HomeMy WebLinkAboutPW CNT 12-15/CHG OR 1/PTS Contractors DEPARTMENT OF PUBLIC WORKS 215 Church Avenue P.O.Box 1130 (11-110PD Oshkosh,Wisconsin 54903-1130 Ph.(920)236-5065 Fax(920)236-5068 OJHKOJH ON THE WATER January 16, 2014 Mr. Steve Horn PTS Contractors, Inc. 4075 Eaton Road Green Bay, WI 54311-9340 Re: Change Order No. 1 Contract 12-15 Dear Mr. Horn: Enclosed is an executed copy of Change Order No. 1 between the City of Oshkosh and PTS Contractors, Inc. regarding the abovementioned project. If you have any questions,please call our office at (920)236-5065. Sincerely, ir David C. Patek Director of Public Works DCP/tlt,_ Enclosure: Change Order No. 1 cc: Pam Ubrig, City Clerk (w/original) Lynn Lorenson, City Attorney(w/copy) Tara Wendt, Assistant Finance Director(w/copy) File (w/original) I:\Engineering\12-15 San Swr&Wtr Mn Ext-W Snell Rd&Walter St\Project_Information\Contract Info\Change Page 1 of 1 Orders\12-15 Executed CO#1 Ltr 1-16-14.docx TO: PTS Contractors, Inc. CHANGE ORDER# 1 4075 Eaton Road DATED: August 20, 2013 Green Bay,WI 54311-9340 Your present contract with the City of Oshkosh, Contract 12-15, awarded January 8, 2013, is hereby amended and changed as follows: NET DECREASE TO: SECTION I - PAVING -$11,579.65 NET DECREASE TO: SECTION II -STORM SEWER -$1,705.52 NET DECREASE TO: SECTION IV-WATER MAIN -$14,566.65 NET DECREASE TO CONTRACT -$27,851.82 Section I Section II Section IV (Paving) (Storm) (Water) Totals Bid Total $62,790.00 $3,208.00 $469,988.50 $535,986.50 C.O.#1 ($11,579.65) ($1,705.52) ($14,566.65) ($27,851.82) Contract Total $51,210.35 $1,502.48 $455,421.85 $508,134.68 CITY OF OSHKOSH BY: 4;e/ Recommended: w City Man- _, .� at*. Wf1_ • 1 Its. Director of Public Works City C erk pproved and accepted: 0,.11 ontr 4-"MP I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin, under the within Change Order. Comptroller Approve, as to form: 1%0, ,.� rl ► • . ..At • City At or ey CONTRACT:12-16 CHANGE ORDER#1 SECTION I-PAVING ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT PRICE PRICE Pavement removal, Square ^ 100 complete as specified Yards 650 860.40 , 210.40 $1.50 $315.60 Driveway removal, Square 101 complete as specified Feet 2,800 _ 1,573.70 -1,226.30 $0.36 ($441.47) 8"concrete driveway, Square 102 complete as specified Feet 925 0.00 _ -925.00 $4.62 ($4,273.50) Milling mobilization, Lump 103 complete as specified Sum 2 2.00 $513.00 Pavement milling, Square 104 complete as specified Yards 1,750 645.19 -1,104.81 $3.38 ($3,734.26) 105 Asphaltic driveways(with Square 1,850 base),complete as Feet 1,135.72 -714.28 $3.19 ($2,278.55) Overlay,complete as Square 106 specified Yards 1'750 1,505.67 -244.33 $7.69 ($1,878.90) HMA pavement type E-1.0, Square 107 19.0mm,complete as Yards 150 specified 68.74 -81.26 $22.05 ($1,791.78) HMA pavement type E-1.0, Square 108 12.0mm,complete as Yards 600 specified 791.73 191.73 $16.39 $3,142.45 109 Tack coat,complete as Gallons 50 specified 50.00 $3.08 Preparation and foundation 110 for asphalt paving for Lump 1 Walter Street,complete as Sum - 1.00 $863.00 Preparation and foundation 111 for asphalt paving for Lump 1 Omro Road,complete as Sum 1.00 $3,225.00 Sawing,complete as Linear 112 specified Feet 1'500 1,084.91 -415.09 $1.54 ($639.24) Terrace work on Walter Lump 113 Street,complete as Sum 1 1.00 $5,695.00 Terrace work on Omro Lump 114 Road,complete as Sum 1 1.00 $4,845.00 SECTION I-(BID ITEMS 100-114)-SUB-TOTALS $3,458.05 ($16,037.70) NET DECREASE TO: SECTION I ($11,579.65) SECTION II-STORM SEWER ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT PRICE PRICE Furnish and install 12"x 18"storm sewer culvert, Linear 2049 complete as specified Feet 15 9.00 -6.00 $28.00 ($168.00) Page 1 of 5 CONTRACT:12-15 CHANGE ORDER 51 Furnish and install 24" storm sewer culvert, Linear 2061 complete as specified Feet 15 0.00 -15.00 $36.00 ($540.00) Furnish and install 12"x 18"storm sewer culvert endwall,complete as 2305 specified Each 1 0.00 -1.00 $119.00 ($119.00), Furnish and install 24" storm sewer culvert endwall,complete as 2309 specified Each 1 0.00 -1.00 $190.00 ($190.00), Connect to existing storm sewer,complete as 2800 specified Each 2 1.00 -1.00 $61.00 ($61.00) Furnish,install,maintain, and remove Type D inlet protection,complete as 2856 specified Each 5 