HomeMy WebLinkAboutPW CNT 82-21/CHG OR 1/Sommers Construction CHANGE ORDER NO. 1
TO: SOMMERS CONSTRUCTION CO., INC. DATED: November 19, 1982
141 Sommers Street
Shiocton, Wisconsin 54170
Your present contract with the City of Oshkosh, Contract No. 82-21 S
is hereby amended and changed as follows:
( insert here work and/or materials to be added or eliminated and
the unit and/or lump sum price to be added to or deducted from the
contract. )
TO CORRECT QUANTITIES FROM ESTIMATED TO FINAL MEASUREMENT:
Total Increase $973.30
Total Decrease $ 28.50
Net Increase to Contract $944.80
Rec d -nded : CI- Y OF OSHKOS
�ee�.( `, ,' fie By �R A , ....t
I / l irec�or f 07 is Wor s ity Manager
aac Z1' itC th J
Ap roved and accepted:
(" •
4 , ,L-4-7 ,t72,4.i
Contractor
I certify that provision has been made to pay the liability that
will accrue to the City of Oshkosh, Wisconsin, under the within
Change Order.
?iit040144,.//
Comptroller
Approved as to form:
I0,1n W tJiu -
e55f City Attorney
• CHANGE ORDER #1 - CONTRACT 82-21
ITEM CONTRACT INSTALLED NET DIFFERENCE COST/ DECREASE IN INCREASE IN
NUMBER QUANTITY QUANTITY INCREASE DECREASE UNIT CONTRACT PRICE CONTRACT PRICE
1 . 700 883 183 --- $1.90 --- $347.70
2. 225 268 43 --- $2.30 --- $ 98.90
3. 220 393 173 --- $2.10 --- $363.30
4. 810 1,056 246 --- $0.40 --- $ 98.40
5. 675 677 2 --- $1.00 --- $ 2.00
6. 100 103 3 --- $2.00 --- $ 6.00
7. 75 94 19 --- $3.00 --- $ 57.00
8. 120 117 --- 3 $9.50 $28.50 ---
$28.50 $973.30
NET INCREASE TO CONTRACT $944.80
•