NOVEMBER 26, 2013 13-510 RESOLUTION
(CARRIED___7-0___ LOST _______ LAID OVER _______ WITHDRAWN _______)
PURPOSE: APPROVAL OF CHANGE ORDER NO. 2 FOR PUBLIC WORKS
CONTRACT NO. 13-06 WITH AL DIX CONCRETE, INC. FOR
CONCRETE SIDEWALK – NEW AND RECONSTRUCTION
(+$37,639.14)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
AL DIX CONCRETE, INC.
500 Draper Street
Kaukauna, WI 54130
Net Increase to contract: $37,639.14
PURPOSE: See attached Change Order.
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Acct. No. 311-0410-7480-00000 Sidewalk Construction Fund
317-0410-7480-03304 Special Assessments Fund – Sidewalks
541-1867-6401-08673 Water Utility – Maintenance of Mains
541-1867-6401-08675 Water Utility – Maintenance of Services
561-2010-1799-00000 Storm Water Utility – Construction in Progress
OIHKOIH
ON THE WATER MEMORANDUM
TO: Honorable Mayor and Members of the Common Council
FROM: Steven M. Gohde, Assistant Director of Public WorksJ
DATE: November 21, 2013
RE: Change Order No. 2 for Public Works Contract No. 13-06 / Concrete Sidewalk-New &
Reconstruction /Al Dix Concrete, Inc. (+$37,639.14)
BACKGROUND
Change Order No. 2 for Contract 13-06 is scheduled for consideration by the Common Council at the November
26, 2013 meeting. The contract was originally awarded to Al Dix Concrete, Inc. in March of 2013. This final
change order is for final quantities and for additional services provided.
ANALYSIS
Following is a summary of the significant changes to each section of the Capital Improvement Program (CIP)
and the Water Utility Operating Budget:
• CIP-Sidewalk— Based on review of potential city liability, it was determined that correction of defective
private driveway approaches needed to be included in this contract. The scope of work involved with
the private driveway approaches was not known at the time of bidding. The result was a large overage
in Bid Items #1510 (6" concrete driveway) and #1906 (asphalt pavement). Additionally, an asphalt
paving machine was required to be used on the larger driveway repairs. This resulted in an increased
unit price for this work.
• Water Utility Operating Budget/CIP-Street — The Water Department had some water break patches
which needed to be finished prior to the winter season to minimize maintenance. Bid Items #1308,
#1318, #1319, and #1512 (concrete pavement and concrete sidewalk) are actual quantities installed
and are actually only a slight increase over similar work that had been done in the previous year. Due
to this work being completed in the recent cold weather, a surcharge for hot water from the concrete
plants increased the price of the concrete by $2.00 per square yard for concrete pavement and $0.10
per square foot for concrete walk and driveway. This cost increases are reflected in Bid Items #10001
through #10006.
FISCAL IMPACT
Funding for the project is included in the 2013 CIP Sections for Street & Sidewalk Construction. The remaining
funding will be through the Water Utility Operating Budget. The additional services provided for the Sidewalk
Section of the CIP will be billed to the adjoining property owner's per the Municipal Code. CIP Street Section
funding is available from street reconstruction projects coming in under budget.
Budget Section Change Order Amount New Contract Total Funding
CIP-Sidewalk $17,367.28 $380,571.64 $350,000.00
Water Utility Operating/
Street Patch $20,271.86 $129,105.80 (See Note) $129,105.80
CIP-Street $0.00 $4,024.96 $4,024.96
_Total $37,639.14 $513,702.40 $483,130.76
Note: Water Utility Operating Budget contains $774,000 for maintenance of mains and services. The
$129,105.80 needed for repairing concrete pavement is part of this maintenance budget.
RECOMMENDATIONS
I recommend approval of Change Order No. 2 to Contact No. 13-06 in the amount of +$37,639.14 to Al Dix
Concrete, Inc.
Approved:
Mark A. Rohloff
City Manager
SMG/tlt
I:1Engineering113-06 Conc Sidewalk(New&Rehab)1Project Information\CorrespondencelMemo113-06 CO#2 Memo_11-21-13.docx
TO: Al Dix Concrete CHANGE ORDER#2
500 Draper Street DATED: November 19, 2013
Kaukauna, WI 54130
Your present contract with the City of Oshkosh, Contract No. 13-06, awarded March 26, 2013, is hereby
amended and changed as follows:
NET INCREASE TO: SECTION I - PAVING 37,639.14
NET INCREASE TO: SECTION II - STORM SEWER 0.00
NET INCREASE TO CONTRACT $37,639.14
Section I Section II
(Paving) (Storm) Totals
Bid Total $322,828.50 $650.00 $323,478.50
C.O. #1 $146,600.27 $5,984.49 $152,584.76
Prev.Contract Total $469,428.77 $6,634.49 $476,063.26
C.O. #2 $37,639.14 $0.00 $37,639.14
Contract Total $507,067.91 $6,634.49 $513,702.40
CITY OF OSHKOSH
BY:
Recommended: City Manager
Director of Public Works City Clerk
Approved and accepted:
Contractor
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin,
under the within Change Order.
