 Curb and gutter removal, Linear
complete as specified Feet 300 63.40 363.40 $3.00
109 Construct 30"curb and
gutter,complete as Linear
specified Feet 300 96.80 396.80 $18.80
110 Terrace restoration,
including seed,fertilizer,
and mulch,complete as Square
specified Yards 2,750 -2,405.97 344.03 $4.00
111 Furnish and install
pavement ties,complete
as specified Each 100 5.00 105.00 $5.00
112 Construct 4"thick concrete
sidewalk in Water Dept.
repair locations at approx.
60 sites,complete as
specified Square
Feet 1,500 -26.62 1,473.38 $4.15
113 Construct 6"thick concrete
sidewalk in Water Dept.
repair locations at approx.
20 sites,complete as
specified Square
Feet 500 414.14 914.14 $4.30
Page 1 of 5
CONTRACT 11-06 CHANGE ORDER#2
ITEM BID CO#1 INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
114 7"non-reinforced concrete
pavement removal and
replacement,including
sawing,pavement ties,
integral curb&grading,
terracing&traffic control, Square
complete as specified Yards 75 -75.00 0.00 $41.40
115 8"non-reinforced concrete
pavement removal and
replacement,including
sawing,pavement ties,
integral curb&grading,
terracing&traffic control, Square
complete as specified Yards 1,750 -1,567.11 182.89 $42.15
116 8"special High Early
Strength,non-reinforced
concrete pavement
removal and replacement,
including sawing,
pavement ties,integral
curb and grading,terracing
and traffic control, Square
complete as specified Yards 100 -79.37 20.63 $48.50
117 Extra crushed stone base,
complete as specified Tons 300 -273.00 27.00 $13.00
118 No.4 epoxy-coated
reinforcement rods,
installed as specified Linear
Feet 520 1,180.00 1,700.00 $1.50
119 Construct 12"wide radius
curb head,complete as Linear
specified Feet 75 -15.00 60.00 $4.00
120 Furnish,install,and
maintain erosion mat, Square
complete as specified Yards 2,500 -2,500.00 0.00 $1.10
121 Profile sawcut concrete
curb,complete as Linear
specified Feet 50 -50.00 0.00 $26.00
122 Sidewalk curb,complete Linear
as specified Feet 40 -40.00 0.00 $40.00
123 Adjust manholes and
inlets,complete as
specified Each 2 -2.00, 0.00 $200.00,
124 Remove trees and stumps,
complete as specified Inch
Diameter 92_ -92.00 0.00 $12.00
SECTION I-(BID ITEMS 100-124)-SUB-TOTALS $0.00 ($434.76)
Page 2 of 5
CONTRACT 11-06 CHANGE ORDER#2
ITEM BID CO#1 INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
ADDITIONAL WORK REQUIRED: C.O.#1 -SECTION I
ITEM BID CO#1 INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
125 7"/7-bag non-reinforced
concrete removal&
replacement,including
sawing,pavement ties,
intregral curb&grading,
terracing&traffic control, Square
complete as specified Yards 0.00 74.23 74.23 $43.60
126 7"18-bag non-reinforced
concrete removal&
replacement,including
sawing,pavement ties,
intregral curb&grading,
terracing&traffic control, Square
complete as specified Yards 0.00 0.00 0.00 $45.80
127 8"/7-bag non-reinforced
concrete removal&
replacement,including
sawing,pavement ties,
integral curb&grading,
terracing&traffic control, Square
complete as specified Yards 0.00 1,222.96 1,222.96 $45.25
128 8"/8-bag non-reinforced
concrete removal&
replacement,including
sawing,pavement ties,
integral curb&grading,
terracing&traffic control, Square
complete as specified Yards 0.00 125.23 125.23 $46.04
129 9'17-bag non-reinforced
concrete removal&
replacement,including
sawing,pavement ties,
integral curb&grading,
terracing&traffic control,
Square
complete as specified Yards 0.00 157.30 157.30 $47.60
130 9"/8-bag non-reinforced
concrete removal&
replacement,including
sawing,pavement ties,
integral curb&grading,
terracing&traffic control, Square
complete as specified Yards 0.00 100.37 100.37 $49.82
131 7"/6-bag non-reinforced
concrete removal&
replacement,including
sawing,pavement ties,
integral curb&grading,
terracing&traffic control, Square
complete as specified Feet 0.00 533.61 533.61 $4.78
Page 3 of 5
CONTRACT 11-06 CHANGE ORDER#2
ITEM BID CO#1 INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
132 8"/9-bag non-reinforced
concrete removal&
replacement,including
sawing,pavement ties,
integral curb&grading,
terracing&traffic control, Square
complete as specified Feet 0.00 84.00 84.00 $5.72
133 Adjust Manhole,complete
as specified Each 0.00 1.00 1.00 $100.00
134 Repair Water Patch,
complete as specified Each 0.00 1.00 1.00 $50.00
135 5"/7-bag non-reinforced
concrete removal&
replacement,including
sawing,pavement ties,
integral curb&grading,
terracing&traffic control, Square
complete as specified Feet 0.00 226.24 226.24 $4.84
136 Sign Usage for Jackson
Street bridge pavement
repair
Each 0.00 1.00 1.00 $2,000.00
ADDITIONAL WORK: C.O.#1 -(ITEMS 125-136)-SUB-TOTAL $0.00 $0.00
NET DECREASE TO: SECTION I ($434.76)
SECTION II-STORM SEWER
ITEM BID CO#1 INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
2032 Furnish and install 8"
Storm Sewer,complete as Linear
specified Feet 6.00 -6.00 0.00 $45.00
2036 Furnish and install 12"
Storm Sewer with
endwalls,complete as Linear
specified Feet 60.00 -60.00 0.00 $48.00
2042 Furnish and install 15"
Storm Sewer with
endwalls,complete as Linear
specified Feet 60.00 -60.00 0.00 $55.00
2300 Furnish and install 12"
RCP Class Ill apron end
walls with joint ties,
complete as specified
Each 6.00 -6.00 0.00 $650.00
2302 Furnish and install 15"
RCP Class Ill apron end
walls with joint ties,
complete as specified Each 4.00 -4.00 0.00 $700.00
2532 Furnish and install Std.
Storm Manhole(4'inside
diameter)in one location
with casting,complete as
specified Each 1.00 -1.00 0.00 $1,750.00
Page 4 of 5
CONTRACT 11-06 CHANGE ORDER#2
ITEM BID CO#1 INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
2610 Furnish and install Type I
Inlet/with sump in one
location with casting,
complete as specified Each 1.00 -1.00 0.00 $1,300.00
2854 Furnish,install,and
maintain Type"C"inlet
protection,complete as
specified Each 5.00 -5.00 0.00 $40.00
2856 Furnish,install,and
maintain Type"D"inlet
protection std.,complete
as specified Each 74.00 -7.00 67.00 $40.00
2868 Furnish,install,and
maintain ditch checks,
complete as specified Each _ 8.00 -8.00 0.00 $100.00
SECTION II-(BID ITEMS 2032-2868)-SUB-TOTALS $0.00 $0.00
NET INCREASE TO: SECTION II $0.00
NET INCREASE TO SECTIONS I&II $0.00
NET DECREASE TO SECTIONS I&II ($434.76)
NET DECREASE TO CONTRACT: ($434.76)
Page 5 of 5