HomeMy WebLinkAboutMarino Construction/CHG OR G-1/Grand Opera House 2/2/1984 yarbro - kernpinger architects, inc. 1018 W. SOUTH PARK AVENUE • POST OFFICE BOX 2096 • OSHKOSH, WISCONSIN 54903 • 414/235-3310 CHANGE ORDER NO. G-1 OWNER'S COPY FILE NO. 8133/79005 - Phase II CONTRACTOR'S COPY DATE 2 February 1984 ARCHITECT'S COPY The City of Oshkosh OWNER 215 Church Avenue, Oshkosh, Wisconsin 54901 Marino Construction Company, Inc. CONTRACTOR 3620 South Clement Avenue, Milwaukee, Wisconsin 53207 General Construction Work, Phase II, Restoration and CONTRACT FOR Rehabilitation, The Grand Opera House, City of Oshkosh, _WI IT IS HEREBY AGREED THE FOLLOWING CHANGE IN THE WORK SHALL BE COMPLETED IN ACCORDANCE WITH THE ATTACHED PROPOSAL AND SUBJECT TO TERMS OF THE ORIGINAL CONTRACT DATED 15 September_1983 SEE ATTACHMENT FOR THE SUM OF (ADD - THREE THOUSAND EIGHT HUNDRED ELEVEN AND 56/100THS DOLLARS ($ 3 , 811. 56 ADD DEDUCT ORIGINAL CONTRACT 476, 944. 00 PRIOR TO THIS ORDER NONE NONE EXTRA ORDERS 3 , 811. 56 THIS ORDER $3 , 811 . 56 NONE CREDIT ORDERS NONE TOTAL TO DATE $3, 811 . 56 NONE NET TOTAL TO DATE 480 , 755. 56 i APPROVED ACCEPTED/ YARBRO- EMPIN ER, AR HITECTS CITY O OSHKOSH, WISCONSIN .ter BY / . �./ _ BYy 1 ^ C.ity_Manager BY 1`r<l i- C `: Clerk ACCEPTED App • . as. to I tam, MARINO c-QNSTRUCTION COMPANY, INC. BY �: _ •rney 3/4,.// I h- -•y certify that the necessary BY �' t/ -` � /r pi' isi ans have hePn made to pay the liability that will accrue under this f colltract .City Comptroller ATTACHMENT Change Order No. G-1 Marino Construction Co. , Inc. 2 February 1984 RE: File 8133/79005 - Phase II Restoration & Rehabilitation The Grand Opera House City of Oshkosh, Wisconsin PER ARCHITECTS REQUEST: Estimate No. 1 dated 14 December 1983 and revision to Estimate No. 1 dated 6 January 1984 , per Drawing A-126, copies attached. This adds a metal door frame into the existing masonry wall between Vestibule D. 09 and Stage Left D.10 ADD $1, 990 . 86 Estimate No. 2 dated 14 December 1983 and revision to Estimate No. 2 dated 6 January 1984 , per Drawing A-127 , copies attached. This provides for subfloor work under mudset ceramic tile in Rooms C. 06 and C. 08 , Men and Women Toilets. The tile will occur in a future phase ADD 1, 820. 70 Estimate No. 3 dated 6 January 1984 , per Drawing A-130, copies attached. This revises the chimney wall, Room D. 02, Alcove West (West Warming Room) to express the fireplace and chimney NO CHANGE NET ADD $3 , 811. 56 since 1908 op W� .�... •-=5,'P m Emu.IJib9IYACriliNIS TIN-�+I dra 4iimm MARINO CONSTRUCTION CO 6. n VMa Milwaukee, K3u07 Incorporated Phone (414) 7444386 GENERAL CONTRACTORS • BUILDERS December 14, 1983 Yarbro-Kempinger Architects, Inc. P.O. Box 2096 Oshkosh, WI. 54903 Attention: Robert Yarbro RE: Grand Opera House Phase II Change Estimate No. 1 Gentlemen: Attached please find our change estimate no. 1 per drawing A-126 which will result in an ADD to our contract in the amount of ONE THOUSAND-NINE HIINDRED • SEE JAN. !P� /9,4/ C 7-TE A Please issue the appropriate change order. Respectfully