CHANGE ORDER NO. 5
TO: FLUOR BROS. CONSTRUCTION CO. DATED: March 18, 1985
203 Otter Avenue
P.O. Box 2326 .
Oshkosh, WI 54903
Your present contract with the City of Oshkosh, Contract No. 84-01
is hereby amended and changed as follows:
( insert here work and/or materials to be added or eliminated and
the unit and/or lump sum price to be added to or deducted from the
contract . )
OSHKOSH LOW LIFT/HIGH SERVICE PUMPING STATION
For a description of the following items in this change order
refer to the following sheet No. 2 .
Item No . 1 $248 . 00
Item No . 2 $ 170 . 00
Item No . 3 $ 139 . 00
Item No. 4 $715 . 00
Item No. 5 $2 , 397 . 00
Item No . 6 $829 . 00
Total Change Order No . 5 $4 , 498 .00
All Items are to be made at No Change in the Contract Time
Original Contract .Amount $ 1 , 393 , 700 . 00
Total Amount of Previous Change Orders To Date 8 , 301 . 00
Previous Adjusted Contract Amount $ 1 , 402 ,001 . 00
Change Order No. 5 Amount 4 , 498 . 00
Total Amount of Current Contract Including C . O . 5 $ 1 , 406 , 499 .00
Recwa.sendbd ; CI Y OF OSHKOSH
By: d.6-.. / /:u19
eirect. Public Works City Manager
City Clerk
Approved_and accepted :
/V,`,
Contractor
I certify that provision has been made to pay the liability that
will accrue to the City of Oshkosh, Wisconsin, under the within
Change Order.
�t 7
Comptroller
Approved aa to form:
City Attorney
Yl s-z.
Change Order No. 5
Sheet No. 2
March 18, 1985
Item No. 1
Extend concrete encasement of the electrical primary entrance conduits an additional
7 '9" south of the north wall of the equipment access room. Encasement with
reinforcement should be the same as that shown for the conduit encasement in the
Low LIft Pipe Gallery.
Item No. 2
Provide 2" diameter galvanized forged eye bolts at each of the four corners on
both of the smaller roof hatches. Eye bolts are to be located as indicated
by the "tick" marks on the corners of the roof hatches in "roof plan 1" on
contract drawing A-2.
iLelu No. 3
Revise the 3 x 3 x 4 perimeter steel angle for the two small removeable roof
hatches from an overall width of 6'-6" to an overall width of 5'-2".
Item No. 4
A. Provide oversize hook lengths on all horizontal reinforcement members at
"T" intersectons @ all interior walls on the low service and high service
tanks. Hook lengths are to be increased from 10-inches to 17-inches
on #5 bars and from 12-inches to 18-inches on #6bars.
B. Provide additional reinforcemnt required due to increase in the size
of the sump pump chamber from 18" in diameter to 30" in diameter.
Item No. 5
Provide additional labor for penetrating the north wall of the existing north
reservoir at the location of the new 30" diamter D.I. main. Wall thickness
found to be 40". As builts indicate a wall thickness of 18".
item No. 6
Provide 2" x 2" x 1/8" structural steel supports for the vertical portions
of the metal decking at the locations shown on the reviewed copies of the
metal decking shop drawings.