HomeMy WebLinkAboutMiron Construction/Chg Or G-13/Oshkosh Centre CHANGE Distribution tel: ORDER OWNER ❑ ARCHITECT ❑ AM DOCUMENT C701 CONTRACTOR ❑ l FIELD ❑ OTHER ❑ PROJECT: Oshkosh Centre CHANGE ORDER NUMBER: G-13 (name, address) Oshkosh, WI INITIATION DATE: November 25, 1985 TO (Contractor): ARCHITECT'S PROJECT NO: 1383 EP. G. Mir on Construction Ejl. 806 Valley Road CONTRACT FOR: Gen. Project Work Menasha, WI 54 952 Entire Project I J CONTRACT DATE: December 20, 1984 You are directed to make the following changes in this Contract: 4. Provide and install date stone per City of Oshkosh ' s request. Add $ 343 . 00 5. Rework window frame i n control booth per attached dated 10-18-85. Window had to be shortened because ' • of structural interference. Add 102. 00 6. Delete curb and gutter, walk slab, guardrail and partial asphalt paving around existing pump house to be d - - Change straight curb a long east k, �" ,b_3, . },�1, 1 •ity of Oshkosh standard curb and ` Sgutter . Deduct (1, 964 . 00) e__ 1 ,,,,,,.(, .,,,, ......,,,. ., .., , ,,.,. ,. ,, ,,,,:siorrs q( ` yS TOTAL ADD $ 991. 00 (Proposal attached) ' ,4 ( i Lz ,_. . Not valid until signed by both the Owner and Architect. ut�y� ;o,r �.::r er Signature of the Contractor indicates his agreement herewith, including any adjustment in the Contract Sum or Contract Time. The original (Contract Sum) (6traranteed-Maxri mtm-Ees) was $ 3, 675, 000. 00 . Net change by previously authorized Change Orders $ (484, 159. 37) • The (Contract Sum) (Ctaara4teed Maxirz>;Fxa Lest) prior to this Change Order was $ 3 , 190, 840. 63 - The (Contract Sum) (.C,uarantee.d.das.imilm_Cost) will be (increased) -(dQcrea )-(uac•hat ed) 991. 00 by this Change Order $ 3 191, 831. 63 ra The new (Contract Sum) (Guanteed-Maxifnuat-Go ,t) including this Change Order will be $ . The Contract Time will be (iticreased)-( ceased) (unchanged) by ( 0 ) Days. The Date of Substantial Completion as of the date of this Change Order therefore is March 28, 1986 . Authorized: Reinke , Hansche, Last, Inc. oP..TG. IMsiron Construction The E he City of Oshkosh 8S ENO Tth Main Street ctiu�ACValley Road O l Church Street Address Address Address Oshkosh, WI 54901 Me asha , I 54952 Oshkos- , WI X4901 BY AfC'7 BY .Mr, �} ' 'F M g r. ,gr. , / / �" 6 a✓1.14.� 1_ -- -(,`CE�.2, DATE /.„2/�8f DATE �— ,. �! Donna ( . Serwas,(i tyw er AIA DOCUMENT G701 • CHANGE ORDER • APRIL 1978 EDITION • AIA • © 1978 Date: 0 - ,5 THE AMERICAN INSTITUTE OF ARCHITECTS,1735 NEW YORK AVE., N.W.,WASHINGTON, D.C.20006 G701—19/a Telephone(414)734-4161 P. G . MIRON CONSTRUCTION CO . , INC. P , G CONTRACTORS • CONSTRUCTION MANAGERS • MACHINE ERECTORS • DESIGN SERVICES P.O. Box 962 Appleton, WI 54912 November 13, 1985 Reinke, Hansche, Last, Inc. 805 N. Main Street Oshkosh, Wisconsin 54901 RE: OSHKOSH CENTRE Gentlemen: The following is a list of extras completed for the above captioned project. The breakdowns are as follows: 1) Added handrail. P. G. Miron Labor $ 196.00 Appleton