December 2, 2013
Mr. Al Dix
Al Dix Concrete
500 Draper Street
Kaukauna, WI 54130
RE: Contract 13-06—Change Order No. 2 (Final)
Dear Mr. Dix:
Enclosed is an executed copy of Change Order No. 2 (Final) between the City of Oshkosh and Al Dix
Concrete regarding the abovementioned project.
If you have any questions, please call our office at (920)236-5065.
Sincerely,
DA-:"9° n ' "
David C. Patek, P.E.
1771
l
Director of Public Works
DCP/tlt
Enclosure: Change Order No. 2 (Final)
cc: Pam Ubrig, City Clerk (w/original)
Lynn Lorenson, City Attorney(w/copy)
Tara Wendt, Assistant Finance Director(w/copy)
File (w/original)
I:\Engineering113-06 Conc Sidewalk(New&Rehab)\Project_Information\Contract Info\Change Orders113-06 Executed Page 1 of 1
CO#2 Ltr 12-2-13.docx
TO: Al Dix Concrete CHANGE ORDER#2 Cf 10L2
500 Draper Street DATED: November 19, 2013
Kaukauna, WI 54130
Your present contract with the City of Oshkosh, Contract No. 13-06, awarded March 26, 2013, is hereby
amended and changed as follows:
NET INCREASE TO: SECTION I - PAVING 37,639.14
NET INCREASE TO: SECTION II - STORM SEWER 0.00
NET INCREASE TO CONTRACT $37,639.14
Section I Section II
(Paving) (Storm) Totals
Bid Total $322,828.50 $650.00 $323,478.50
C.O. #1 $146,600.27 $5,984.49 $152,584.76
Prev.Contract Total $469,428.77 $6,634.49 $476,063.26
C.O. #2 $37,639.14 $0.00 $37,639.14
Contract Total $507,067.91 $6,634.49 $513,702.40
CITY OF OSHKOSH
BY:
Recommended: City Manage
I 0 ADy-)Th
Director of Public Works City Clerk
Ap. •ve• and accepted:
ft(
Contractor
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin,
under the within Change Order.
Comptroller
Approved as t• form: ,141A_ApII■4,
City . I -
CONTRACT: 13-06 CHANGE ORDER#2
SECTION I-PAVING
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE
PRICE
1110 Removing curb and gutter, Linear
complete as specified Feet 200.00 131.00 -69.00 $3.00 ($207.00)
1120 Removing concrete and
asphalt sidewalk and
driveway,complete as Square
specified Feet 62825.00 67,585.85 4,760.85 $0.65 $3,094.55
1210 Borrow excavation, Cubic
complete as specified Yards 5000.00 1,113.15 -3,886.85 $0.15 ($583.03)
1308 7"concrete pavement
removal and replacement,
including sawing, pavement
ties,integral curb and
grading,terracing,and
traffic control,complete as
specified Square
Yards 293.58 397.78 104.20 $43.00 $4,480.60
1318 8"concrete pavement
removal and replacement,
including sawing,pavement
ties, integral curb and
grading,terracing,and
traffic control, complete as
specified Square
Yards 850.00 887.09 37.09 $45.00 $1,669.05
1319 8"concrete pavement
SHES removal and
replacement, including
sawing,pavement ties,
integral curb and grading,
terracing,and traffic
control,complete as Square
specified Yards 30.00 220.74 190.74 $47.00 $8,964.78
1350 Pavement ties,complete
as specified Each 300.00 55.00 -245.00 $6.00 ($1,470.00)
1360 Adjust manholes and inlets,
complete as specified
Each 9.00 9.00 $200.00
1370 Terrace work,complete as Square
specified Yards 4089.66 4,089.66 $4.00
1410 12"radius curb with 6"
CABC and grading, Linear
complete as specified Feet 75.00 35.50 -39.50 $5.25 ($207.38)
1440 30"curb and gutter,7"with
5"CABC and grading,
complete as specified Linear
Feet 200.00 190.00 -10.00 $20.00 ($200.00)
1460 Sidewalk curb,complete as Linear
specified Feet 25.00 0.00 -25.00 $16.00 ($400.00)
1500 4"concrete sidewalk with
3"CABC and grading, Square
