1018 W. SOUTH PARK AVENUE • POST OFFICE BOX 2096 • OSHKOSH,WISCONSIN 54903 • 414/235-3310
6 March 1984
Mr. James Marino
Marino Construction Co. , Inc.
3620 South Clement Avenue
Milwaukee, Wisconsin 53207
RE: File 8133/79005 - Phase II
Restoration and Rehabilitation
The Grand Opera House
City of Oshkosh, Wisconsin
Jim:
We have reviewed your revised cost breakdown for Change
Estimate No. 4 and have come to the following conclusions.
Breakdown - Page 1
1. You omitted 38 sq. ft. of brick work above
the window and added 38 L.F. of stone cap.
There is no additional stone cap as such.
There is some 14 or less feet of stone
(over the entrance and where the stone
covers corbelled brick at each end pier. )
Somehow the credit for omitting the 38 sq.ft.
of brick doesn't show up but your cost out
$48 . 00 material and $480. 00 labor.
We would recommend the $480. 00 labor if
you credited $654 . 00 for the omission of
the brick
Proposed Credit $ 174 . 00
2 . Your charge out $100. 00 material and
$300. 00 labor for removing 3 pipe columns
and 16 L.F. of steel beams. Removal of
one pipe column was included in your
original proposal and the installation
of WF 12x26 which is now omitted.
We could recommend an even exchange
between omitted work and newly required
steel work
Proposed Credit $ 400. 00
Page 2
6 March 1984
Mr. James Marino
RE: File 8133/79005 - Phase II
Restoration and Rehabilitation
The Grand Opera House
City of Oshkosh, Wisconsin
3. Carpentry Work
- Studs: We figure about 80 L.F. more
studs. We could recommend $80. 00 for
materials and $135. 00 for labor
Proposed Credit $ 585.00
- Insulation: We are not aware that
insulation work changed
Proposed Credit $ 48 . 00
- Parapet Blocking : This work did not change
Proposed Credit $ 200. 00
- Omit original 3/4" plywood soffit
Proposed Credit $ 128 . 00
- Finish Labor: Install 160 S.F. of pine
boards on walls and soffits. Install
larger windows and related trim, we
think $720. 00 is adequate. That is
about $3. 00/S.F.
Proposed Credit $1, 689. 00
- Supervision: We maintain that no extra
supervision is involved to provide the
revised building face in lieu of the
original design
Proposed Credit $ 944 . 00
4 . Subcontract Work
- Pine Boards: We think there is only about
160 sq.ft. of pine boards. At $. 50/sq. ft. ,
that is $80. 00 instead of your $1, 009
(subcontractor price)
Proposed Credit $ 929. 00
Page 3
6 March 1984
Mr. James Marino
RE: File 8133/79005 - Phase II
Restoration and Rehabilitation
The Grand Opera House
City of Oshkosh, Wisconsin
- Stone: The only stone added was the stone
over corbelled brick over the entrance
and at the east and west pier recon-
struction at first floor ceiling line
(approximately) . By quantity, the
added stone should be about $300. 00
Proposed Credit $1, 086. 00
- Painting : Extra painting work, boards
plus the added window height should be
no more than $250. 00
Proposed Credit $ 250. 00
5. Sales Tax Credit
1354 x 5% $ 67.70
Proposed Credits $3,491. 70
Profit & Overhead-15% 523 . 76
$4 , 015. 46
1% Bond 40.15
Proposed Total Credit $4, 055. 61
Your Proposal $12, 064.33
Less our Proposed Credit 4, 055. 61
Proposed Change Estimate No. 4 $ 8, 008 .72
Your response prior to the March 13 Meeting is requested.
Sincerely,
YARBRO-KEMPINGER ARCHITECTS, INC.
by
Robert L. Yarbro
RLY/mh
c : Mrs. Lynne Webster
Ms. Catherine Porter
Mark F. Pfaller II
yarbro -
kempinger
architects, inc.
1018 W. SOUTH PARK AVENUE • POST OFFICE BOX 2096 • OSHKOSH, WISCONSIN 54903 • 414/2354310
6 March 1984
Mr. James Marino
Marino Construction Co. , Inc.
3620 South Clement Avenue
Milwaukee, Wisconsin 53207
RE: File 8133/79005 - Phase II
Restoration and Rehabilitation
The Grand Opera House
City of Oshkosh, Wisconsin
Jim:
We have reviewed your cost breakdown for Charge Estimate
No. 7 and have come to the following conclusion.
1. The following items were included in the original
work.