submitted, MARINO CONSTRUCTION CO. ,INC. (g)///77/ 1.214/ l/4VrJ ames R. Marino Executive Vice-President attach. JRM/mis �rrr� COMMERCIAL • INDUSTRIAL • INSTITUTIONAL BUILDING • Carpentry, Concrete, Masonry ESTIMATE SHEET PAGE NO. OF PAGES JOB NAME CONTRACTOR I ESTIMATE NO. Grand Opera House Phase II Marino Construction Co. ,Inc. 1 1 LOCATION ARCHITECT I DATE Oshkosh, WI. Yarbro-Kempinger, Inc. 12/14/83 ESTIMATOR CHECKED BY I BID DATE W.J. S rin: James R. Marino -_ JOB DESCRIPTION - --------_---- Drawing A-126 FORWARD DESCRIPTION QUANTITY ® MATERIAL LABOR SUBCONTRACT i TOTAL Remove existing masonry 4'X8' 81.00 98'.00 !-1 Too thing 2 .00 0 j 00 ( Patching 7: .00 0.00 Patch threshold concrete fill : .00 ( 8.00 Set frame r_00 910y00 Lintels 6' .00 Supervision 11 0 00 Tools ' 6' .00 I Truckin g 91.00 1 11 Compressor & buster 5' .00 ! I Dumpster 41.00 Block Iron & Supply 85.00 Elmer Kranzusch 40.00 498.00 1,066.00 125.00 I 1 1- 5% Sales tax 24.90 522.90 , II G.C. 's 15% 78.50 L60.00 18.75 60 .40 1,226.00 143.75 1 JI _ ____H__,+ 1 I i I _ - i__. 1 1I I - _ I � I I � , — — — TOTAL COSTS L� I , I n 7 , , i MISC.JOB EXPENSES AMOUNT }I 1 1 1% Bond J1 .71 I , t- -I- I - OVERHEAD "h _111 IPROFIT ° 11 I 11 TOTAL BID SUBMITTED 1 '91).86 since 1908 a _ MARINO CONSTRUCTION CO. w� sin 53207 Incorporated r e (4141 744 ,386 GENERAL CONTRACTORS • BUILDERS January 6, 1984 Yarbro-Kempinger Architects, Inc. P.O. Box 2096 Oshkosh, WI. 54903 Attention: Mr. Robert Yarbro RE: Grand Opera House - Phase II Change Estimate No. 1 Gentlemen: Our request for the additional work shown on drawing A-126 should be $1,990.86 as shown on our breakdown sheet, not $1,971.15 as shown on our letter of 12/14/83. We are sorry for the inconvenience this error may have caused you. Yours very truly, MARINO CONSTRUCTION CO. ,INC. 17(f+-4:.1 W.J. Syring, Project Manager WJS/mis COMMERCIAL • !NOW, r%!t?,:,, e - .i.., r,,E=__, M,,s7:;n.,w - .... Fl---- ; r A , i: 1 1 II; I .• Ai ":i r" A ...) ‘.0 ,---j. iii -5. ■IJ :": 1 'I 1 _1•11._1:. -- •--4 t ' ..-- '?' .,.., ..---. ■-• N,:, - sti -; ;1 1 111, !: 1;,.1 1(.4 \6. .;...'I •sij\ ....\.... 'i tr. U.; % : I\ t.0 • , <T- N ru . 1 ' ''— • • :z ..Z. ci l' CL c'- , i . VlA i .._) u) • c:'S„- I 4-i. --;-." \ 1 f.,1) r-)i INI - I II r,c LI... —.. -.....--..-.. i \I , '-- -------- , I L A 1 _ •... I , iW C... 4 till_i_i _ Ilt( c ,.....: \I\ Li tli tf.2:_i. ----__.° t ..._0 I tv_: -, <7• ________ ,...,.. .,..\ i ..- ' vo ) -1 1--- ..- .. li.: 1--:---1 1 to VsT)) L 1 ul . ' . ) rc _i . 1 1----04 - ) ,._ i i•-• rc w r- 1N-1 ---,_ ,-, i ro' . i- .4! .._ ____—_______ --Nkt- . 0 m r '1:P11111 ..:,1 (1 f) '"fri _.. ., (\i - --- ''- '`i - (0 2 (..) _ C ••-1, _1 —i 6 -..4 / ,..0 • r-- 1 W \- f'' C'') ul •• .• - - i4c■ -- • r- 0 F I — ...___..-- ------ ...1 .• 4': ii---- ) Vt.), t•.,, . el C._.C..