complete as specified Feet 64650.00 52,433.67 -12,216.33 $3.29 ($40,191.73)
1502 4"concrete sidewalk with
3"CABC and grading,
water department locations,
complete as specified Square
Feet 6500.00 6,462.83 -37.17 $6.00 ($223.02)
Page 1 of 4
CONTRACT: 13-06 CHANGE ORDER#2
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE
PRICE
1510 6"concrete sidewalk,
driveway,or ramp with 3"
CABC and grading, Square
complete as specified Feet 7436.46 13,096.79 5,660.33 $3.62 $20,490.39
1512 6"concrete sidewalk,
driveway,or ramp with 3"
CABC and grading,water
department locations, Square
complete as specified Feet 2500.00 3,021.66 521.66 $6.30 $3,286.46
1520 8"concrete sidewalk,
driveway,or ramp,with 3"
CABC and grading, Square
complete as specified Feet 150.00 0.00 -150.00 $3.95 ($592.50)
1540 Curb ramp detectable
warning field(natural/non-
painted),complete as Square
specified Feet 200.00 32.00 -168.00 $25.00 ($4,200.00)
1550 No.4 reinforcing rods,
deformed,epoxy-coated, Linear
complete as specified Feet 1609.00 1,609.00 $0.75
1560 Drilled No.4 sidewalk tie
bars,deformed,epoxy-
coated,complete as
specified Each 3700.00 4,275.00 575.00 $1.00 $575.00
1580 Cold weather covering
(sidewalk)-single
visquine,complete as Square
specified Feet 350.00 0.00 -350.00 $0.01 ($3.50)
1582 Cold weather covering
(sidewalk)-double
visquine),complete as Square
specified Feet 200.00 0.00 -200.00 $0.01 ($2.00)
1584 Cold weather covering
(sidewalk)-double
visquine with 6"hay, Square
complete as specified Feet 200.00 0.00 -200.00 $0.01 ($2.00)
1700 Sawing existing pavement, Linear
complete as specified Feet 1100.00 3,666.90 2,566.90 $2.00 $5,133.80
1720 Profile saw cut concrete
curb,complete as specified Linear
Feet 25.00 0.00 -25.00 $30.00 ($750.00)
1800 Base aggregate dense,'/.",
complete as specified Tons 314.27 314.27 $12.00
Page 2 of 4
CONTRACT:13-06 CHANGE ORDER#2
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE
PRICE
1906 4"asphaltic pavement with
10"CABC and grading, Square
complete as specified Yards 1200.00 2,245.73 1,045.73 $30.00 $31,371.90
SECTION I-(BID ITEMS 1106-1906)-SUB-TOTALS $79,066.53 ($49,032.16)
ADDITIONAL WORK REQUIRED: C.O.#2-SECTION I
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE
PRICE
10000 Additional cost to hire Sub-
Contractor to pave asphalt
patches with a paver,due
to large increase in
quantity,complete as Square
specified Yards 521.94 1,668.70 1,146.76 $5.00 $5,733.80
10001 Additional costs for late
season water patches for
8"concrete pavement, Square
complete as specified Yards 0.00 194.03 194.03 $2.00 $388.06
10002 Additional costs for late
season water patches for
7"concrete pavement, Square
complete as specified Yards 0.00 104.20 104.20 $2.00 $208.40
10003 Additional cost for late
season water patches for
cold weather covering, Square
complete as specified Yards 0.00 207.01 207.01 $1.00 $207.01
10004 Additional Traffic Control
and mobilization for
additional late season
concrete patches, complete Lump
as specified Sum 0.00 1.00 1.00 $1,000.00 $1,000.00
10005 Additional costs for late
season water patches for
4"concrete sidewalk, Square
complete as specified Yards 0.00 288.15 288.15 $0.10 $28.82
10006 Additional costs for late
season water patches for
6"concrete sidewalk, Square
complete as specified Yards 0.00 386.80 386.80 _ $0.10 $38.68
ADDITIONAL WORK: C.O.#2-(ITEMS 10000-10006)-SUB-TOTAL $7,604.77 $0.00
NET INCREASE TO: SECTION I $37,639.14