Material Labor Total
- Remove coping $11. 40 $103. 50 $115. 00
- Wood Nailers 48 . 00 216. 00 264 .00
- Bolts 10. 00 30. 00 40. 00
- 3/4 " Plywood 12 . 00 36. 00 48 . 00
Proposed Credit $467. 00
2. Brick
West Side - 460 brick @ $1. 70/brick = $ 782 . 00
East Side - 575 brick @ $1. 70/brick = 977 . 50
$1,759. 50
Your cost of $3, 881. 25 less $1. 759. 50
Proposed Credit $2,122. 25
3. Supervision
21 hours in lieu of 10 hours
Proposed Credit $ 177 . 00
Page 2
6 March 1984
Mr. James Marino
RE: File 8133/79005 - Phase II
Restoration and Rehabilitation
The Grand Opera House
City of Oshkosh, Wisconsin
3. Flashing
23 L.F. X $10.00/L.F. in lieu of $41.30/L.F.
Proposed Credit $ 720. 00
4 . Omit Dumpster and Trucking
Proposed Credit $ 123. 00
5. Adjust Sales Tax $338 . 50 X 5%
Proposed Credit $ 16, 93
Proposed Credit $3, 626.18
Profit & Overhead 543. 93
$4 ,170. 11
1% Bond 41 . 70
Total Proposed Credit $4, 211. 81
Your Proposal $8, 813. 96
Less our Proposed Credit 4,170.11
Proposed Charge Estimate No. 7 $4 , 643. 85
Your response prior to the March 13 Meeting is requested.
Sincerely,
YARBRO-KEMPINGER ARCHITECTS, INC.
by
Robert L. Yarbro
RLY/mh
c : Mrs. Lynne Webster
Ms. Catherine Porter
Mark F. Pfaller II
yarbro kempinger
architects, inc.
-- 1018 W. SOUTH PARK AVENUE • POST OFFICE BOX 2096 • OSHKOSH, WISCONSIN 54903 • 414/235-3310
CHANGE ORDER NO. G-3 OWNER'S COPY
FILE NO. 8133/79005 - Phase II CONTRACTOR'S COPY
DATE 11 April 1984 ARCHITECT'S COPY
The City of Oshkosh
OWNER 215 Church Avenue, Oshkosh, Wisconsin 54901
Marino Construction Company, Inc.
CONTRACTOR 3620 South Clement Avenue, Milwaukee, Wisconsin 53207
General Construction Work, Phase II, Restoration and
CONTRACT FOR Rehabilitation, The Grand Opera House, City of Oshkosh, WI
IT IS HEREBY AGREED THE FOLLOWING CHANGE IN THE WORK SHALL BE COMPLETED IN ACCORDANCE WITH THE
ATTACHED PROPOSAL AND SUBJECT TO TERMS OF THE ORIGINAL CONTRACT DATED September 15, 1983
SEE ATTACHMENT
FOR THE SUM OF (ADD - 0EXJ7 TWELVE THOUSAND STX HTTNITRED FIFTY TWO
AND 57/100THS DOLLARS ($ 12 , 652 . 57
ADD DEDUCT ORIGINAL CONTRACT
476 , 944 . 00
PRIOR TO EXTRA ORDERS
THIS ORDER 30 ,474 . 33 NONE 43 ,126 . 90
THIS ORDER 12 , 652 . 57 NONE CREDIT ORDERS
NONE
TOTAL TO DATE 43 ,126. 90 NET TOTAL TO DATE
520, 070. 90
APPROVED ACCEPTED /
YARBRO-KEMPINGER, ARCHITECTS CITY OF HKOSH, AISCONSIN
PFALL R ERB ASSOCIATES , INC. /
BY 7,....�_ ---'y� .pager
BY ' ' L' ) �f
ACCEP ED erk
7 Approvedias to y6rm,
MARINO CONSTRUCTION COMPANY, INC. BY i - E,_ (le . .rney
I ' = certi "� _ ''e essary
j`
BY -'49412,,.� '� //G 40 44i provisions have been made to pay the
liability that will accrue under this
col tract
irl
CitV l rarnf--ml 1 or
ATTACHMENT
Change Order No. G-3
Marino Construction Co. , Inc
11 April 1984
RE: File 8133/79005-Phase II
Restoration & Rehabilitation
The Grand Opera House
City of Oshkosh, Wisconsin
ITEM NO. 1
Change the Annex south wall work as defined and
required by Architect's Drawings , Sheets A-128
and A-129 , dated 5 December 1983 , copy attached,
and as agreed between the Owner and Contractor
on 10 April 1984 , based on Yarbro-Kempinger/
Pfaller Herbst Associates letter of 6 March 1984 ,
copy attached, on Change Estimate No. 4 . ADD $ 8 ,008 . 72
ITEM NO. 2
Revise Masonry Work, Annex parapet walls as
shown and required by Architect's Drawing
Sheet A-132 , dated 24 January 1984 , copy
attached, and as agreed between the Owner and
Contractor on 10 April 1984 , based on
Yarbro-Kempinger/Pfaller Herbst Associates
letter of 6 March 1984 , copy attached, on
Marino's Change Estimate No. 7 . ADD 4 ,643 . 85
ITEM NO. 3
See Supplementary Conditions , Article 30 ,
Paragraph C and the Contract, Article 3 .
Change the Substantial Completion date
from June 29 , 1984 to August 28, 1984 at
no change in Contract Amount. No Change
NET CONTRACT CHANGE, ADD $12 ,652 .57