HomeMy WebLinkAboutPW CNT 84-01/CHG OR #8 Change Oroer Ho. 8 May 15, 1986
Contract No. -@ , Low Lift/High Service Pumping Station
Owner: City of Osnxosh '
C;ontractor: Fluor Bros. Construction Co.
ngineer: Howaro Needles Tammen & Bergendoff
C cent ract: No. 84-01, Low Lift/High Service Pumping St at ion, is hereby
amended and oh nged as follows:
Item No. 1 Move Bop kflow Preverter, Add Increase Cost $2, 573. 00
Drain Piping to Ventilation Units, and
Add a Gate Valve at the Air Release nH.
Item Variable Speed Drives To I nor ease Cost $1, 351. 00
Operate Over Entire 4-20ma Range
Item No. 3 Ado Additional Controls To Increase Cost $4, 697. 00
The New I&C Panel For Existing High
Se Pumps Wos. 5 and 6.
It em • c. 4 AdUi• ionaI Sidewalk Panels Increase Cost $140. 00
Total $8, 761. 00
Origimal A• ou•nt of Contract $1, 393, 700. 00
Total Amount of P'revious Change Orders to Date $50, 080. 00
Pre ouEi Ao`]usted Contract Amount $1, 443, 780. 00
Change Order No. 8 Amount $8, 761. 00
Total Amount of Current Contract Including C. 0. No. 8 $1, 452, 541. 00
_______
RC
^'^' 4ydi/i _____ uy: r���_���������_
Director of Pop ic Works ' City Manager.
Ast7,,,,n4) ' ������__ _--- __
City Clerk
__
/ //��___
Aoproved and f ccept ed
Fluor Bros. Construction Co.
I certify that prov1sion has been made to pay the liability that will
accrue to the City of Oshkosh, Wisconsin, under the within Change Order.
` ~
H Comptroller
--� ------�� --� ---T-�-----
City At torney
-- -