HomeMy WebLinkAboutPW CNT 84-12/CHG OR 1 CHANGE ORDER NO. 1
To: FOUR-WAY CONST. OF WI INC. DATED: March 19, 1985
P.O. Box 133
Berlin, WI 54923
Your present contract with the City of Oshkosh, Contract No. 84-12 ,
is hereby amended and changed as follows:
( insert here work and/or materials to be added or eliminated and
the unit and/or lump sum price to be added to or deducted from the
contract. )
ADD - SANITARY & STORM SEWER WORK AT CONVENTION CENTRE SITE
Total Sanitary Sewer Added by this change order - $13,325.50
Total Storm Sewer added by this change order - $ 5,790.50
TOTAL ADDED TO CONTRACT - $19,116.00
(See attached sheet for breakdown)
Aec• - nded° CI Y OF OS 03H
' /iwilk , BY; g(,/,,Z,-- )
Director o - Public Works City . nager
,1.\ -771,/;,1Q," (). VLUM.,d
City Clerk
Apprgv arid__ cceted
---/
L
-> /
Con _ ac r "j
I certify that provision has been made to pay the liability that
will accrue to the City of Oshkosh, Wisconsin, under the within
Change Order.
t�l .x,,- -tc (1 rid lrtL�`
Comptroller
Appoved as to form:
Lk-(1).Al•C- --V) 114
City Att r ey
CHANGE ORDER #1 - CONTRACT 84-12
UNIL PRICE TOTAL
SANITARY SELO'R
1 . Furnish & install approx 250
lin. ft. 18" sanitary sewer
(6-8 ' depth) , as specified ,
per lin. ft. $49. 45 $12, 362. 50
2. Furnish & install 1 standard
sanitary manhole, each $ 713. 00
3. Abandon two manholes , each 125. 00 $ 250. 00
TOTAL - SANITARY SEWER $13,325. 50
STORM SEWER
1 . Furnish & install approx . 95
lin. ft. 12" RCP storm sewer ,
(6-, ' depth) , per lin. ft. $25. 10 $ 2,384. 50
2. Furnish & install 1 standard
storm manhole, as specified ,
each $ 756. 00
3. Furnish & install 1 box storm
manhole, as specified , each $ 2,650. 00
TOTAL - STORM SEWER $ 5,790. 50
TOTAL ADDED BY THIS CHANGE ORDER $19, 116. 00