HomeMy WebLinkAboutPW CNT 85-10/CHG OR 1 CHANGE ORDER NO. 1
TO: ROBERT ALBRIGHT CONST. DATED: June 25, 1985
1633 Brooks Road
Oshkosh, Wisconsin 54901
Your present contract with the City of Oshkosh, Contract No. 85-10 9
is hereby amended and changed as follows:
( insert here work and/or materials to be added or eliminated and
the unit and/or lump sum price to be added to or deducted from the
contract. )
ADD TO BLDG. ADDNS. & ALTERATIONS TO PARKS, STREET/SANITATION & ELECTRICAL
DEPTS.
SEE ATTACHED ITEMIZED LISTING.
TOTAL ADDED BY CHANGE ORDER #1 $34,113.05
TOTAL DEDUCTED BY CHANGE ORDER #1 222.00
NET ADDED BY CHANGE ORDER #1 $33,891 .05
Recommended ;
T7 l .
CI OF OSHKOSH
-\ __(- i/ /s Z B ,
�irecto-J: of=-Public Works City
'Ia ar
City Clerk
Armor.. ved , an.'l acc5 epted`;
i � I
c € �, //
I certify that provision has been made to pay the liability that
will accrue to the City of Oshkosh, Wisconsin, under the within
Change Order .
...� 4,-6..7'�_'ti .ire'✓V .L'L' .._... _,......._._
Comptioller
App owed as to form:
J i Ly A t;t o r.`.e�, _.__�s
CHANGE ORDER #1 - CONTRACT 85-10
Electrical & Sign Dept. alterations @ 926 Dempsey Trail
1. Furnish & install 2 coats of paint (dark color) from
floor to 9' above first floor. ADD $560.00
Sanitation Garage @ 639 Witzel Avenue
1. Provide interior liner panel on all walls ADD $5,400.00
2 . Provide all labor, materials & taxes to connect
the bldg. sanitary sewer line into the existing
city garage sanitary sewer in lieu of the storm
sewer line extending out of the last addition to
the city garage. This change is required by the
Plumbing Inspector. ADD $897.00
Park Dept. Building Addn. @ 805 Witzel Avenue
1. Deepen & modify foundations as necessary to circumvent
the landfill and bear on the clay subgrade. Changes are
to include but not limited to:
A. Addn. excavation & backfill;
B. Dewatering of excavations as required;
C. Addn. concrete & rebar required;
D. Provide foundation walls under all masonry walls;
E . All labor, materials, & taxes . ADD $19,216.05
2. Provide 4" PSK fiberglass wall insulation &
6" PSK roof insulation in lieu of 2" in
room A104. ADD $3,240.00
3. Provide interior metal liner panel on the
exterior walls of room A104. ADD $4,800.00
4. To offset a portion of the cost of change to
Sanitation (2 .) , replace the concrete base for
the exterior oil storage tank w/a concrete saddle
over its ' top and eliminate two hold down straps .
Also eliminate one of magnesium anodes . DEDUCT $222.00
TOTAL ADDED BY THIS CHANGE ORDER $34,113.05
TOTAL DEDUCTED BY THIS CHANGE ORDER - $ 222.00
TOTAL - CHANGE ORDER #1 $33,891 .05
NEW CONTRACT TOTAL INCLUDING CHANGE ORDER `1 . $440,434.05