HomeMy WebLinkAboutPW CNT 84-01/CHG OR 5 Sheet No. 1 CHANGE ORDER NO. 5 TO: FLUOR BROS. CONSTRUCTION CO. DATED: March 18, 1985 203 Otter Avenue P.O. Box 2326 . Oshkosh, WI 54903 Your present contract with the City of Oshkosh, Contract No. 84-01 is hereby amended and changed as follows: ( insert here work and/or materials to be added or eliminated and the unit and/or lump sum price to be added to or deducted from the contract . ) OSHKOSH LOW LIFT/HIGH SERVICE PUMPING STATION For a description of the following items in this change order refer to the following sheet No. 2 . Item No . 1 $248 . 00 Item No . 2 $ 170 . 00 Item No . 3 $ 139 . 00 Item No. 4 $715 . 00 Item No. 5 $2 , 397 . 00 Item No . 6 $829 . 00 Total Change Order No . 5 $4 , 498 .00 All Items are to be made at No Change in the Contract Time Original Contract .Amount $ 1 , 393 , 700 . 00 Total Amount of Previous Change Orders To Date 8 , 301 . 00 Previous Adjusted Contract Amount $ 1 , 402 ,001 . 00 Change Order No. 5 Amount 4 , 498 . 00 Total Amount of Current Contract Including C . O . 5 $ 1 , 406 , 499 .00 Recwa.sendbd ; CI Y OF OSHKOSH By: d.6-.. / /:u19 eirect. Public Works City Manager City Clerk Approved_and accepted : /V,`, Contractor I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin, under the within Change Order. �t 7 Comptroller Approved aa to form: City Attorney Yl s-z. Change Order No. 5 Sheet No. 2 March 18, 1985 Item No. 1 Extend concrete encasement of the electrical primary entrance conduits an additional 7 '9" south of the north wall of the equipment access room. Encasement with reinforcement should be the same as that shown for the conduit encasement in the Low LIft Pipe Gallery. Item No. 2 Provide 2" diameter galvanized forged eye bolts at each of the four corners on both of the smaller roof hatches. Eye bolts are to be located as indicated by the "tick" marks on the corners of the roof hatches in "roof plan 1" on contract drawing A-2. iLelu No. 3 Revise the 3 x 3 x 4 perimeter steel angle for the two small removeable roof hatches from an overall width of 6'-6" to an overall width of 5'-2". Item No. 4 A. Provide oversize hook lengths on all horizontal reinforcement members at "T" intersectons @ all interior walls on the low service and high service tanks. Hook lengths are to be increased from 10-inches to 17-inches on #5 bars and from 12-inches to 18-inches on #6bars. B. Provide additional reinforcemnt required due to increase in the size of the sump pump chamber from 18" in diameter to 30" in diameter. Item No. 5 Provide additional labor for penetrating the north wall of the existing north reservoir at the location of the new 30" diamter D.I. main. Wall thickness found to be 40". As builts indicate a wall thickness of 18". item No. 6 Provide 2" x 2" x 1/8" structural steel supports for the vertical portions of the metal decking at the locations shown on the reviewed copies of the metal decking shop drawings.