Structural Steel 987.00 Lee's Color Studio 93.00 1,276.00 P. G. Miron Management 191.00 TOTAL $1,467.00 2) Add soffit and furring at Control Booth. Appleton Lathing Corporation $ 682.00 P. G. Miron Management Fee 102.00 TOTAL $ 784.00 3) Add two fire dampers and reroute ductwork through the Elevator Equipment Room. Van Asten Heating & Sheet Metal $ 225.00 P. G. Miron Management Fee 34.00 TOTAL $ 259.00 4) Date Stone. P. G. Miron Labor $ 145.00 G. Reinke & Company 82.50 Bill Dentinger Inc. 71.00 298.50 P. G. Miron Management Fee 44.50 TOTAL $ 343.00 November 13, 1985 RE: OSHKOSH CENTRE 5) Rework window frame in control booth #204. P. G. Miron Labor $ 26.00 Block Iron & Supply 63.00 89.00 P. G. Miron Management Fee 13.00 TOTAL $ 102.00 6) Delete curb & gutter, walk slab, guardrail and partial asphalt paving, add change in straight curb to standard city curb. TOTAL P. G. MIMIC DEDUCT ($1,964.00) CHANGE Distribution to: ORDER OWNER ❑ ARCHITECT ❑ AlA DOCUMENT G701 CONTRACTOR ❑ FIELD ❑ OTHER ❑ PROJECT: Oshkosh Centre CHANGE ORDER NUMBER: G-13 (name, address) Oshkosh, WI INITIATION DATE: November 25, 1985 TO (Contractor): ARCHITECT'S PROJECT NO: 1383 P. G. Miron Construction Co.' CONTRACT FOR: Gen. Project Work 806 Valley Road Entire Project Menasha, WI 5495_ 2 J CONTRACT DATE: December 20, 1984 You are directed to make the following changes in this Contract: 1. Add two handrails from City sidewalk to exterior doors D-47 and D-48 per attached sketch dated 10-18-85. Handrails required per code because sloped walk falls under ramp definition. Add $1, 467 . 00 2. Add soffit and furring at control booth per attached sketch dated 10-18-85. Soffit re- quired due to rerouting of duct because of structural interference. Add 784 . 00 3 . Add two fire dampers and reroute ductwork through elevator equipment room. Duct could not be put in because of structural interference. Duct piercing fire wall requires fire damper. Add 259. 00 l � I rr 4 UUIWI►iT n11111�1 u FIELD VERIFY SPACIN4' oF NEW -- VER7/cAL SUPPORTS NANDRA/ MAIN Sr A1\ PART-IAL S/ rE PL,4l'J SCALE: /18"-/ 1-0" _a"RA010S \-- R/ND SMOOTH OS1-1/KOSH CENTRE PAINT- pR/NER PRaI• /t/a. /3(!33 /cps/AS 4 2 FINISH -COATS CO P£/Nee • /IANSc/IE • LAST /'/Zcb PIPE SIDEWALK Ii iI 11 II jl Ilr _ /NS6RT3 C / LREAOY IN 1 II II II Pi-Ace) 1 L!i 1111 ,END SUPF'OPT MIDDLE' S UAp0/27— SCALE= / �- / O� SCALE - /1': /eon" 4' 4" 2 4?-6'. 46 /- 4,c, t 4 ,-G �,0.'r -I (CF{NJGt FROM Co.-0') _0 II T II I I INCREASE WA . S-+. T}d1CKNESS TO COvc'. I $TRUCTURAI. -A STEF e- SEAM CONTQOL (3 007H I 20 41 - — — — — — . — f - - - - ---! , 0 4OOH PL /- SCALE - /l4„ / !0,. `_� J - - (DRYWALL a 7-//t /O-6 t ctattNS CErLiNc 2 I r 0 RErLEcTE4) CLG. RI-Ad 0 �' Sc ALE: y.9.„. r_a i' i _ i' IC ACT" ,! r_ 0,,t, , DQYwALL 4444 ACT'� , PRINKLL �ACT 4 DRYWALi.. _+' RETURN ii, a w ____u_ $1 II //,4NDR�11e I --- MEZZ F1.R v 1:`v O w o O.S/-/KOS/-/ CAN TI?E 4 11 Pew. AIG. /383 /of/e/61 Ii II 0, lit w` : REINKE• 1.MNscHE - e.-AS-r /NC i 1i 0 0