HomeMy WebLinkAboutPW CNT 85-10/CHG OR 2 CHANGE ORDER NO. 2
TO: ROBERT ALBRIGHT CONST. DATED: July 8, 1985
1633 Brooks Road
Oshkosh, Wisconsin 54901
Your present contract with the City of Oshkosh, Contract No, 85-10 ,
is hereby amended and changed as follows:
( insert here work and/or materials to be added or eliminated and
the unit and/or lump sum price to be added to or deducted from the
contract. )
ADD TO BLDG. ADDNS. & ALTERATIONS TO PARKS, STREET/SANITATION & ELECTRICAL
DEPTS.
SEE ATTACHED ITEMIZED LISTING.
TOTAL ADDED BY CHANGE ORDER #2 $509.00
Recommended : �y
C I OF G�t?�5. ' n
r,
-" Director of Pub is Works City Manager
City Clerk
A ,,roved and acce ted —I--Contras for v'°"°'
I certify that provision has been made to pay the liability that
will accrue to the City of Oshkosh, Wisconsin, under the within
Change Order.
Comptroller
Approved as to forms
_City Attorney ._
CHANGE ORDER #2 - CONTRACT 85-10
Sanitation Garage @ 639 Witzel Avenue
Change 30" diameter gravity vent exhaust to 36"
diameter as required by State . The State won' t
allow the bldg. to be classified as"unoccupied" for
ventilation design, due to the nature of the stored
materials, but has accepted the bldg. as "unoccupied"
for other design considerations .
Cancellation charge for ordered 30" vent $99.00
Additional cost for 36" vent & roof curb $410.00
TOTAL ADDED BY CHANGE ORDER #2 $509.00
•