- . • "LI cs. • since 1908 -soup t I Ia I,?G O O O Q Mom._ COmO ,n. , , 111 —•-�__ �",P=� ,�L... � �'N51dIWItiT:aia ,p-_ 7+'' :.. Ely 4:47 I lw South Clement Avenue MARINO CONSTRUCTION CO. Mi{waukee, Wisconsin 53207 Incorporated Phone (414) 744 4366 GENERAL CONTRACTORS • BUILDERS December 14, 1983 Yarbro-Kempinger Architects, Inc. P.O. Box 2096 Oshkosh, WI. 54903 Attention: Robert Yarbro RE: Grand Opera Phase II Change Estimate No. 2 Gentlemen: Attached please find our change estimate no. 2 per drawing A-127 which will result in an ADD to our contract in the amount of ONE THOUSAND NINE HUNDRED THREE DOLLARS AND 80/100 CENTS ($1,903.80) . Please issue the appropriate change order. Respectfully submitted, 'RING CONSTRUCTION CO.,INC. James R. Marino Executive Vice-President JRM/mls attach. 71i"•A COMMERCIAL • INDUSTRIAL • INSTITUTIONAL BUILDING • Carpentry, Concrete, Masonry ESTIMATE SHEET . PAGE NO OF PAGES JOB NAME CONTRACTOR ESTIMATE NO. Grand ()•era House Phase II Marino Construction Co. ,Inc. 2 LOCATION A HIT CT DATE Oshkosh, WI. ` arnro-Kempinger Architects, Inc. 12/14/83 ESTIMATOR CHECKED BY BID DATE W.J. Syring James R. Marino J . JOB DESCRIPTION _z -- M M. IIH �• FORWARD DESCRIPTION QUANTITY ® MATERIAL LABOR SUBCONTRACT TOTAL I— _-- -- it Demolition N Ir . �eN�• t .ct r 3/4" P.W. Sub floor 1111111111911911 4/ : .41.11 __ 1 X 3 blocking „ 111111111112111111111111 Redo existing bodging 1 11 11 !U■11 - Supervision , _„■ ' ' .01.11 Trucking 1_10 1 1 Rough hardware 111 I -0 11 ,NM I 021 .81 ► I I 5% sales tax IiIIIIIIIII 1 +-i -f G.C. 's 15% r 1121 ' . t 1' •01.80 II i 1 ll , ■ 1 L 1 NMI I1 jl 111 I Ij� - .� , I -4 II �t —1 1 + *- I -,III I 1 I I 11111 I ' I r -r , ; 1 I } P ij I 1 . , _ - — 1 { -4- — I , - - - 1 II _ im TOTAL COSTS i 1 0 .8C MISC.JOB EXPENSES AMOUNT jill_I Bond 1% 1 12 .00 I i ---tr 1 1 OVERHEAD %�j y_ PROFIT % € TOTAL I BID SUBMITTED j 1 022.8C OR ,0141 FORWARD 1 ,• since 1908 it: it om Tort 7, J_ �flflPf' IIYIfA111IL 1 - y ii MARINO CONSTRUCTION CO. , uk ` ;5€ ,s v5`l2o7 Incorporated Phone (414) 744<=386 GENERAL CONTRACTORS • BUILDERS January 6, 1984 Yarbro-Kempinger Architects, Inc. P.O. Box 2096 Oshkosh, WI. 54903 Attention: Mr. Robert Yarbro RE: Grand Opera House - Phase II Change Estimate No. 2 (Revised) Gentlemen: Per our discussion of January 4, 1984 with Mr. Wallace Syring we are adjusting our cost for Change Estimate No. 2 as follows: Quote of 12/14/83 $1,922.80 Less adjustment on plywood sub flooring (102.10) Revised quotation ADD $1,820.70 See our cost breakdown sheet for the correct amount of our original quotation in lieu of what was sent to your office on 12/14/83. Yours very truly, MARINO CONSTRUCTION CO. ,INC. W. . Syring, P ject Manager WJS/mis [p i .^..OMMERCIAL • s- . ,71118111111111111111111111111111.1.111Millinglimillalimillimilligiallalli. ` Grand Uvera House Phase li Marino, Construction Cp. ,inc. .I. Oshkosh, WI. "tlaro-Kempinver Architects, inc. 12/14/83 / -_ DuAwILlii, A".1.27 ... � ' | | | | \ | | | | \ | \ i | | | - FORWARD _ � | ] \ | | | | | . | | ! | ! ! • - �^om. u^^`x"om�� u�w Demow/pr/ow �uAwxn w m^u.mv _ - -- | i � ''r| [� /^� ' - - `'� ��� ' u « � 4�L� } | \ � `" P.W. Sub -___— _ ______ __ 1 40 4 ^ .4< . _ l U� 2 2 X 3 �lucbiom _ ' - _- ^ ' . — | ' ' --�� — --' ----'- — ------- � -] _ _ _ _ ___ _ !. OO _— 0 .2•-_- _ _ -- ,ugh_hardware 10 00 sale tax 0 20 111118 , . . ..