HomeMy WebLinkAboutPW CNT 83-13/CHG OR #1/ Four Way Construction CHANGE ORDER NO. 1
TO: FOUR-WAY CONST. OF WI INC. DATED: October 24, 1984
P.O. Box 133
Berlin, WI 54923.
Your present contract with the City of Oshkosh, Contract No. 83-13
is hereby amended and changed as follows:
( insert here work and/or materials to be added or eliminated and
the unit and/or lump sum price to be added to or deducted from the
contract. ) ADD - TO WATER MAIN
STATE STREET, extra costs associated with
removing unknown concrete foundations
due to slight realignment of main $ 1,650.00
DIVISION STREFT, extra costs involving
relocating main due to gas and telephone
conflicts and extra fittings required to
repair old services and connect to old
main in poor condition $ 4,264.00
PIERCE AVENUE, extra cost to repair storm
sewer and build new storm inlet in existing
line which was in very poor condition and
collapsed during construction $ 1,815.00
ADAMS AVENUE, extra cost for connection work
added since contract bid and repairing
lateral $ 473.00
TOTAL ADDED BY CHANGE ORDER #1 $ 8,202.00
Recomv'. d: CITY 0, OSHKOSH
s /_ r_/_ By:
Director o —?P.lic Wor s City Manager
City Clerk
Aoprov- . and -cceptea:
-000' .e_4% - /".1
Con a�'er /
I certify that provision has 'been made to pay the Liability that
will accrue to the City of Oshkosh, Wisconsin, under the within
Change Order.
Comptroller
Approved as to form:
City Attor ey , c��