0.00 -5.00 $91.00 ($455.00) Furnish,install,maintain, and remove 12"diameter sediment logs,complete as Linear 2868 specified Feet 300 262.00 _ -38.00 $4.54 ($172.52) SECTION II-(BID ITEMS 2049-2868)-SUB-TOTALS $0.00 ($1,706.62) NET DECREASE TO: SECTION II ($1,705.52) Page2of5 • CONTRACT:12-15 CHANGE ORDER#1 SECTION IV-WATER MAIN ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN NUMBER DESCRIPTION UNIT CONTRACT CONTRACT QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE PRICE Furnish and install new 6" ductile iron water main with poly wrap,complete as Linear 4020 specified Feet 70 47.00 -23.00 $54.25 ($1,247.75) Furnish and Install new 8" ductile iron water main with poly wrap,complete as Linear 4022 specified Feet 925 919.00 -6.00 $71.66 ($429.96) Furnish and install new 8" ductile iron water main with poly wrap and snap-lok restrained joints,complete Linear 4023 as specified Feet 170 176.00 6.00 $35.15 $210.90 Furnish and install new 12" ductile iron water main with poly wrap,complete as Linear 4026 specified Feet 5 7.00 2.00 _ $47.00 $94.00 Furnish and install new 16" ductile iron water main with poly wrap,complete as Linear 4028 specified Feet 2,800 2,778.50 -21.50 $74.20 ($1,595.30) Furnish and install 1"water service new,complete as Linear 4042 specified Feet 90 49.00 -41.00 $39.00 ($1,599.00) Furnish and install 1" corporation and stop box, 4048 complete as specified Each 4 3.00 -1.00 $300.00 ($300.00) Furnish and install water service clay dams, 4054 complete as specified Each 4 5.00 1.00 $46.00 $46.00 Furnish and install connections to existing 12" water main,complete as 4064 specified Each 1 1.00 $961.00 Furnish and install connections to existing 16" water main,complete as 4066 specified Each 1 1.00 $208.00 Furnish and install 8"x 6" 4110 tee,complete as specified . Each 3 3.00 $356.00 Furnish and install 16"x 6" 4137 tee,complete as specified Each 5 5.00 $1,115.00 Furnish and install 8"11%" bend,complete as 4219 specified Each 2 2.00 $246.00 Furnish and install 16" 11'%°bend,complete as 4222 specified Each 2 _ 2.00 $1,020.00 Page 3 of 6 CONTRACT:12-15 CHANGE ORDER#1 Furnish and install 8"22%° bend,complete as 4228 specified Each 2 2.00 $253.00 Furnish and Install 6"46° bend,complete as 4236 specified Each 16 0.00 -16.00 $193.00 ($3,088.00) Furnish and install 8"45° bend,complete as 4237 specified Each 2 2.00 $257.00 Furnish and install 16"45° bend,complete as 4240 specified Each 4 4.00 $1,107.00 Furnish and install 16"x 12"reducer,complete as 4276 specified Each 1 1.00 $760.00 Furnish and install 6"gate valve,complete as 4401 specified Each 8 8.00 $998.00 Furnish and install 8"gate valve,complete as 4402 specified Each 4 4.00 $1,331.00 Furnish and install 16"gate valve,complete as 4405 specified Each 10 9.00 -1.00 $6,042.00 ($6,042.00) Furnish and install 12"x 8" tapping valve&sleeve, 4447 complete as specified Each 1 1.00 $3,496.00 Furnish and install hydrant, 4500 complete as specified Each 8 8.00 $2,984.00 Furnish and install gradelok for hydrant branches,complete as 4504 specified Each 8 0.00 -8.00 $510.00 ($4,080.00) Jack and bore 18"steel casing pipe,complete as Linear 4700 specified Feet 145 145.00 $297.00 Jack and bore 30"steel casing pipe,complete as Linear 4704 specified Feet 40 40.00 $329.00 SECTION IV-(BID ITEMS 4020-4704)-SUB-TOTALS $360.90 ($18,382.01) ADDITIONAL WORK REQUIRED: C.O.#1 -SECTION IV ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN DESCRIPTION UNIT CONTRACT CONTRACT NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE PRICE Furnish and install 1.25" water service new, Linear 4037 complete as specified Feet 0.00 24.00 24.00 $41.00 $984.00 Furnish and install 1.25" corporation and stop box, 4050 complete as specified Each 0.00 1.00 1.00 $432.00 $432.00 Furnish and Install 2"water service new,complete as Linear 4040 _specified Feet 0.00 19.00 19.00 $83.66 $1,589.54 _ Page 4 of 5 ' CONTRACT:12-15 CHANGE ORDER#1 Furnish and install 2" corporation and stop box, 4054 complete as specified Each 0.00 1.00 1.00 $458.92 $458.92 ADDITIONAL WORK: C.O.#1 (ITEM 4037-4084)-SUB-TOTAL $3,464.46 $0.00 NET DECREASE TO: SECTION IV ($14,566.65) NET INCREASE TO SECTIONS I,II,IV $7,273.41 NET DECREASE TO SECTIONS I,II,IV ($35,125.23) NET INCREASE TO CONTRACT: ($27,851.82) Page 5 of 5