__ ___ _ _. ..._ _ _ ___ .1.4.1T- .... .______ _ . ..____ . . _ , - . ‘, ....,. .. .._. .. ., _ . . . _ _ _____ . . _ 1 El. 1---- I .___ _ .. _ . 1 ill ___iii _ ..... ..,...1.._.. __ . __ _ _ _ . _ _ • . _ .. . .. . _. .. __. _. _ _______ __ __ .. . .. ... .. ....._ .. ._ ._._ _ _ .. ._. _ . ___ ____ _. . _ _ . ___ _ ___ .. .. _ �- II ._ ^~^'"�L ^~^�S'-° � \ �--- _ • MISC. w�w EXPENSES AMOUNT__- I., 0 el ' -_-____-- _ - ___- _ . _ -___-_ __' ` PROFIT - -- ------- ----� ---- - - ' --' uu»�u��/r,wm` ^ ' — ---'-��°�- | 1 TOTAL ��.�����.'^�� 1, 22. - -__-L ,,i ) . ` . -- .r- • -1---- [} 1 / -'`.----, (-14 tsVA( c-- 1:.)T:ts1-» 1 r,t A t,10-1-F- , ' 4 / j< O ---)/ , ■ I—t –T C:21 Af...) t.,`.2 VOla ON/kid.): INA nv c -,.--Li ils vILY-V) -- / (No , \ , 1 t ri-v-,11.-16 1:.,•5 t.,1 (....t!?•(.,41,?,if *V---11-4, C.Dt\le....-k-P-,()CO . ‘7e•E DVT/s..lt... 1 '4_,-4--k E-E-'1" bc k Ll , / / ' t; / L 1.,,--1,7,---- ------, _Tr-.. .,, , _ i , 7 '' ',`- 7.•- - , '- ./ --'. , ± iv " . i ••,./ g / • . 7 f2 ,-,F----- -- --:-----z.,-722--, ----' - • ° --_-----= ' .,--;-4--/--4—.- - -- 1 ( ‹,\A,t\ -7 l' t - ‘ 4.10(k)2' - L .1 ..)1-. ?_.t..CX4 otsiL ../1 C:11,51/.7 0: A i (..,•10 / l' E. Co OaY,e, Nq02- 0 ik / ' --' , r-) zi)LiF21.-(,)(,1-2--,-- \k()r . , ) . -+---()Ft --::.1- -\--0. 1-:::-... ( .7---1 12)EXl 1/710N 4 ,.. , -t 1 • , C-L,L., 4) 1E1, ,6k-TIC)Kl .k ,.:-::7: -.---z,-.7-z__-_•---- -_-,--- .---.-7...7.7.--.. .i. ....., / 10 TC)1 LET F)t\A . 1.-1).'`Tt;'( ,, •,, ' t _ is\ 4 11 tEl 611/)1. 1-) Oi r-ii\N z , , i , 0 ' VIE4.51C)FINTIOki Y41-kibILlTATIO , / jri- Al.)E. Ir. I 1 r ,...- ,...c s womEt4 /2- _ / `I A.v21f'PO VIE NATINCILF), i\A-71( 3/4 - 41. K - ) P -L\LL-C.121 OE ti-lt)d.:.,1-, V.7‘,..1Y....., \t\V _ c/-7--sl -- 51Le Kia 1 5133114)06c; 1 , . `)N551 NO : t.. - I-,?-1 22, / a. 66-4,t...E .• 1(4'. 7,-- 1'-0" /////1',Alairirtralriet40702ParAgre-- - 1///// d since 1908 d e c rF r MARINO CONSTRUCTION CO. v n Milwaukee, �:st:o;�, .32n7 Incorporated Pr;oriu 4414) 744-6-386 GENERAL CONTRACTORS • BUILDERS January 6, 1984 Yarbro-Kempinger Architects, Inc. P.O. Box 2096 Oshkosh, WI. 54903 Attention: Mr. Robert Yarbro RE: Grand Opera House - Phase II Change Estimate No. 3 Gentlemen: After reviewing drawing A-130 we find that their will be "no change" in our contract amount for said drawing. Please issue the appropriate change order. Very truly yours, MARINO CONSTRUCTION CO. ,INC. i'�fL ir... W.J. Syring, Project Manager WJS/mis � ty COMMERCIAL_ • iNnt!STr-,t- 6 - r . , -- � . '1:';a _.- ' r1-16, ® /k -----CD �-V j I I (/ EA-tiff. CP 11\01E1 I I pr.1 Ala, Lo ii I I fLY.1k Li I D.cat I I dt-UN E. -vyEY S 1 �TlF-1Z . / „ ,„ 1 , / ,/ ______ �j P.DA ,,,11=7-1C.A.-5 / Te.■I 1 471 of TO (Q C. e Lc(_.v, \M NIL ftE\t-k- To CH t NA NE.•1 -__7c aL.E : 'J4" - 1'-a" AFe2;=,v V-NemPtt■IUE.R, ARC44 ITELTS , INC.. P1-tAhE IL Pi--i%1-i-t: NERtiT Ayao-tATES, I NI c., RESTORATION ? IAAb(LITTIDN I"1L-E t‘10. 8133 / 14)0°6 INS C1P,g1•p OPCP1 . Roo =-�14.E.E1 IAA. A- 11,0 0,t,TE• I - 5•S'S CYAA YN0514, WIeaLoNrstN,