Comptroller
Approved as to form:
City Attorney
CONTRACT: 13-06 CHANGE ORDER#2
SECTION I-PAVING
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE
PRICE
1110 Removing curb and gutter, Linear
complete as specified Feet 200.00 131.00 -69.00 $3.00 ($207.00)
1120 Removing concrete and
asphalt sidewalk and
driveway, complete as Square
specified Feet 62825.00 67,585.85 4,760.85 $0.65 $3,094.55
1210 Borrow excavation, Cubic
complete as specified Yards 5000.00 1,113.15 -3,886.85 $0.15 ($583.03)
1308 7"concrete pavement
removal and replacement,
including sawing,pavement
ties,integral curb and
grading,terracing,and
traffic control,complete as
specified Square
Yards 293.58 397.78 104.20 $43.00 $4,480.60
1318 8"concrete pavement - - -
removal and replacement,
including sawing,pavement
ties, integral curb and
grading,terracing,and
traffic control,complete as
specified Square
Yards 850.00 887.09 37.09 $45.00 $1,669.05
1319 8"concrete pavement
SHES removal and
replacement, including
sawing,pavement ties,
integral curb and grading,
terracing, and traffic
control,complete as Square
specified Yards 30.00 220.74 190.74 $47.00 $8,964.78
1350 Pavement ties,complete - - - -
as specified Each 300.00 55.00 -245.00 $6.00 ($1,470.00)
1360 Adjust manholes and inlets,
complete as specified
_ Each 9.00 9.00 $200.00
1370 Terrace work,complete as Square
specified _ Yards 4089.66 4,089.66 $4.00
1410 12"radius curb with 6" - - -CABC and grading, Linear
complete as specified Feet 75.00 35.50 -39.50 $5.25 ($207.38)
1440 30"curb and gutter, 7"with
5"CABC and grading,
complete as specified Linear
Feet 200.00 190.00 -10.00 $20.00 ($200.00)
1460 Sidewalk curb,complete as Linear
specified Feet 25.00 0.00 -25.00 $16.00 ($400.00)
1500 4"concrete sidewalk with
3"CABC and grading, Square
complete as specified Feet 64650.00 52,433.67 -12,216.33 $3.29 ($40,191.73)
1502 4"concrete sidewalk with
3"CABC and grading,
water department locations,
complete as specified Square
Feet 6500.00 6,462.83 -37.17 $6.00 ($223.02)
Page 1 of 4
CONTRACT:13-06 CHANGE ORDER#2
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT
PRICE
1510 6"concrete sidewalk,
driveway,or ramp with 3"
CABC and grading, Square
complete as specified Feet 7436.46 13,096.79 5,660.33 $3.62 $20,490.39
1512 6"concrete sidewalk,
driveway,or ramp with 3"
CABC and grading,water
department locations, Square
complete as specified Feet 2500.00 3,021.66 521.66 $6.30 $3,286.46
1520 8"concrete sidewalk,
driveway,or ramp,with 3"
CABC and grading, Square
complete as specified Feet 150.00 0.00 -150.00 $3.95 ($592.50)
1540 Curb ramp detectable
warning field(naturaVnon-
painted),complete as Square
specified Feet 200.00 32.00 -168.00 $25.00 ($4,200.00)
1550 No.4 reinforcing rods,
deformed,epoxy-coated, Linear
complete as specified Feet 1609.00_ 1,609.00 $0.75
1560 Drilled No.4 sidewalk tie
bars, deformed,epoxy-
coated,complete as
specified Each 3700.00 _ 4,275.00 575.00 $1.00 $575.00
1580 Cold weather covering
(sidewalk)-single
visquine, complete as Square
specified Feet 350.00 0.00 -350.00 $0.01 ($3.50)
1582 Cold weather covering
(sidewalk)-double
visquine),complete as Square
specified Feet 200.00 0.00 -200.00 $0.01 ($2.00)
1584 Cold weather covering
(sidewalk)-double
visquine with 6"hay, Square
complete as specified Feet 200.00 0.00 -200.00 $0.01 ($2.00)
1700 Sawing existing pavement, Linear
complete as specified Feet 1100.00 3,666.90 2,566.90 $2.00 $5,133.80
1720 Profile saw cut concrete
curb,complete as specified Linear
Feet 25.00 0.00 -25.00 $30.00 ($750.00)
1800 Base aggregate dense,3/4",
complete as specified Tons 314.27 314.27 $12.00
Page 2 of 4
CONTRACT:13-06 CHANGE ORDER#2
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT
PRICE
1906 4"asphaltic pavement with
10"CABC and grading, Square
complete as specified Yards 1200.00 2,245.73 1,045.73 $30.00 $31,371.90
SECTION I-(BID ITEMS 1106-1906)-SUB-TOTALS $79,066.53 ($49,032.16)
ADDITIONAL WORK REQUIRED: C.O.#2-SECTION I
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT
PRICE
10000 Additional cost to hire Sub-
Contractor to pave asphalt
patches with a paver,due
to large increase in
quantity,complete as Square
specified Yards 521.94 1,668.70 1,146.76 $5.00 $5,733.80
10001 Additional costs for late
season water patches for
8"concrete pavement, Square
complete as specified Yards 0.00 194.03 194.03 $2.00 $388.06
10002 Additional costs for late
season water patches for
7"concrete pavement, Square
complete as specified Yards 0.00 104.20 104.20 $2.00 $208.40
10003 Additional cost for late
season water patches for
cold weather covering, Square
complete as specified Yards 0.00 207.01 207.01 $1.00 $207.01
10004 Additional Traffic Control
and mobilization for
additional late season
concrete patches,complete Lump
as specified Sum 0.00 1.00 _ 1.00 $1,000.00 $1,000.00
10005 Additional costs for late
season water patches for
4"concrete sidewalk, Square
complete as specified Yards 0.00 288.15 288.15 $0.10 $28.82
10006 Additional costs for late
season water patches for
6"concrete sidewalk, Square
complete as specified Yards 0.00 386.80 386.80 $0.10 $38.68
ADDITIONAL WORK: C.O.#2-(ITEMS 10000-10006)-SUB-TOTAL $7,604.77 $0.00
NET INCREASE TO: SECTION I $37,639.14
Page 3 of 4