HomeMy WebLinkAboutMiron Construction Co/Chg Or G-19 CHANGE Distribution to:
ORDER OWNER ❑
ARCHITECT ❑
AIA DOCUMENT G701 CONTRACTOR ❑
FIELD ❑
OTHER ❑
PROJECT: OSHKOSH CENTRE CHANGE ORDER NUMBER: G-19
(name, address) Oshkosh, Wisconsin
INITIATION DATE: January 29, 1986
TO (Contractor):
F G. MIRON CONSTRUCTION CO, INC] ARCHITECT'S PROJECT NO: Proj 1383
806 Valley Road CONTRACT FOR: General Project Work
Menasha, WI 54952 Entire Project
CONTRACT DATE: December 20 , 1986
You are directed to make the following changes in this Contract:
1, Provide and install vinyl base as indicated on room fin'i,sh schedule. ADD $2,357.50
(Vinyl base added to this contract. A/E thought vinyl base was under
carpet contract but original assignment of contracts does indicate vinyl
base to be under General Construction Contract.)
•
(Proposal Attached)
Not valid until signed by hot!) the Owner and Architect.
Signature of the Contractor indicates his agreement herewith, including any adjustment in the Contract Sum or Contract Time.
The original (Contract Sum) ( s`& rt.Ye4XM N-Mq ) was $3,675,000.00
Net change by previously authorized Change Orders $ (477,284.95) •
The (Contract Sum) (GKX>XXI# X51XiXY MICI5 prior to this Change Order was $3,197,715.05 •
The (Contract Sum) (6 r XXaXX i3OXFo€ii will be (increased) (d*XXX )(MXKYrYt.0) 2,357.50
by this Change Order $
The new (Contract Sum) ( A3 iS.ENIUMNXi€rlb1336Xt) including this Change Order will be $3,200,072.55
The Contract Time will be (iriiaWfKWXIi (unchanged) by ( 0 ) Days.
The Date of Substantial Completion as of the date of this Change Order therefore is March 28, 1986
Authorized:
REINKE HANSCHE LAST, INC. P. G. MIRON CONST. CO, INC. CITY OF OSHKOSH
gO "N.0 ain Street t 0 VCal�ley Road OWN I�5 Church ` trf=_et
Address Address Address
Oshkosh, WI 54901 Menasha, WI 54952 Oshk7sh, WI 5.901
ItY
AP(C9:117444"-=-- I;Y
7777-- A. s a 4<,/G/�� 3/ - S26, _- - [�v rx ruPrx y Vii,,
?ag
bonne �'=Ser=,�as �:-�tyC�erk
AIA DOCUMENT 0701 • I i;\',E� o:,� • )1;! �s • • 2/21/86
Ii n Oi •_y C7o1 — ld7d
JAN 2 8 19PR'
Inn Telephone (414)734-4161
:: : P . G . MIRON CONSTRUCTION CO . , INC.
CONTRACTORS • CONSTRUCTION MANAGERS • MACHINE ERECTORS • DESIGN SERVICES
P.O. Box 962 Appleton,WI 54912
January 27, 1986
Reinke, Hansche, Last, Inc.
83.5 N. Main Street
Oshkosh, Wisconsin 54901
RE: OSHKOSH CENTRE
Gentlemen:
We have received a quotation from LFM Floors to furnish and install
the vinyl base throughout the Conference Centre. A breakdown of the
costs is as follows:
LFM Floors $2,050.00
P. G. Miron Management Fee 307.50
TOTAL $2,357.50
Please issue a change order in the above amount at your earliest
convenience. Should you have any questions please feel free to call.
Sincerely,
P. G. MIRON CONSTRUCTION
/ ;
Gregory :A. Kippenhaz ,
President