HomeMy WebLinkAbout82-17/CHG OR 1/Four Way Const CHANGE ORDER NO. 1
TO: FOUR-WAY CONST. OF WI, INC. DATED: January 28, 1983
P.O. Box 133
Berlin, WI 54923.
Your present contract with the City of Oshkosh, Contract No. 82-17 S
is hereby amended and changed as follows:
( insert here work and/or materials to be added or eliminated and
the unit and/or lump sum price to be added to or deducted from the
contract. )
ADD
15 hydrants @ $100 extra each= $1,500.00
A change in specifications to standardize on hydrants
that were less costly to maintain and repair.